Task Name Duration Start Finish

ARCHITECTURAL AND M&E WORKS 696 days Mon 8/1/22 Fri 11/29/24
Architectural 617 days Mon 8/1/22 Wed 8/28/24
Station Box - BL-1 493 days Thu 9/1/22 Tue 4/30/24
Station Box - BL-2 493 days Sat 10/1/22 Fri 5/31/24
Station Box - BL-3 467 days Sat 10/1/22 Tue 4/30/24
Station Box - BL-4 493 days Sat 10/1/22 Fri 5/31/24
Station Box - BL-5 493 days Thu 9/1/22 Tue 4/30/24
Station Box - BL-6 493 days Sat 10/1/22 Fri 5/31/24
Station Box - BL-7 493 days Sat 10/1/22 Fri 5/31/24
Station Box - BL-8 446 days Thu 9/1/22 Thu 2/29/24
Station Box - BL-9 469 days Thu 9/1/22 Wed 3/27/24
Station Box - BL-10 493 days Thu 9/1/22 Tue 4/30/24
Station Box - BL-11 519 days Thu 9/1/22 Fri 5/31/24
Station Box - BL-12 519 days Thu 9/1/22 Fri 5/31/24
Station Box - BL-13 469 days Thu 9/1/22 Wed 3/27/24
Station Box - BL-14 448 days Mon 8/1/22 Wed 1/31/24
Station Box - BL-15 493 days Thu 9/1/22 Tue 4/30/24
Station Box - BL-16 519 days Thu 9/1/22 Fri 5/31/24
Station Box - BL-17 495 days Mon 8/1/22 Wed 3/27/24
Station Box - BL-18 493 days Thu 9/1/22 Tue 4/30/24
Station Box - BL-19 495 days Mon 8/1/22 Wed 3/27/24
Station Box - BL-20 495 days Mon 8/1/22 Wed 3/27/24
Station Box - BL-21 495 days Mon 8/1/22 Wed 3/27/24
Launching Shaft - LS6 221 days Sat 9/2/23 Fri 5/31/24
Entrance & Shaft 261 days Tue 10/10/23 Wed 8/28/24

Escape Stair 8 & Utility Shaft L (BL 1) 171 days Tue 10/10/23 Fri 5/10/24
Exhaust, Ducting & Fresh Air Shaft B
(BL 19-20) 195 days Tue 10/17/23 Sat 6/15/24

Escape Stair 1 & Utility Shaft E (BL 1) 170 days Thu 10/26/23 Sat 5/25/24

Escape Stair 3 & Utility Shaft G (BL 8) 170 days Thu 10/26/23 Sat 5/25/24

Exhaust & Fresh Air Shaft A (LS6-BL1) 195 days Sat 11/4/23 Thu 7/4/24
Entrance-02 A (BL8-9) 195 days Wed 11/8/23 Mon 7/8/24
Entrance-02 B (BL15-16) 195 days Wed 11/8/23 Mon 7/8/24
Escape Stair 5 & Utility Shaft I (BL 20-
21) 147 days Mon 12/4/23 Tue 6/4/24

Escape Stair 6 & Utility Shaft J (BL 17) 171 days Sat 12/23/23 Tue 7/23/24

Escape Stair 2 & Utility Shaft F (BL 4-5) 174 days Thu 1/18/24 Sat 8/17/24
Escape Stair 7 & Utility Shaft K (BL 4-5) 172 days Sat 1/27/24 Tue 8/27/24
Escape Stair 4 & Utility Shaft H (BL 18-
19) 147 days Wed 2/28/24 Wed 8/28/24
Shaft A & B (LS6-2) 73 days Fri 3/1/24 Fri 5/31/24
Shaft C & D (BL20) 73 days Fri 3/1/24 Fri 5/31/24
Access Shaft E (BL16-17) 73 days Fri 3/1/24 Fri 5/31/24
Lift Shaft G (BL8-9) 73 days Fri 3/1/24 Fri 5/31/24
Ducting & Utility Shaft H (BL1) 73 days Fri 3/1/24 Fri 5/31/24
M&E Works 526 days Mon 8/15/22 Thu 5/23/24
Station Box - BL-1 470 days Thu 9/15/22 Wed 4/17/24
Station Box - BL-2 470 days Sat 10/15/22 Sat 5/18/24
Station Box - BL-3 444 days Sat 10/15/22 Wed 4/17/24
Station Box - BL-4 470 days Sat 10/15/22 Sat 5/18/24
Station Box - BL-5 470 days Thu 9/15/22 Wed 4/17/24
Station Box - BL-6 470 days Sat 10/15/22 Sat 5/18/24
Station Box - BL-7 470 days Sat 10/15/22 Sat 5/18/24
Station Box - BL-8 423 days Thu 9/15/22 Fri 2/16/24
Station Box - BL-9 446 days Thu 9/15/22 Thu 3/14/24
Station Box - BL-10 470 days Thu 9/15/22 Wed 4/17/24
Station Box - BL-11 496 days Thu 9/15/22 Sat 5/18/24
Station Box - BL-12 496 days Thu 9/15/22 Sat 5/18/24
Station Box - BL-13 446 days Thu 9/15/22 Thu 3/14/24
Station Box - BL-14 425 days Mon 8/15/22 Thu 1/18/24
Station Box - BL-15 470 days Thu 9/15/22 Wed 4/17/24
Station Box - BL-16 496 days Thu 9/15/22 Sat 5/18/24
Station Box - BL-17 472 days Mon 8/15/22 Thu 3/14/24
Station Box - BL-18 470 days Thu 9/15/22 Wed 4/17/24
Station Box - BL-19 472 days Mon 8/15/22 Thu 3/14/24
Station Box - BL-20 472 days Mon 8/15/22 Thu 3/14/24
Station Box - BL-21 472 days Mon 8/15/22 Thu 3/14/24
Launching Shaft - LS6 202 days Sat 9/16/23 Thu 5/23/24
Entrance & Shaft 241 days Tue 10/24/23 Fri 8/16/24
Escape Stair 8 & Utility Shaft L (BL 1) 151 days Tue 10/24/23 Tue 4/30/24
Exhaust, Ducting & Fresh Air Shaft B (BL
19-20) 175 days Tue 10/31/23 Wed 6/5/24
Escape Stair 1 & Utility Shaft E (BL 1) 150 days Fri 11/10/23 Thu 5/16/24
Escape Stair 3 & Utility Shaft G (BL 8) 150 days Fri 11/10/23 Thu 5/16/24

Exhaust & Fresh Air Shaft A (LS6-BL1) 175 days Sat 11/18/23 Tue 6/25/24
Entrance-02 A (BL8-9) 175 days Wed 11/22/23 Fri 6/28/24
Entrance-02 B (BL15-16) 175 days Wed 11/22/23 Fri 6/28/24

Escape Stair 5 & Utility Shaft I (BL 20-21) 128 days Mon 12/18/23 Sat 5/25/24
Escape Stair 6 & Utility Shaft J (BL 17) 149 days Fri 1/12/24 Sat 7/13/24

Escape Stair 2 & Utility Shaft F (BL 4-5) 154 days Thu 2/1/24 Thu 8/8/24

Escape Stair 7 & Utility Shaft K (BL 4-5) 152 days Mon 2/12/24 Thu 8/15/24

Escape Stair 4 & Utility Shaft H (BL 18-19) 127 days Wed 3/13/24 Fri 8/16/24
Shaft A & B (LS6-2) 53 days Fri 3/15/24 Wed 5/22/24
Shaft C & D (BL20) 53 days Fri 3/15/24 Wed 5/22/24
Access Shaft E (BL16-17) 53 days Fri 3/15/24 Wed 5/22/24
Lift Shaft G (BL8-9) 53 days Fri 3/15/24 Wed 5/22/24
Ducting & Utility Shaft H (BL1) 53 days Fri 3/15/24 Wed 5/22/24
Testing & Commissioning (Station Box, LS2
& LS3) 151 days Sat 6/1/24 Fri 11/29/24