Fixing the mesh with nails

• Fix the first transverse bar


End of roll • Approximately every 80 cm
80 cm. • Nail just before slurry seal operation
First torsioned
flat bar

WHEN SLURRY SEALING: ONLY at the beginning of every roll

Building
Installation Procedure Products 1
7. Fixing the mesh with nails
Roll width Strand
1 2 3 4
Number of fixings
200cm 3 0 2 0
300cm 5 0 3 0
330cm 5 0 3 0
400cm 6 0 4 0

4th strand

3d strand

2d strand

1st strand

Example : mesh width 4m

Building
Installation Procedure Products 2
7. Fixing the mesh with nails
• Use Spit clip A
• Length 40 - 50 mm in asphalt
• 40 mm : at lower temp.
• 50 mm : at higher temp.
• Length 30 mm in concrete
• Use Spit P200 or P70 gun.

On concrete -> drill holes into the concrete


first to ensure good anchorage.