EXAMPLE: 1

Estimate the cost of a mansory platform 6m*5m from the given diagram and specification.
GENERAL SPECIFICATION:
1) Foundation - lime concrete
2) Mansory - 1st class brickwork in l
3) Flooring - 2.5 cm cement concrete over 7.5 cm lime concrete, over wall only 2.5 cm ce
4) Wall Finishing - Outsides walls are 12mm cement p
RATES: take local current rates

SEPARATE OR INDIVISUAL WALL

Centre to centre length long wall = 6-2*(40/2) =5.60m


Centre to centre length short wall = 5-2*(40/2) =4.60m
Particular of item of Total
Item Nos. Dimension in meter Quantity Explanatory Notes
work Quantity
No:
length breadth height
Earthwork in
1 excavation in
foundation...
long walls 2 6.4 0.8 0.7 7.168 11.424 L= 5.6 + 0.8 = 6.4
short walls 2 3.8 0.8 0.7 4.256 L= 4.6 - 0.8 = 3.8
Earthwork in filling
2 1 5.2 4.2 1.925 42.042 42.042 H= 2 - 0.75 = 1.925
inside above G.L
Lime concrete in
3
foundation
long walls 2 6.4 0.8 0.2 2.048 3.264
short walls 2 3.8 0.8 0.2 1.216
First class brick work in
4
lime mortar…
long walls….
1st footing 2 6.2 0.6 0.2 1.488 21.42 L= 5.6 + 0.6 = 6.2
2nd footing 2 6.1 0.5 0.1 0.61 L= 5.6 + 0.5 = 6.1
wall above footing…. 2 6 0.4 2.2 10.56 L= 5.6 + 0.4 = 6.0
short walls….
1st footing 2 4 0.6 0.2 0.96 L= 4.6 - 0.6= 4.0
2nd footing 2 4.1 0.5 0.1 0.41 L= 4.6 - 0.5= 4.1
wall above footing…. 2 4.2 0.4 2.2 7.392 L= 4.6 - 0.4= 4.2
12 mm cement sand
5 plastering 1:6 in wall
outside
Including 10 cm below
2 6 2.1 25.2 46.2
long walls G.L
short walls 2 5 2.1 21
2.5 cm c.c 1:2:4 floor
6 over and including 7.5 1 5.2 4.2 21.84 21.84
cm L.C
2.5 cm c.c 1:2:4 floor
7
on top of walls-
long walls 2 6 0.4 4.8 8.16
short walls 2 4.2 0.4 3.36
Abstract of Estimated Cost

Item Particular of item of woruanti Units Rates Per Amount


Rs .P Rs .P
Earthwork in
1 excavation in 11 cu m 350 % cu m 39.984
foundation...
Earthwork in filling
2 42 cu m 275 % cu m 115.6155
inside above G.L
Lime concrete in
3 3.3 cu m 220 cu m 718.08
foundation
First class brick work in
4 21 cu m 300 cu m 6426
lime mortar…
12 mm cement sand
5 plastering 1:6 in wall 46 sq m 7 sq m 323.4
outside
2.5 cm c.c 1:2:4 floor
6 over and including 7.5 22 sq m 18.64 sq m 407.0976
cm L.C
2.5 cm c.c 1:2:4 floor
7 on top of walls- 8.2 sq m 18 sq m 146.88

Total 8177.057
Add 3% For Contingencies 245.3117
dd 2% For Workcharged Establishment 163.5411
Grand Total 8585.91

CENTRE LINE METHOD:

Centre to centre length long wall = 6-2*(40/2) =5.60 * 2 = 11.2


Centre to centre length short wall = 5-2*(40/2) =4.60 * 2 = 9.2
Total 20.4 m

Item Particular of item of Total


Nos. Dimension in meter Quantity
No: work Quantity
length breadth height
Earthwork in
1 excavation in 1 20.4 0.8 0.7 11.424 11.424
foundation...
Earthwork in filling
2 1 5.2 4.2 1.925 42.042 42.042
inside above G.L
Lime concrete in
3 1 20.4 0.8 0.2 3.264 3.264
foundation
First class brick work in
4 21.42
lime mortar…
1st footing 1 20.4 0.6 0.2 2.448
2nd footing 1 20.4 0.5 0.1 1.02
wall above footing…. 1 20.4 0.4 2.2 17.952
12 mm cement sand
5 plastering 1:6 in wall
outside
long walls 2 6 2.1 25.2 46.2
short walls 2 5 2.1 21
2.5 cm c.c 1:2:4 floor
6 over and including 7.5 1 5.2 4.2 21.84 21.84
cm L.C
2.5 cm c.c 1:2:4 floor
7
on top of walls-
long walls 2 6 0.4 4.8 8.16
short walls 2 4.2 0.4 3.36

EXAMPLE: 3

Prepare a detailed estimate of a mortar garage from the given drawings, plan and section.
Adopt suitable rates. General Specifications are as follows:
1) Foundation and plinth
2) Superstructure
3) Finishing
motor garage:
long wall = 6.5+0.3 = 6.8

short wall = 3.0+ 0.3 = 3.3


approach ramp:
long wall = 2.5+0.1 = 2.6
short wall = 2.0+ 0.2 + 0.05 = 2.25

Particular of item of Total


Nos. Dimension in meter Quantity Explanatory Notes
Item work Quantity
length breadth height
Earthwork in
1 excavation in 9.6773125
foundation...
Garage:
long walls 2 7.4 0.6 0.65 5.772 L= 6.8 + 0.6 = 7.4
short walls 2 2.7 0.6 0.65 2.106 L= 3.3 - 0.6 = 2.7
L= 6.5 + 0.15= 6.35
1 6.35 2.85 0.075 1.357313 B= 3.0 - 0.15 = 2.85
H= 1.5 - 0.075 = 0.075
in filling in plinth
Approach ramp
Excavation front wall 1 2.8 0.2 0.34 0.1904 L= 2.6 + 0.2 = 2.8
excavation side wall 2 1.85 0.2 0.34 0.2516 L= 2.25-(0.2/2)-(0.6/2)

2 Lime concrete in 3.766


foundation
Garage:
long walls 2 7.4 0.6 0.3 2.664
short walls 2 2.7 0.6 0.3 0.972
Approach ramp
front wall 1 2.8 0.2 0.1 0.056
side wall 2 1.85 0.2 0.1 0.074
First class brick work in
foundation and plinth
3 4.174
with 1:6 cement sand
mortar
Garage:
long walls 2 7.2 0.4 0.5 2.88 L= 6.8 + 0.4 = 7.2
short walls 2 2.9 0.4 0.5 1.16 L= 3.3 - 0.4 = 2.9
ramp
front wall 1 2.7 0.1 0.2 0.054 L= 2.6 + 0.1 = 2.7
side wall 2 2 0.1 0.2 0.08 L= 2.25-(0.1/2)-(0.4/2)
2 cm thick damp proof
4 7.08
course-
long walls 2 7.2 0.4 5.76
short walls 2 2.9 0.4 2.32
deduct sill of gate…. 1 2.5 0.4 1
1st class brickrwork in
5 superstructure in lime 14.325
mortar
long wall 30 cm width 2 7.1 0.3 3 12.78 L= 6.8 + 0.3 = 7.1
short wall 30 cm width 2 3 0.3 3 5.4 L= 3.3 - 0.3 = 3.0

Deduct-
Gate opening 1 2.5 0.3 2.3 1.725
Window opening 3 1 0.3 1.2 1.08
Shelve opening 2 1 0.2 1.8 0.72

1 2.9 0.3 0.2 0.174 Bearing 20 cm


lintel over gate
lintel over window 3 1.2 0.3 0.1 0.108 Bearing 10 cm
lintel over shelves 2 1.2 0.2 0.1 0.048 Bearing 10 cm
R.C.C 1:2:4 work
excluding steel and its
bending but including
6 3.8832
centering and
shuttering and binding
steel-
Roof Slab- 1 7.4 3.9 0.12 3.4632
Lintel over gate,
0.354
window and shelves
slab if shelves 20 cm wid 6 1.1 0.2 0.05 0.066 Bearing 5 cm
7.5 cm lime concrete in
roof terrracing
7 1 7.4 3.9 28.86
including finish
surface…
12mm plater cement
8
sand 1:6 in wall -
inside- 132.0134
long wall 2 6.5 3 39
short wall 2 3 3 18
jambs, sills, soffits of
2 5.6 0.2 2.24 L=2*1.8 + 2*1 = 5.6
shelves 20 cm width
jambs of gate 2 0.3 2.3 1.38
soffit of lintel of gate 1 2.5 0.3 0.75
outside-
2 7.1 3 42.6
long walls above plinths
short wall 2 3.6 3 21.6
long wall plinth 2 7.2 0.3 4.32 L = 7.1 +0.1 = 7.2
short wall plinth 1 3.7 0.3 1.11 L = 3.6 +0.1 = 3.7
ramp front wall 1 2.7 0.1 0.27 10 cm below G.L
ramp side wall 2 2.1 0.177 0.7434 average height
Deduct: 13.9
2 1 1.2 2.4
Window opening
Gate opening 2 2.5 2.3 11.5 Jambs taken seperately

Net Total 118.1134

6mm plaster with 1:3


Cement coarse sand 25.602
9 mortar-

1 6.5 3 19.5
ceiling-
outer projection of
slab, bottomand
vertical faces-
long side 2 7.4 0.27 3.996 b= 15 +12 = 27 cm
short side 2 3.9 0.27 2.106
2.5 cm c.c. 1:2:4 floor
over and including 7.5
1 6.5 3 19.5 20.375
cm lime concrete inside
10 room
sill of gate 35 cm width 1 2.5 0.35 0.875 only 2.5cm c.c

4 cm c.c. 1:2:4 floor


1 2.1 2.7 5.67 over all only 4 cm c.c
over and including 7.5
11 cm lime concrete ramp
chaukhat wrought 2 no. verticals 1.2m
2 4.4 0.1 0.08 0.0704
12 framed fixed in window 2 no. horizontals 1m
4 cm thick shutters
Sishamed wood
2 0.97 1.17 2.2698 rebates 1.5 cm
battened in window
13 including fittings..
mild steel bar is R.C.C weight of steel = 78.5
1 0.0388 78.5 3.048155
14 @ 1% q/cu m
15 Iron holds fasts
in windows 8
in gates 6
14 @ 1 kg each 4 kg
Sheet Iron Gate 20
B.W.G. in angle iron 1 2.7 2.3 6.21 10 cm extended on site
16 frame
white washing 3 coats
143.71
17 inside and outside-
walls 118.11 same as plaster
ceiling and outside
25.6 same as 9
projection
Painting two coats over
18 a coat of priming

4.5 1 1.2 5.4 17.82


window
gate 2 2.7 2.3 12.42

Abstract of Estimated Cost

Particular of item of Qua Amount


Item work ntity Units Rates Per
Rs .P Rs .P
Earthwork in
excavation in 9.7 cu m 350 %cu m 33.845
1 foundation...
Lime concrete in
3.8 cu m 220 /cu m 828.52
2 foundation
foundation and plinth
with 1:6 cement sand 4.2 cu m 320 /cu m 1335.68
3 mortar

2 cm thick damp proof 7.1 sq m 18 /sq m 127.44


4 course-
1st class brickrwork in
superstructure in lime 14 cu m 320 /cu m 4584
5 mortar
R.C.C 1:2:4 work
excluding steel and its
bending but including
centering and 3.9 cu m 675 /cu m 2621.16
shuttering and binding
6 steel-
7.5 cm lime concrete in
roof terrracing
including finish 29 sq m 9 /sq m 259.74
7 surface…
12mm plater cement
sand 1:6 in wall - 118 sq m 7.1 /sq m 838.6051
8
Cement coarse sand
mortar- 26 sq m 5.3 /sq m 135.6906
9
2.5 cm c.c. 1:2:4 floor
over and including 7.5
cm lime concrete inside 20 sq m 18.65 /sq m 379.9938
10 room

4 cm c.c. 1:2:4 floor


over and including 7.5 5.7 sq m 22 /sq m 124.74
11 cm lime concrete ramp
Wood work- sal wood is
chaukhat wrought
framed fixed in window 0.1 cu m 4700 /cu m 330.88
12 10*8 cm
4 cm thick shutters
Sishamed wood
battened in window 2.3 sq m 125 /sq m 283.725
13 including fittings..
mild steel bar is R.C.C
@ 1% 3 quintal 515 /quintal 1569.802
14
15 Iron holds fasts 4 kg 7 /kg 28
Sheet Iron Gate 20
B.W.G. in angle iron 6.2 sq m 120 /sq m 745.2
16 frame
white washing 3 coats
inside and outside- 144 sq m 0.75 /sq m 107.7825
17
Painting two coats over
a coat of priming 18 sq m 10.4 /sq m 185.328
18
total 14520.13
Add 3% For Contingencies 435.604
dd 2% For Workcharged Establishment 290.4026
Grand Total 15246.14

PLINTH AREA RATIO

Plinth area = 7.1*3.6 = 25.56 sq m


P.A Rate = (Plinth area / Total cost) = (15246.1 / 25.56) = Rs. 598.85 sq m
CENTRE LINE METHOD:
Centre to centre length of all wall = 2*6.8 / 2*3.3 =20.20 m
Centre to centre length of all wall of ramp = (2.5+0.1)+2(2+0.05+0.2) = 7.1

Particular of item of
Nos. Quantity Explanatory
Item work Dimension in meter
length breadth height notes
Earthwork in
excavation in
1 foundation...
garage 1 20.2 0.6 0.65 7.88
L= 7.1 - 2*
1 6.5 0.2 0.34 0.44
ramp (60/2) = 6.5
Lime concrete in
2 foundation
garage 1 20.2 0.6 0.3 3.64
L= 7.1 - 2*
1 6.7 0.2 0.1 0.134
ramp (40/2) = 6.7
First class brick work in
foundation and plinth
with 1:6 cement sand
3 mortar
garage 1 20.2 0.4 0.5 4.04
ramp
L= 2.6 + 0.1 =
1 2.7 0.1 0.2 0.054
front wall 2.7
L= 2.25-
2 2 0.1 0.2 0.08 (0.1/2)-
side wall (0.4/2)
2 cm thick damp proof
1 20.2 0.4 8.08
4 course-
deduct sill gate 13 2.5 0.4 1
total 7.08
1st class brickrwork in
superstructure in lime 1 20.2 0.3 3 18.18
5 mortar
Deduct-
Gate opening 1 2.5 0.3 2.3 1.725
Window opening 3 1 0.3 1.2 1.08
Shelve opening 2 1 0.2 1.8 0.72
lintel over gate 1 2.9 0.3 0.2 0.174
lintel over window 3 1.2 0.3 0.1 0.108
lintel over shelves 2 1.2 0.2 0.1 0.048
total 14.3

Example 5:

Prepare a detailed estimate of a two roomed building with front verandha from the given drawings-plan, elevatio
calculate also the plinth area and the general specification are as follow:
1) Foundation and Plinth
2) Damp proof course
3) Superstructure
4) Roof
5) Flooring
6) Plastering and finishing
7) Doors and windows
8) Miscelleanous items.
Center to center length:

Room:

long wall = 3.5+4+0.3+(2*(0.3/2)) = 8.1m


short wall = 4.0+ (2*(0.3/2)) = 4.3
Verandha:
front = 3.5+4+(3*0.3)+(2*0.5)-0.3 = 8.2
sides = 2.5+ (0.3/2) + (0.3/2) = 2.75

Particular of item of Total


Nos. Quantity Explanatory Notes
Item work Dimension in meter Quantity
length breadth height
Earthwork in
1 excavation in 31.35
foundation...

room:

2 9 0.9 0.9 14.58 L= 8.1 + 0.9 = 9


long walls
short walls 2 3.4 0.9 0.9 5.508 L= 4.3 - 0.9 = 3.4
verandha
Excavation front wall 1 8.9 0.7 0.9 5.607 L= 8.2+ 0.7 = 8.9
L= 2.75-(0.9/2)-(0.7/2
2 1.95 0.7 0.9 2.457
excavation side wall =1.95)
Step: 1 2.9 1 0.15 0.44 L=2.7(2*0.1) = 2.9
Earthwork in filling in
2 25.61
plinth..
L= 4-0.1 = 3.9
B= 3.5-0.1 = 3.4
1 3.9 3.4 0.54 7.16
H = 0.6+0.02-0.08 =
room 1 .54
L=8.2-0.3 = 7.9
1 3.9 3.9 0.54 8.22 B = 2.75 -0.2-0.15 =
room 2 2.4
Verandha 1 7.9 2.4 0.54 10.23

3 Lime concrete in 10.74


foundation
rooms:
long walls 2 9 0.9 0.3 4.86
short walls 3 3.4 0.9 0.3 2.754 may be taken 1/3 of
verandha excavation
front wall 1 8.9 0.7 0.3 1.869
side wall 2 1.95 0.7 0.3 0.819
step 1 2.9 1 0.15 0.435
First class brick work in
foundation and plinth
4 22.32
with 1:6 cement
mortar
room:
long walls
1st footing 2 8.8 0.7 0.2 2.46 L= 8.1 + 0.7 = 8.8
2nd footing 2 8.7 0.6 0.1 1.04 L= 8.1 + 0.6 = 8.7
3rd footing 2 8.6 0.5 0.1 0.86 L= 8.1 + 0.5 = 8.6
Plinth footing 2 8.5 0.4 0.8 5.44 L= 8.1 + 0.4 = 8.5
short walls
1st footing 3 3.6 0.7 0.2 1.51 L= 4.3 - 0.7 = 3.6
2nd footing 3 3.7 0.6 0.1 0.67 L= 4.3 - 0.6 = 3.7
3rd footing 3 3.8 0.5 0.1 0.57 L= 4.3 - 0.5 = 3.8
Plinth footing 3 3.9 0.4 0.8 3.74 L= 4.3 - 0.4 = 3.9
verandha
front wall
1st footing 1 8.7 0.5 0.2 0.87 L= 8.2+ 0.5 = 8.7
2nd footing 1 8.6 0.4 0.1 0.34 L= 8.2+ 0.4 = 8.6
Plinth footing 1 8.5 0.3 0.9 2.3 L= 8.2+ 0.3 = 8.5
side wall
L= 2.75-(0.5/2)-(0.7/2
2 2.15 0.5 0.2 0.43
1st footing =2.15)
L= 2.75-(0.4/2)-(06/2
2 2.25 0.4 0.1 0.18
2nd footing =2.25)
L= 2.75-(0.5/2)-(03/2
2 2.35 0.3 0.1 0.14
Plinth footing =2.35)
Plinth wall remaining L= 2.75-(0.4/2)-(03/2
2 2.4 0.3 0.8 1.15
portion =2.4)
Steps
1st step 1 2.7 0.9 0.15 0.36
2nd step 1 2.1 0.6 0.15 0.19
3rd step 1 1.5 0.3 0.15 0.07
2 cm thick damp proof
5 10.52
course-
long walls 2 8.5 0.4 6.8
short walls 3 3.9 0.4 4.68
deduct sill of gate…. 2 1.2 0.4 0.96
1st class brickrwork in
6 superstructure in lime 30.1
mortar
Rooms-
long wall 2 8.4 0.3 4 20.16 L= out to out
short wall 3 4 0.3 4 14.4 L= in to in
Verandha
front 1 8.4 0.2 0.3 0.5
side wall 2 2.5 0.2 0.3 0.3
Parapet
Over Rooms-
long wall 2 8.4 0.2 0.6 2.016 h = 47+10+3 = 60 cm
short wall 2 4.2 0.2 0.6 1.008 L= 4+(2*0.3)-(2*0.2)=4.2
Verandha
front 1 8.4 0.2 0.4 0.67 h = 27+10+3 = 40 cm
side wall 2 2.5 0.2 0.4 0.4
Deduct-
Gate opening 2 1.2 0.3 2.1 1.512
Window opening 10 1 0.3 1.5 4.5
c.s windows 12 1 0.3 0.5 1.8
Shelve opening 2 1 0.2 1.5 0.6
lintel over gate 2 1.4 0.3 0.1 0.084 Bearing 10 cm

10 1.2 0.3 0.1 0.36 Bearing 10 cm

lintel over window

12 1.2 0.3 0.1 0.432 Bearing 10 cm

lintel over cs windows


lintel over shelves 2 1.2 0.3 0.1 0.072 Bearing 10 cm
R.B work excluding
steel and its bending
7 but including centering 1.788
and shuttering and
binding steel-
Lintel over gate,
0.948 same as 6
window and shelves
over verandha pillars
front 1 8.4 0.2 0.3 0.504 out to out
sides 2 2.8 0.2 0.3 0.336 inside bearing 30 cm
R.C.C work in ver
columns excluding
30 cm insertion into
steel and its bending
8 4 0.0177 3.14 2.7 0.19 the plinth wall below
but including form and
floor
binding steel complete
fair finished
R.C.C work excluding
steel and its bending
but including centering
9 8.328
and shuttering and
binding steel-, fair
finished
Roof slab rooms 1 8.64 4.84 0.12 5.018 12 cm projections
10cm inner bearing,
1 8.4 2.8 0.1 2.352
roof slab verandha excluding chajja

chajja projections

1 9.3 0.45 0.6 0.251 average thickness


ver. Front
ver. Sides 2 2.7 0.45 0.6 0.146
Sun-shed and breakers
in windows
top 4 2.5 0.45 0.05 0.225
5 cm into insertion
4 2.5 0.15 0.05 0.075
bottom into walls
5 cm into insertion
8 1.5 0.75 0.05 0.195
sides and average breadth
shelf slab 6 1.1 0.2 0.05 0.066 5 cm beraing

Mild steel bars


1%of total of items 1.8
10 including bending in 10.31 0.01 78.5 8.10q
and 9
reininforcement 2 1%
of R.B and R.C.C works
10 cm lime concrete in
11 53.6
roof terracing complete
with surface finishing
clear roof area in
1 8 4.2 33.6
room between parapet
verandha 1 8 2.5 20
3 cm thick insulation
12 53.6
layers of sand and clay-
rooms 1 8 4.2 33.6 clear roof area
verandah 1 8 2.5 20
Sal wood work in
13 chowkhat wrought 0.735
framed and fixed
Doors ( 3 cm insertion
2 5.46 0.12 0.8 0.105
into floors)
windows 10 5 0.1 0.8 0.4
CS windows 12 3 0.8 0.8 0.23
4mm thick indian trak
14 wood glazed shutters 16.274
including fittings-
Doors ( 3 cm insertion
2 1.07 2.035 4.355 rebate 1.5 cm
into floors)
windows 10 0.87 1.37 11.919
4mm thick indian trak
15 wood glazed shutters 12 0.87 0.37 3.863
including fittings-
ironn work (mild steel)
16 in hold fests and 303.52
window greatings-
holds fast in doors 12 12 6 no per doors
holds fasts in windows 40 40 4 nos per windows
24 24 2 nos per cs windows
hold fast in cs windows
window bars 16 mm
dia@ 1.58 kg/m-
ver. Bars at 10 cm
80 1.5 120
windows centers app
CS windows 24 1 24 2 horizontal bars
12mm plater cement
sand 1:1:6 cement,
17
sand, lime mortar-
inside
inside-
may be taken as inner
rooms 1 2 3.5 4 28 153.64
p *h = 15 * 4
2 4 4 32
4 4 4 64
room 2
ver inner wall 1 8.4 3 25.2 length out to out
ver.front above
1 8 0.6 4.8
cols.inner face
ver sides above cols.
2 2.5 0.6 3
Inner face
jambs sills and soffit of
2 2 0.2 2 L=2*1+2*1.5 = 5m
shelves
soffits of ver lintel-
No deduction for
1 8.4 0.2 1.6
front col.ends
sides 2 2.5 0.2 1
Deduct opening in walls
in between ver and
rooms-
door openings- 2 1.2 2.1 5.04 one surface of each
window openings 2 1 1.5 3 one surface of each
outside
rooms 152
Black plinth including
1 8.5 0.75 6.38 ht = 0.6+0.5+0.1=0.75
10cm below GL
back super structure 1 8.4 4 33.6
Sides plinth including
10 cm below gl
sides super structure 2 4.7 0.75 7.05
verandha 2 4.6 4 36.8
above cola, fronts outer
1 8.4 0.6 5.04
face
above cola, sides outer
2 2.7 0.6 3.24
face
plinth front including 1 8.5 0.7 5.95 ht = 0.6+0.1=0.7
plinth sides 2 2.75 0.7 3.85
wall above ver. Roof 1 8.4 0.77 6.47 ht = 4+3.23=0.77
Parapet
rooms
2 8.4 0.6 10.08
long wall outer surface
long wall inner surface 2 8 0.47 7.52
long wall top surface 2 8.4 0.2 3.36
2 4.6 5.52
short wall outer surface

2 4.2 3.95
short wall inner surface
short wall top surface 2 4.2 0.2 1.68
Verandah parapet
front wall outer 1 8.4 0.4 3.36
fornt wall inner face 1 8 0.27 2.16
1 8.4 0.2 1.68
front wall top face
side wall outer face 2 2.7 0.4 2.16
side wall inner face 2 2.5 0.27 1.35

2 2.5 0.2 1
side wall top face
Deduct 20.24
window openings 8 1 0.5 6 one surface of each
Cs window openings 12 2.7 0.7 1.89
step from plinth level 1 including 10 cm below G
ends of ver. Side wall
and lintel above col 2 0.2 0.6 0.24
level
ends of ver parapet
wall. From wall above 2 0.2 0.27 0.11
ver. Roof level
total 285.6
20 mm thick cement
plaster 1:3in step
18
finished cement
rendered
1st step river 1 4.5 0.15 0.675 1.49 Front and sides
2nd step river 1 3.3 0.15 0.495 Front and sides

1 2.1 0.15 0.315 Front and sides


3rd step river
1st step tread 1 3.9 0.3 2.43 Front and sides
2nd step tread 1 2.7 0.3 Front and sides
3rd step tread 1 1.5 0.3 Front and sides
plinth wall above
1st step 2 0.3 0.45 0.27 4.59 sides
2nd step 2 0.3 0.3 0.18 sides
3rd step 1 1.5 0.3 0.15 sides

2.5 cm c.c. 1:2:4 floor


19 50
over and including 8 cm
lime concrete floor
room1 1 4 3.5 14
Sills Of verandha
1 4 4 16 openings have been
room 2 taken under item 20
verandha 1 8 2.5 20
2.5 cm c.c. 1:2:4 floor in
20 4.02
sills
door 2 1.2 0.3 0.72
ver opening front 1 8.5 0.25 2.12
sills of verandha
2 2.5 0.25 1.25
opening sides
deduct pillars 4 4 0.07
white washing three
21 203.64
coats inside-

153.64 same as 17 inside wall


walls
ceiling of room 1 1 4 3.5 14
ceiling of room 2 1 4 4 16
ceiling of ver.. 1 8 2.5 20
Colour washing two
22 coats over one coat of 171.58
white washing outside-
walls 131.96 same as 17 outside wall

upper and lower faces


1 9.3 0.95 8.84
and edges.
chajja ver. Front
upper and lower faces
2 2.7 0.95 5.13
chajja ver sides and edges.
sunshades and
upper and lower faces
sunshaders in windows - 4 2.5 0.95 9.5
and edges.
top
bottom 4 2.5 0.25 2.5 inner and outer faces
sides 16 1.5 0.45 6
edges of sides 8 1.5 0.5 0.6
outer projections of B= 0.12+0.12+0.12 =
1 26 0.36 9.36
roof slab 0.36m
deduct portions below L= outer perimeter -
1 29.1 2.91
g.l steps
painting doors and
windows two coats
23 65.77
over one coat of
priming…

2(1/4) times one


(9/2) 1.2 2.1 11.34
surface for both sides
door panelled

54/2 1 1.5 33.75


window panelled
one surface of both
12 1 0.5 6
cs windows glazed sides
window bars 10 0.84 1.34 11.25 excluding chowkhat, on
cs window bars 12 0.84 0.34 3.43 flat area for over all
Solignum painting two
24 coats in back of 9.19
chaukhat-
doors 2 5.46 0.12 1.31
windows 10 5 0.1 5 lengths same for
12 3 0.08 2.88 chowkhat in item 13
cs window

C.I pipe 10 cm dia.(rain


25 water spout) complete 4 1 4
with painting

Abstract of Estimated Cost

Qua
Item Particular of item of Amount
ntity
No: work Units Rates Per
Rs .P Rs .P

Earthwork in 31 cu m 350 % cu m 109.725


excavation in
1 foundation...

26 cu m 275 % cu m 70.4275
Earthwork in filling in
2 plinth..

Lime concrete in 11 cu m 220 per cu m 2362.8


3 foundation
First class brick work in
foundation and plinth
22 cu m 320 per cu m 7142.4
with 1:6 cement
4 mortar
2 cm thick damp proof
11 sq m 18 per sq m 189.36
5 course-
1st class brickrwork in
superstructure in lime 30 cu m 320 per cu m 9632
6 mortar
R.B work excluding
steel and its bending
but including centering 1.8 cu m 520 per cu m 929.76
and shuttering and
7 binding steel-
R.C.C work in ver
columns excluding
steel and its bending
0.2 cu m 590 per cu m 112.1
but including form and
binding steel complete
8 fair finished
R.C.C work excluding
steel and its bending 8.3 cu m 775 per cu m 6454.2
9 but including centering
Mild steel bars
including bending in 8.10q quintal 515 per q #VALUE!
10 reininforcement 2 1%
10 cm lime concrete in
roof terracing complete 54 sq m 12 per sq m 643.2
11 with surface finishing
3 cm thick insulation
54 sq m 1.5 per sq m 80.4
12 layers of sand and clay-
Sal wood work in
chowkhat wrought 0.7 cu m 4700 per cu m 3454.5
13 framed and fixed
4mm thick indian trak
wood glazed shutters 16 sq m 225 per sq m 3661.65
14 including fittings-
4mm thick indian trak
wood glazed shutters 3.9 sq m 200 per sq m 772.6
15 including fittings-
in hold fests and
3 quintal 700 per q 2124.5
16 window greatings-
sand 1:1:6 cement,
sand, lime mortar- 285 sq m 2.9 per sq m 826.5
17 inside
20 mm thick cement
plaster 1:3in step
4.6 sq m 16 per sq m 73.44
finished cement
18 rendered
19 2.5 cm c.c. 1:2:4 floor 50 sq m 18.65 per sq m 932.5
20 sills 4 sq m 18 per sq m 72.36
white washing three
204 sq m 0.75 per sq m 152.73
21 coats inside-
Colour washing two
coats over one coat of 172 sq m 0.82 per sq m 140.6956
22 white washing outside-
painting doors and
windows two coats
66 sq m 10.4 per sq m 684.008
over one coat of
23 priming…
Solignum painting two
coats in back of 9.2 sq m 3.5 per sq m 32.165
24 chaukhat-

C.I pipe 10 cm dia.(rain


water spout) complete 4 m 27 per m 108
25 with painting
total 44935.25
Add 3% of
1348.05
Contingencies
Add 2% for
Workcharged 898.7
Establishment
Grand Toatal 47181

Plinth Area Ratio


Plinth Area = 8.4*7.3 = 61.32 sqm
Plinth Area Ratio: (Total Cost/ Plinth Area) = RS (47181/61.32) = Rs 769.42

CENTRE LINE METHOD:

total length of center lines of all walls of roo :(2X8.1)+(3X4.3)


number of junctions is two similar walls :29.10m
total length of all center lines of walls of ver :8.20+2(2.75)
number of junction is two dissimilar walls at same le :13.70m

Item Particular of item of Nos. Quantity Explanatory


No: work Dimension in meter
length breadth height notes
Earthwork in
1 excavation in
foundation
L=29.10-
Rooms 28.2 0.9 0.9 22.84 2X.90/2=28.
20m
L=13.70-
verandah 12.8 0.7 0.9 8.06 2X.90/2=12.
80m
Total 30.9
Lime concrete in
2
foundation
L=29.10-
Rooms 1 28.2 0.9 0.3 7.61 2X.90/2=28.
20m
L=13.70-
Verandah 1 12.8 0.7 0.3 2.69 2X.90/2=12.
80m
total 10.3

1-class brickwork in
3 foundation and plinth
1:6 cement motor
rooms
L=29.10-
1st footing 1 28.4 0.7 0.2 3.98 2X70/2=28.
4m
L=29.10--
2nd footing 1 28.5 0.6 0.1 1.71
.6=28.5m
L=29.10-
3rd footing 1 28.6 0.5 0.1 1.43
.4=28.7m
L=29.10-
Pint wall above footing 1 28.7 0.4 0.8 9.18
.5=28.6m
verandah
L=13.7-
1st footing 1 13 0.5 0.2 1.3 2X70/2=13
m
L=13.7-
2nd footing 1 13.1 0.4 0.1 0.52
.6=13.1m
L=13.7-
Pint wall above footing 1 13.2 0.3 0.1 0.4
.5=13.2m
L=13.7-
Pint wall above footing 1 13.3 0.3 0.8 3.19
.4=13.3m
total 21.71

4 cm damp proof course

length same
rooms 1 28.7 0.4 11.48
as pint wall
deduct door sills 2 1.2 0.4 0.96
total 10.52 sq m
1-class brickwork in
5 superstructure in
lime motor
L=29.10-
rooms 1 28.8 0.3 4 34.56
.3=28.8m
L=13.7-
verandah above lintel 1 13.4 0.2 0.3 0.8
.3=13.4

total center
line length
parapet over room 1 25.2 0.2 0.6 3.02 =2X
8.2+2X4.4=
25.2

total length
=
parapet over verandah 1 13.4 0.2 0.4 1.07
1X8.4+2X2.
5=13.4m
total 39.45
deduct openings
9.36
lintels etc
net total 30.09 cu m