1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING W/ PROPOSED ADDITIONAL FLOOR

H.V. dela Costa St., Client: PLDT


Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: - Date: 07/27/20 Date:

3D MODELS OF CRITICAL FOOTINGS

* 3 STOREY MODEL

CF2

F1
CF1

* 4 STOREY MODEL

F1 CF1 CF2
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING W/ PROPOSED ADDITIONAL FLOOR
H.V. dela Costa St., Client: PLDT
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: - Date: 07/27/20 Date:

FOOTING F1 DETAIL
ORIGINAL DESIGN
L = 1600 m (Length)
W = 1600 m (Width)
t = 400 mm (Thickness)
Øm = 16 mm (Diameter of Rebars)
nL = 10 pcs (No. of Rebars along Length)
nW = 10 pcs (No. of Rebars along Width)
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING W/ PROPOSED ADDITIONAL FLOOR
H.V. dela Costa St., Client: PLDT
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: - Date: 07/27/20 Date:

FOOTING CF1 DETAIL


ORIGINAL DESIGN
L = 1750 m (Length)
W = 1750 m (Width)
t = 450 mm (Thickness)
Øm = 16 mm (Diameter of Rebars)
nL = 11 pcs (No. of Rebars along Length)
nW = 11 pcs (No. of Rebars along Width)
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING W/ PROPOSED ADDITIONAL FLOOR
H.V. dela Costa St., Client: PLDT
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: - Date: 07/27/20 Date:

FOOTING CF2 DETAIL


ORIGINAL DESIGN
L = 1750 m (Length)
W = 1750 m (Width)
t = 450 mm (Thickness)
Øm = 16 mm (Diameter of Rebars)
nL = 11 pcs (No. of Rebars along Length)
nW = 11 pcs (No. of Rebars along Width)
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING W/ PROPOSED ADDITIONAL FLOOR
H.V. dela Costa St., Client: PLDT
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: - Date: 07/30/20 Date:

TABLE 1: INVESTIGATION SUMMARY FOR CENTER COLUMN FOOTING

Safety Factor
for the
Options Loads Original Size design to be
REMARKS SETTLEMENT CHECK
adequate

Pdl 264 kN Length 1600 mm Settlement 14mm


3
STOREY
Pll 275 kN Width 1600 mm 2.1 SAFE Allowable 21mm
Peq 50 kN Thick 400 mm Remark OK
Pdl 391 kN Length 1600 mm Settlement 21mm
4 NOT
STOREY
Pll 413 kN Width 1600 mm 1.4 Allowable 21mm
SAFE
Peq 74 kN Thick 400 mm Remark OK

TABLE 2: DESIGN SUMMARY

Adjustment Size if Safety Factor is:


Options Dimension
SF = 3 SF = 2.5 SF = 2
Length 1900 mm 1750 mm
Width 1900 mm 1750 mm
3 SAME AS
Thick 400 mm 400 mm
STOREY ORIGINAL
No. of Rebar Along Length 12 - 16mmdia 12 - 16mmdia
No. of Rebar Along Width 12 - 16mmdia 12 - 16mmdia
Length 2350 mm 2150 mm 1900 mm
Width 2350 mm 2150 mm 1900 mm
4
Thick 400 mm 400 mm 400 mm
STOREY
No. of Rebar Along Length 13 - 16mmdia 12 - 16mmdia 12 - 16mmdia
No. of Rebar Along Width 13 - 16mmdia 12 - 16mmdia 12 - 16mmdia

CONCLUSION

Without the additional floor, the Foundation of 3 Storey


Steel Parking is adequate if we use a Safety Factor of 2,
which is allowed by the code.
But for the proposed additional floor, there will be a
necessary retroffiting for the foundation to be safe based on
NSCP 2015 code.
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING W/ PROPOSED ADDITIONAL FLOOR
H.V. dela Costa St., Client: PLDT
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: - Date: 07/30/20 Date:

TABLE 3: INVESTIGATION SUMMARY FOR EDGE COLUMN FOOTING

Safety Factor
for the
Options Loads Original Size design to be
REMARKS SETTLEMENT CHECK
adequate

Pdl 159 kN Length 1750 mm Settlement 8mm


3
STOREY
Pll 97 kN Width 1750 mm 3 SAFE Allowable 21mm
Peq 28 kN Thick 450 mm Remark OK
Pdl 229 kN Length 1750 mm Settlement 12mm
4
STOREY
Pll 146 kN Width 1750 mm 3 SAFE Allowable 21mm
Peq 40 kN Thick 450 mm Remark OK

TABLE 4: DESIGN SUMMARY

Adjustment Size if Safety Factor is:


Options Dimension
SF = 3 SF = 2.5 SF = 2
Length
Width
3 SAME AS SAME AS SAME AS
Thick
STOREY ORIGINAL ORIGINAL ORIGINAL
No. of Rebar Along Length
No. of Rebar Along Width
Length
Width
4 SAME AS SAME AS SAME AS
Thick
STOREY ORIGINAL ORIGINAL ORIGINAL
No. of Rebar Along Length
No. of Rebar Along Width

CONCLUSION

As seen in the tables with or without additional floor,


or even adjusting the safety factor. It is safe to say that
there won't be any retrofitting for this foundation.
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING W/ PROPOSED ADDITIONAL FLOOR
H.V. dela Costa St., Client: PLDT
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: - Date: 07/30/20 Date:

TABLE 5: INVESTIGATION SUMMARY FOR CORNER COLUMN FOOTING

Safety Factor
for the
Options Loads Original Size design to be
REMARKS SETTLEMENT CHECK
adequate

Pdl 93 kN Length 1750 mm Settlement 9mm


3
STOREY
Pll 49 kN Width 1750 mm 3 SAFE Allowable 21mm
Peq 16 kN Thick 450 mm Remark OK
Pdl 130 kN Length 1750 mm Settlement 13mm
4
STOREY
Pll 73 kN Width 1750 mm 3 SAFE Allowable 21mm
Peq 22 kN Thick 450 mm Remark OK

TABLE 6: DESIGN SUMMARY

Adjustment Size if Safety Factor is:


Options Dimension
SF = 3 SF = 2.5 SF = 2
Length
Width
3 SAME AS SAME AS SAME AS
Thick
STOREY ORIGINAL ORIGINAL ORIGINAL
No. of Rebar Along Length
No. of Rebar Along Width
Length
Width
4 SAME AS SAME AS SAME AS
Thick
STOREY ORIGINAL ORIGINAL ORIGINAL
No. of Rebar Along Length
No. of Rebar Along Width

CONCLUSION

As seen in the tables with or without additional floor,


or even adjusting the safety factor. It is safe to say that
there won't be any retrofitting for this foundation.
1009 Cityland 10 Tower 2Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: - Date: 07/27/20 Date:
DESIGN OF FOOTING : SYMBOLS & NOTATIONS, and LOAD COMBINATION

Material Properties:
f'c = Specified compressive strength of concrete, Mpa
fy = Specified yield strength of non-prestressed reinforcement, Mpa
λ = Shear Modification Factor for Light Weight Concrete

Soil Properties:
SBCA = Soil Bearing Capacity on laboratory test results
SF = Safety Factor
SBC = Soil Bearing Capacity to be use on Design

Axial Loads (Service Condition):


PDL = Axial Load based on DeadLoads only
PLL = Axial Load based on Liveloads only
PEQ = Axial Load based on Earthquake only
PWL = Axial Load based on Windload only

Column Dimension:
X = Column Dimension along Length of Footing
Y = Column Dimension along Width of Footing
Loc = Center

}
Location
Edge of Column
Corner

Footing Parameters:
Øm = Rebar Diameter to be Use
L = Length (Longer Dimension of Footing)
W = Width (Shorter Dimension of Footing)
t = Thickness of Footing
nL = quantity of rebar along side "L"
nW = quantity of rebar along side "W"

NSCP REQUIREMENTS
ρ = Reliability/Redundancy Factor, NSCP 208-3
Ca = Seismic Coefficient, NSCP table 208.7
I = Importance Factor, NSCP table 208.1

SERVICE LOAD COMBINATIONS ULTIMATE LOAD COMBINATIONS


BASIC LOAD COMBINATION LC1 = 1.4PDL
LC1 = PDL + PLL LC2 = 1.2PDL + 1.6PLL
LC2 = PDL + 0.6PWL LC3 = 1.2PDL + PLL + PWL
LC3 = PDL + PEQ/1.4 LC4 = (1.2+0.5CaI)*PDL + PLL + PEQ
ALTERNATE BASIC LOAD COMBINATION
LC4 = 0.75 ( PDL + PLL + 0.6PWL )
LC5 = 0.75 ( PDL + PLL + PEQ/1.4 )

DESIGN SYMBOLS
Areqd = Area Required dX = Effective Depth along specified Side
Aprov = Area Provided fs = Elastic Steel Stress
a = Area of Punching Failure L' = Distance of Footing End to Column @ L
A = Area of Footing Mn = Nominal Moment Capacity
AsX = Area of Rebars along specified Side Mu = Ultimate Moment to be Resist
Ag = Concrete Area perpendicular to Rebar PS = Maximum Service Load Combination
αs = Column Location Factor PU = Maximum Ultimate Load Combination
bo = Perimeter of Punching Failure φ = 0.75 for shear, 0.65-0.9 for flexure
bW = Base width perpendicular to Rebar qu = Soil Uplift Pressure
βR = Ratio of Column Length to Width ρW = Steel Ratio to Concrete Area
βW = Whitneys Constant Vc = Reinforced Concrete Shear Strength
c = Neutral Axis to Extreme Fiber Vu = Ultimate Shear Load
D/C = Demand-Capacity Ratio W' = Distance of Footing End to Column @ W
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: - Date: 07/27/20 Date:
DESIGN OF FOOTING : FORMULAS

CHECK FOOTING DIMENSION


TO SATISFY : Areqd ≤ Aprov
Areqd = Ps / SBC
Aprov = LW

CHECK FOR SHEAR ALONG SIDE "L"


TO SATISFY : Vu ≤ φVc WHERE:
FORMULAS qu = Pu / Aprov
Vu = quL(W' - dW) W' = 0.5 ( W - Y)
Vc = (0.16λ√f'c + 17ρwVudW/Mu)bWdW dW = t - 75mm - 3*Øm/2

}
Least of
= (0.16λ√f'c + 17ρw)bWdW the 3 ρw = AsW / bwdW
= 0.29λ√f'c bwd bw = L
2
AsW = nWπØm / 4
CHECK FOR SHEAR ALONG SIDE "W"
TO SATISFY : Vu ≤ φVc WHERE:
FORMULAS qu = Pu / Aprov
Vu = quW(L' - dL) L' = 0.5 ( L - X )
Vc = (0.16λ√f'c + 17ρwVudL/Mu)bwdL dL = t - 75mm - Øm/2

}
Least of
= (0.16λ√f'c + 17ρw)bwdL the 3 ρw = AsL / bwdL
= 0.29λ√f'c bwd bw = W
AsL = nLπØm2 / 4
CHECK FOR PUNCHING
TO SATISFY : Vu ≤ φVc WHERE:
FORMULAS qu = Pu / Aprov
Vu = qu(A - a) A = LW
Vc = 0.33λ√f'c bodmin a = ( Y + dL ) ( X + dW )

}
Least of
= 0.17(1+2/β)λ√f'c bodmin the 3 bo = 2 ( Y + dL + X + dW )
= 0.083(2+αsd/bo)λ√f'c bodmin βR = X/Y or Y/X whichever is Larger
αs = 40 for Center Column
30 for Edge Column
20 for Corner Column
CHECK FOR MOMENT (REBAR ALONG "W")
TO SATISFY : Mu ≤ φMn WHERE:
As ≤ As,min qu = Pu / Aprov
FORMULAS W' = 0.5 ( W - Y )
Mu = quLW'(W'/2) βW = 0.85 > 0.85*0.05(f'c-28)/7 > 0.65
Mn = 0.85f'cβc(dW-βc/2) c = 600dW/(600+fs)
As = nWπØm2 / 4 Ag = Lt
As,min = 0.002Ag if fy<420 bw = L
= 0.0014Ag if fy≥420
= 0.756Ag/fy if fy≥420
= 0.25bwd√f'c / fy
= 1.4bwd / fy }
To be disregard
if 3*Mu ≤ φMn

CHECK FOR MOMENT (REBAR ALONG "L")


TO SATISFY : Mu ≤ φMn WHERE:
As ≤ As,min qu = Pu / Aprov
FORMULAS L' = 0.5 ( L - X )
Mu = quWL'(L'/2) βW = 0.85 > 0.85*0.05(f'c-28)/7 > 0.65
Mn = 0.85f'cβc(dL-βc/2) c = 600dL/(600+fs)
As = nLπØm2 / 4 Ag = Wt
As,min = 0.002Ag if fy<420 bw = W
= 0.0014Ag if fy≥420
= 0.756Ag/fy if fy≥420
= 0.25bwd√f'c / fy
= 1.4bwd / fy
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 3s-org Date: 07/27/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1600
Material Properties:
f'c = 20.7 MPa
1400
fy = 414 MPa
λ = 1 1200

Soil Bearing Capacity 1000


SBCA = 450 kPa

WIDTH
SF = 3 800

SBC = 150 kPa


600

Axial Loads (Service Condition): 400


PDL = 264 kN
PLL = 275 kN 200
PEQ = 50 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500

Footing Parameters: Column Dimension:


t = 400 mm Loc = CENTER
L = 1600 mm dL = 306.00 mm Y = 500 mm L' = 625.00 mm
W = 1600 mm dW = 322.00 mm X = 350 mm W' = 550.00 mm
Øm = 16 mm
2
nL = 10 pcs AsL = 2010.62 mm NSCP REQUIREMENTS
s = 160.44 mm ≤450 ∴OKAY ρ = 1
nW = 10 pcs AsW = 2010.62 mm2 Ca = 0.5
s = 160.44 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 539.00 kN
LC1 = 539.00 kN Areqd = 3.59 m2
LC2 = 264.00 kN Aprov = 2.56 m2
LC3 = 299.71 kN D/C = 1.40
ALTERNATE BASIC LOAD COMBINATION ∴ NOT SAFE
LC4 = 404.25 kN
LC5 = 431.04 kN PUNCHING SHEAR CHECK
Vu = 596.68 kN
ULTIMATE LOAD COMBINATIONS Vc = 1358.08 kN ∴ φVc=1018.56 kN
LC1 = 369.60 kN = 2698.52 kN
LC2 = 756.80 kN ∴ qu=295.63 kPa = 2097.53 kN
LC3 = 591.80 kN D/C = 0.29
LC4 = 707.80 kN ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 107.84 kN Mu = 71.54 β = 0.85
Vc = 391.63 kN ∴ φVc=293.73 kN fs = 4953.99 As = 2010.62
= 409.22 kN c = 34.79 Asmin = 1280 OKAY
= 679.77 kN Mn = 255.73
D/C = 0.21 φ = 0.90 D/C = 0.31
∴ SAFE φMn = 230.15 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 150.89 kN Mu = 92.38 β = 0.85
Vc = 373.49 kN ∴ φVc=280.12 kN fs = 4678.016 As = 2010.62
= 390.59 kN c = 34.79 Asmin 1655.652 OKAY
= 645.99 kN Mn = 242.41
D/C = 0.31 φ = 0.90 D/C = 0.42
∴ SAFE φMn = 218.17 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 3s-org' Date: 07/27/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1600
Material Properties:
f'c = 20.7 MPa
1400
fy = 414 MPa
λ = 1 1200

Soil Bearing Capacity 1000


SBCA = 450 kPa

WIDTH
SF = 2 800

SBC = 225 kPa


600

Axial Loads (Service Condition): 400


PDL = 264 kN
PLL = 275 kN 200
PEQ = 50 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500

Footing Parameters: Column Dimension:


t = 400 mm Loc = CENTER
L = 1600 mm dL = 306.00 mm Y = 500 mm L' = 625.00 mm
W = 1600 mm dW = 322.00 mm X = 350 mm W' = 550.00 mm
Øm = 16 mm
2
nL = 10 pcs AsL = 2010.62 mm NSCP REQUIREMENTS
s = 160.44 mm ≤450 ∴OKAY ρ = 1
nW = 10 pcs AsW = 2010.62 mm2 Ca = 0.5
s = 160.44 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 539.00 kN
LC1 = 539.00 kN Areqd = 2.40 m2
LC2 = 264.00 kN Aprov = 2.56 m2
LC3 = 299.71 kN D/C = 0.94
ALTERNATE BASIC LOAD COMBINATION ∴ SAFE
LC4 = 404.25 kN
LC5 = 431.04 kN PUNCHING SHEAR CHECK
Vu = 596.68 kN
ULTIMATE LOAD COMBINATIONS Vc = 1358.08 kN ∴ φVc=1018.56 kN
LC1 = 369.60 kN = 2698.52 kN
LC2 = 756.80 kN ∴ qu=295.63 kPa = 2097.53 kN
LC3 = 591.80 kN D/C = 0.29
LC4 = 707.80 kN ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 107.84 kN Mu = 71.54 β = 0.85
Vc = 391.63 kN ∴ φVc=293.73 kN fs = 4953.99 As = 2010.62
= 409.22 kN c = 34.79 Asmin = 1280 OKAY
= 679.77 kN Mn = 255.73
D/C = 0.21 φ = 0.90 D/C = 0.31
∴ SAFE φMn = 230.15 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 150.89 kN Mu = 92.38 β = 0.85
Vc = 373.49 kN ∴ φVc=280.12 kN fs = 4678.016 As = 2010.62
= 390.59 kN c = 34.79 Asmin 1655.652 OKAY
= 645.99 kN Mn = 242.41
D/C = 0.31 φ = 0.90 D/C = 0.42
∴ SAFE φMn = 218.17 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 4s-org Date: 07/27/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1600
Material Properties:
f'c = 20.7 MPa
1400
fy = 414 MPa
λ = 1 1200

Soil Bearing Capacity 1000


SBCA = 450 kPa

WIDTH
SF = 3 800

SBC = 150 kPa


600

Axial Loads (Service Condition): 400


PDL = 391 kN
PLL = 413 kN 200
PEQ = 74 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500

Footing Parameters: Column Dimension:


t = 400 mm Loc = CENTER
L = 1600 mm dL = 306.00 mm Y = 500 mm L' = 625.00 mm
W = 1600 mm dW = 322.00 mm X = 350 mm W' = 550.00 mm
Øm = 16 mm
2
nL = 10 pcs AsL = 2010.62 mm NSCP REQUIREMENTS
s = 160.44 mm ≤450 ∴OKAY ρ = 1
nW = 10 pcs AsW = 2010.62 mm2 Ca = 0.5
s = 160.44 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 804.00 kN
LC1 = 804.00 kN Areqd = 5.36 m2
LC2 = 391.00 kN Aprov = 2.56 m2
LC3 = 443.86 kN D/C = 2.09
ALTERNATE BASIC LOAD COMBINATION ∴ NOT SAFE
LC4 = 603.00 kN
LC5 = 642.64 kN PUNCHING SHEAR CHECK
Vu = 890.92 kN
ULTIMATE LOAD COMBINATIONS Vc = 1358.08 kN ∴ φVc=1018.56 kN
LC1 = 547.40 kN = 2698.52 kN
LC2 = 1130.00 kN ∴ qu=441.41 kPa = 2097.53 kN
LC3 = 882.20 kN D/C = 0.44
LC4 = 1053.95 kN ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 161.03 kN Mu = 106.82 β = 0.85
Vc = 391.63 kN ∴ φVc=293.73 kN fs = 4953.99 As = 2010.62
= 409.22 kN c = 34.79 Asmin = 1742.222 OKAY
= 679.77 kN Mn = 255.73
D/C = 0.32 φ = 0.90 D/C = 0.46
∴ SAFE φMn = 230.15 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 225.29 kN Mu = 137.94 β = 0.85
Vc = 373.49 kN ∴ φVc=280.12 kN fs = 4678.016 As = 2010.62
= 390.59 kN c = 34.79 Asmin 1655.652 OKAY
= 645.99 kN Mn = 242.41
D/C = 0.47 φ = 0.90 D/C = 0.63
∴ SAFE φMn = 218.17 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 4s-org' Date: 07/27/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1600
Material Properties:
f'c = 20.7 MPa
1400
fy = 414 MPa
λ = 1 1200

Soil Bearing Capacity 1000


SBCA = 450 kPa

WIDTH
SF = 2 800

SBC = 225 kPa


600

Axial Loads (Service Condition): 400


PDL = 391 kN
PLL = 413 kN 200
PEQ = 74 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500

Footing Parameters: Column Dimension:


t = 400 mm Loc = CENTER
L = 1600 mm dL = 306.00 mm Y = 500 mm L' = 625.00 mm
W = 1600 mm dW = 322.00 mm X = 350 mm W' = 550.00 mm
Øm = 16 mm
2
nL = 10 pcs AsL = 2010.62 mm NSCP REQUIREMENTS
s = 160.44 mm ≤450 ∴OKAY ρ = 1
nW = 10 pcs AsW = 2010.62 mm2 Ca = 0.5
s = 160.44 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 804.00 kN
LC1 = 804.00 kN Areqd = 3.57 m2
LC2 = 391.00 kN Aprov = 2.56 m2
LC3 = 443.86 kN D/C = 1.40
ALTERNATE BASIC LOAD COMBINATION ∴ NOT SAFE
LC4 = 603.00 kN
LC5 = 642.64 kN PUNCHING SHEAR CHECK
Vu = 890.92 kN
ULTIMATE LOAD COMBINATIONS Vc = 1358.08 kN ∴ φVc=1018.56 kN
LC1 = 547.40 kN = 2698.52 kN
LC2 = 1130.00 kN ∴ qu=441.41 kPa = 2097.53 kN
LC3 = 882.20 kN D/C = 0.44
LC4 = 1053.95 kN ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 161.03 kN Mu = 106.82 β = 0.85
Vc = 391.63 kN ∴ φVc=293.73 kN fs = 4953.99 As = 2010.62
= 409.22 kN c = 34.79 Asmin = 1742.222 OKAY
= 679.77 kN Mn = 255.73
D/C = 0.32 φ = 0.90 D/C = 0.46
∴ SAFE φMn = 230.15 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 225.29 kN Mu = 137.94 β = 0.85
Vc = 373.49 kN ∴ φVc=280.12 kN fs = 4678.016 As = 2010.62
= 390.59 kN c = 34.79 Asmin 1655.652 OKAY
= 645.99 kN Mn = 242.41
D/C = 0.47 φ = 0.90 D/C = 0.63
∴ SAFE φMn = 218.17 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 4s-ret Date: 07/27/20 Date:
DESIGN OF FOOTING
INPUT DATA:
2000
Material Properties:
f'c = 20.7 MPa 1800
fy = 414 MPa
1600
λ = 1
1400
Soil Bearing Capacity 1200
SBCA = 450 kPa

WIDTH
SF = 2 1000

SBC = 225 kPa 800

600
Axial Loads (Service Condition):
PDL = 391 kN 400
PLL = 413 kN
200
PEQ = 74 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500 3000

Footing Parameters: Column Dimension:


t = 400 mm Loc = CENTER
L = 1900 mm dL = 306.00 mm Y = 500 mm L' = 775.00 mm
W = 1900 mm dW = 322.00 mm X = 350 mm W' = 700.00 mm
Øm = 16 mm
2
nL = 12 pcs AsL = 2412.74 mm NSCP REQUIREMENTS
s = 158.55 mm ≤450 ∴OKAY ρ = 1
nW = 12 pcs AsW = 2412.74 mm2 Ca = 0.5
s = 158.55 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 804.00 kN
LC1 = 804.00 kN Areqd = 3.57 m2
LC2 = 391.00 kN Aprov = 3.61 m2
LC3 = 443.86 kN D/C = 0.99
ALTERNATE BASIC LOAD COMBINATION ∴ SAFE
LC4 = 603.00 kN
LC5 = 642.64 kN PUNCHING SHEAR CHECK
Vu = 960.46 kN
ULTIMATE LOAD COMBINATIONS Vc = 1358.08 kN ∴ φVc=1018.56 kN
LC1 = 547.40 kN = 2698.52 kN
LC2 = 1130.00 kN ∴ qu=313.02 kPa = 2097.53 kN
LC3 = 882.20 kN D/C = 0.47
LC4 = 1053.95 kN ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 224.81 kN Mu = 145.71 β = 0.85
Vc = 465.74 kN ∴ φVc=349.31 kN fs = 4896.136 As = 2412.74
= 486.38 kN c = 35.15 Asmin = 2068.889 OKAY
= 807.22 kN Mn = 306.72
D/C = 0.37 φ = 0.90 D/C = 0.53
∴ SAFE φMn = 276.04 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 278.93 kN Mu = 178.61 β = 0.85
Vc = 442.83 kN ∴ φVc=332.13 kN fs = 4623.036 As = 2412.74
= 464.25 kN c = 35.15 Asmin 1966.087 OKAY
= 767.11 kN Mn = 290.73
D/C = 0.48 φ = 0.90 D/C = 0.68
∴ SAFE φMn = 261.66 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 3s-org Date: 07/27/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1800
Material Properties:
f'c = 20.7 MPa 1600
fy = 414 MPa
λ = 1 1400

1200
Soil Bearing Capacity
SBCA = 450 kPa 1000

WIDTH
SF = 3
800
SBC = 150 kPa
600
Axial Loads (Service Condition):
400
PDL = 159 kN
PLL = 97 kN 200
PEQ = 28 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500 3000

Footing Parameters: Column Dimension:


t = 450 mm Loc = EDGE
L = 1750 mm dL = 356.00 mm Y = 700 mm L' = 650.00 mm
W = 1750 mm dW = 372.00 mm X = 450 mm W' = 525.00 mm
Øm = 16 mm
2
nL = 11 pcs AsL = 2211.68 mm NSCP REQUIREMENTS
s = 159.40 mm ≤450 ∴OKAY ρ = 1
nW = 11 pcs AsW = 2211.68 mm2 Ca = 0.5
s = 159.40 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 256.00 kN
LC1 = 256.00 kN Areqd = 1.71 m2
LC2 = 159.00 kN Aprov = 3.06 m2
LC3 = 179.00 kN D/C = 0.56
ALTERNATE BASIC LOAD COMBINATION ∴ SAFE
LC4 = 192.00 kN
LC5 = 207.00 kN PUNCHING SHEAR CHECK
Vu = 254.77 kN
ULTIMATE LOAD COMBINATIONS Vc = 2007.59 kN ∴ φVc=1505.69 kN
LC1 = 222.60 kN = 4251.76 kN
LC2 = 346.00 kN = 2445.65 kN
LC3 = 287.80 kN D/C = 0.08
LC4 = 355.55 kN ∴ qu=116.1 kPa ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 31.09 kN Mu = 28.00 β = 0.85
Vc = 489.43 kN ∴ φVc=367.07 kN fs = 5779.954 As = 2211.68
= 511.50 kN c = 34.98 Asmin = 1575 OKAY
= 858.94 kN Mn = 327.00
D/C = 0.05 φ = 0.90 D/C = 0.10
∴ SAFE φMn = 294.30 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 59.73 kN Mu = 42.92 β = 0.85
Vc = 472.14 kN ∴ φVc=354.11 kN fs = 5505.548 As = 2211.68
= 491.12 kN c = 34.98 Asmin 1575 OKAY
= 822.00 kN Mn = 312.35
D/C = 0.10 φ = 0.90 D/C = 0.15
∴ SAFE φMn = 281.12 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 4s-org Date: 07/27/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1800
Material Properties:
f'c = 20.7 MPa 1600
fy = 414 MPa
λ = 1 1400

1200
Soil Bearing Capacity
SBCA = 450 kPa 1000

WIDTH
SF = 3
800
SBC = 150 kPa
600
Axial Loads (Service Condition):
400
PDL = 229 kN
PLL = 146 kN 200
PEQ = 40 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500 3000

Footing Parameters: Column Dimension:


t = 450 mm Loc = EDGE
L = 1750 mm dL = 356.00 mm Y = 700 mm L' = 650.00 mm
W = 1750 mm dW = 372.00 mm X = 450 mm W' = 525.00 mm
Øm = 16 mm
2
nL = 11 pcs AsL = 2211.68 mm NSCP REQUIREMENTS
s = 159.40 mm ≤450 ∴OKAY ρ = 1
nW = 11 pcs AsW = 2211.68 mm2 Ca = 0.5
s = 159.40 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 375.00 kN
LC1 = 375.00 kN Areqd = 2.50 m2
LC2 = 229.00 kN Aprov = 3.06 m2
LC3 = 257.57 kN D/C = 0.82
ALTERNATE BASIC LOAD COMBINATION ∴ SAFE
LC4 = 281.25 kN
LC5 = 302.68 kN PUNCHING SHEAR CHECK
Vu = 371.21 kN
ULTIMATE LOAD COMBINATIONS Vc = 2007.59 kN ∴ φVc=1505.69 kN
LC1 = 320.60 kN = 4251.76 kN
LC2 = 508.40 kN = 2445.65 kN
LC3 = 420.80 kN D/C = 0.12
LC4 = 518.05 kN ∴ qu=169.16 kPa ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 45.29 kN Mu = 40.80 β = 0.85
Vc = 489.43 kN ∴ φVc=367.07 kN fs = 5779.954 As = 2211.68
= 511.50 kN c = 34.98 Asmin = 1575 OKAY
= 858.94 kN Mn = 327.00
D/C = 0.07 φ = 0.90 D/C = 0.14
∴ SAFE φMn = 294.30 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 87.03 kN Mu = 62.54 β = 0.85
Vc = 472.14 kN ∴ φVc=354.11 kN fs = 5505.548 As = 2211.68
= 491.12 kN c = 34.98 Asmin 1575 OKAY
= 822.00 kN Mn = 312.35
D/C = 0.14 φ = 0.90 D/C = 0.22
∴ SAFE φMn = 281.12 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 3s-ednew Date: 08/03/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1400
Material Properties:
f'c = 20.7 MPa
fy = 414 MPa 1200

λ = 1
1000

Soil Bearing Capacity


SBCA = 450 kPa 800

WIDTH
SF = 3
SBC = 150 kPa 600

Axial Loads (Service Condition): 400


PDL = 159 kN
PLL = 97 kN 200
PEQ = 28 kN
0 LENGTH
PWL = 0 kN
0 200 400 600 800 1000 1200 1400 1600 1800 2000

Footing Parameters: Column Dimension:


t = 400 mm Loc = EDGE
L = 1600 mm dL = 322.00 mm Y = 700 mm L' = 575.00 mm
W = 1300 mm dW = 306.00 mm X = 450 mm W' = 600.00 mm
Øm = 16 mm
2
nL = 6 pcs AsL = 1206.37 mm NSCP REQUIREMENTS
s = 228.80 mm ≤450 ∴OKAY ρ = 1
nW = 8 pcs AsW = 1608.50 mm2 Ca = 0.5
s = 206.29 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 256.00 kN
LC1 = 256.00 kN Areqd = 1.71 m2
LC2 = 159.00 kN Aprov = 2.08 m2
LC3 = 179.00 kN D/C = 0.82
ALTERNATE BASIC LOAD COMBINATION ∴ SAFE
LC4 = 192.00 kN
LC5 = 207.00 kN PUNCHING SHEAR CHECK
Vu = 223.48 kN
ULTIMATE LOAD COMBINATIONS Vc = 1633.74 kN ∴ φVc=1225.3 kN
LC1 = 222.60 kN = 3460.00 kN
LC2 = 346.00 kN = 1882.60 kN
LC3 = 287.80 kN D/C = 0.09
LC4 = 355.55 kN ∴ qu=170.94 kPa ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 80.41 kN Mu = 49.23 β = 0.85
Vc = 370.07 kN ∴ φVc=277.56 kN fs = 5997.519 As = 1608.50
= 383.75 kN c = 27.83 Asmin = 1280 OKAY
= 645.99 kN Mn = 195.89
D/C = 0.17 φ = 0.90 D/C = 0.28
∴ SAFE φMn = 176.31 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 56.22 kN Mu = 36.74 β = 0.85
Vc = 314.83 kN ∴ φVc=236.12 kN fs = 6921.028 As = 1206.37
= 325.23 kN c = 25.69 Asmin 1040 OKAY
= 552.31 kN Mn = 155.37
D/C = 0.14 φ = 0.90 D/C = 0.26
∴ SAFE φMn = 139.83 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 4s-ednew Date: 08/03/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1400
Material Properties:
f'c = 20.7 MPa
fy = 414 MPa 1200

λ = 1
1000

Soil Bearing Capacity


SBCA = 450 kPa 800

WIDTH
SF = 3
SBC = 150 kPa 600

Axial Loads (Service Condition): 400


PDL = 229 kN
PLL = 146 kN 200
PEQ = 40 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500

Footing Parameters: Column Dimension:


t = 400 mm Loc = EDGE
L = 1800 mm dL = 322.00 mm Y = 700 mm L' = 675.00 mm
W = 1400 mm dW = 306.00 mm X = 450 mm W' = 700.00 mm
Øm = 16 mm
2
nL = 8 pcs AsL = 1608.50 mm NSCP REQUIREMENTS
s = 177.71 mm ≤450 ∴OKAY ρ = 1
nW = 10 pcs AsW = 2010.62 mm2 Ca = 0.5
s = 182.67 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 375.00 kN
LC1 = 375.00 kN Areqd = 2.50 m2
LC2 = 229.00 kN Aprov = 2.52 m2
LC3 = 257.57 kN D/C = 0.99
ALTERNATE BASIC LOAD COMBINATION ∴ SAFE
LC4 = 281.25 kN
LC5 = 302.68 kN PUNCHING SHEAR CHECK
Vu = 359.22 kN
ULTIMATE LOAD COMBINATIONS Vc = 1633.74 kN ∴ φVc=1225.3 kN
LC1 = 320.60 kN = 3460.00 kN
LC2 = 508.40 kN = 1882.60 kN
LC3 = 420.80 kN D/C = 0.14
LC4 = 518.05 kN ∴ qu=205.58 kPa ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 145.79 kN Mu = 90.66 β = 0.85
Vc = 417.78 kN ∴ φVc=313.33 kN fs = 5337.768 As = 2010.62
= 435.14 kN c = 30.92 Asmin = 1862.609 OKAY
= 726.74 kN Mn = 243.77
D/C = 0.27 φ = 0.90 D/C = 0.41
∴ SAFE φMn = 219.40 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 101.60 kN Mu = 65.57 β = 0.85
Vc = 341.81 kN ∴ φVc=256.35 kN fs = 5474.677 As = 1608.50
= 355.51 kN c = 31.80 Asmin 1524.444 OKAY
= 594.79 kN Mn = 205.42
D/C = 0.23 φ = 0.90 D/C = 0.35
∴ SAFE φMn = 184.88 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 3s-org Date: 07/27/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1800
Material Properties:
f'c = 20.7 MPa 1600
fy = 414 MPa
λ = 1 1400

1200
Soil Bearing Capacity
SBCA = 450 kPa 1000

WIDTH
SF = 3
800
SBC = 150 kPa
600
Axial Loads (Service Condition):
400
PDL = 93 kN
PLL = 49 kN 200
PEQ = 16 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500 3000

Footing Parameters: Column Dimension:


t = 450 mm Loc = CORNER
L = 1750 mm dL = 356.00 mm Y = 700 mm L' = 650.00 mm
W = 1750 mm dW = 372.00 mm X = 450 mm W' = 525.00 mm
Øm = 16 mm
2
nL = 11 pcs AsL = 2211.68 mm NSCP REQUIREMENTS
s = 159.40 mm ≤450 ∴OKAY ρ = 1
nW = 11 pcs AsW = 2211.68 mm2 Ca = 0.5
s = 159.40 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 142.00 kN
LC1 = 142.00 kN Areqd = 0.95 m2
LC2 = 93.00 kN Aprov = 3.06 m2
LC3 = 104.43 kN D/C = 0.31
ALTERNATE BASIC LOAD COMBINATION ∴ SAFE
LC4 = 106.50 kN
LC5 = 115.07 kN PUNCHING SHEAR CHECK
Vu = 143.20 kN
ULTIMATE LOAD COMBINATIONS Vc = 2007.59 kN
LC1 = 130.20 kN = 4251.76 kN
LC2 = 190.00 kN = 1967.06 kN ∴ φVc=1475.29 kN
LC3 = 160.60 kN D/C = 0.04
LC4 = 199.85 kN ∴ qu=65.26 kPa ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 17.47 kN Mu = 15.74 β = 0.85
Vc = 489.43 kN ∴ φVc=367.07 kN fs = 5779.954 As = 2211.68
= 511.50 kN c = 34.98 Asmin = 1575 OKAY
= 858.94 kN Mn = 327.00
D/C = 0.03 φ = 0.90 D/C = 0.05
∴ SAFE φMn = 294.30 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 33.57 kN Mu = 24.12 β = 0.85
Vc = 472.14 kN ∴ φVc=354.11 kN fs = 5505.548 As = 2211.68
= 491.12 kN c = 34.98 Asmin 1575 OKAY
= 822.00 kN Mn = 312.35
D/C = 0.05 φ = 0.90 D/C = 0.09
∴ SAFE φMn = 281.12 kNm ∴ SAFE
1009 Cityland 10 Tower 2 Project: 3 STOREY STEEL PARKING BUILDING
H.V. dela Costa St., Client: PLDT GRACE PARK CALOOCAN
Salcedo Village, Location: GRACE PARK, CALOOCAN CITY
Makati City Job. No.: 1 Design by: SAC Checked by: SCM
Tel. no.: 519-8268 Subject: 4s-org Date: 07/27/20 Date:
DESIGN OF FOOTING
INPUT DATA:
1800
Material Properties:
f'c = 20.7 MPa 1600
fy = 414 MPa
λ = 1 1400

1200
Soil Bearing Capacity
SBCA = 450 kPa 1000

WIDTH
SF = 3
800
SBC = 150 kPa
600
Axial Loads (Service Condition):
400
PDL = 130 kN
PLL = 73 kN 200
PEQ = 22 kN
0 LENGTH
PWL = 0 kN
0 500 1000 1500 2000 2500 3000

Footing Parameters: Column Dimension:


t = 450 mm Loc = CORNER
L = 1750 mm dL = 356.00 mm Y = 700 mm L' = 650.00 mm
W = 1750 mm dW = 372.00 mm X = 450 mm W' = 525.00 mm
Øm = 16 mm
2
nL = 11 pcs AsL = 2211.68 mm NSCP REQUIREMENTS
s = 159.40 mm ≤450 ∴OKAY ρ = 1
nW = 11 pcs AsW = 2211.68 mm2 Ca = 0.5
s = 159.40 mm ≤450 ∴OKAY I = 1

DESIGN COMPUTATION:
SERVICE LOAD COMBINATIONS FOOTING DIMENSION CHECKING
BASIC LOAD COMBINATION Ps = 203.00 kN
LC1 = 203.00 kN Areqd = 1.35 m2
LC2 = 130.00 kN Aprov = 3.06 m2
LC3 = 145.71 kN D/C = 0.44
ALTERNATE BASIC LOAD COMBINATION ∴ SAFE
LC4 = 152.25 kN
LC5 = 164.04 kN PUNCHING SHEAR CHECK
Vu = 203.15 kN
ULTIMATE LOAD COMBINATIONS Vc = 2007.59 kN
LC1 = 182.00 kN = 4251.76 kN
LC2 = 272.80 kN = 1967.06 kN ∴ φVc=1475.29 kN
LC3 = 229.00 kN D/C = 0.06
LC4 = 283.50 kN ∴ qu=92.57 kPa ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "L" CHECK FOR MOMENT (REBAR ALONG "W")
Vu = 24.79 kN Mu = 22.33 β = 0.85
Vc = 489.43 kN ∴ φVc=367.07 kN fs = 5779.954 As = 2211.68
= 511.50 kN c = 34.98 Asmin = 1575 OKAY
= 858.94 kN Mn = 327.00
D/C = 0.04 φ = 0.90 D/C = 0.08
∴ SAFE φMn = 294.30 kNm ∴ SAFE

CHECK FOR SHEAR ALONG SIDE "W" CHECK FOR MOMENT (REBAR ALONG "L")
Vu = 47.63 kN Mu = 34.22 β = 0.85
Vc = 472.14 kN ∴ φVc=354.11 kN fs = 5505.548 As = 2211.68
= 491.12 kN c = 34.98 Asmin 1575 OKAY
= 822.00 kN Mn = 312.35
D/C = 0.08 φ = 0.90 D/C = 0.12
∴ SAFE φMn = 281.12 kNm ∴ SAFE