Dismantling of Boiler 15-Nov-10 23:44

Dismantling of Boiler
Activity Name Original BL Project BL Project Total Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16
Duration Start Finish Float W W W W W W W W
S M T T F S S M T T F S S M T T F S S M T T F S S M T T F S S M T T F S S M T T F S S M T T F S S MT
Dismantling of Boiler 35 28-Nov-10 08-Jan-11 0

Electrical Isolation 2 28-Nov-10 30-Nov-10 0

Isolation of Instrument 3 28-Nov-10 30-Nov-10 0 Isolation of Instrument


Isolation of all stored Energy points 3 28-Nov-10 30-Nov-10 0 Isolation of all stored Energy points
Isolation of Electric Lightning and Electric Motor 1 30-Nov-10 30-Nov-10 0 Isolation of Electric Lightning and Electric Motor
Instrument and Mechanical Isolation 19 01-Dec-10 22-Dec-10 0

Disconnection of Burner and Pilot Lines FG-1600 4 01-Dec-10 05-Dec-10 0


Disconnection of Burner No. 1 and 2 line (3") 2 01-Dec-10 02-Dec-10 0 Disconnection of Burner No. 1 and 2 line (3")
Disconnection of Level Safety ZSH123 and ZSH124 1 01-Dec-10 01-Dec-10 0 Disconnection of Level Safety ZSH123 and ZSH124
Disconnection of Pilot No. 1 and 2 line (1/2") 2 02-Dec-10 03-Dec-10 0 Disconnection of Pilot No. 1 and 2 line (1/2")
Isolation of instruments UV112 and UV113 1 03-Dec-10 03-Dec-10 0 Isolation of instruments UV112 and UV113
Disconnection of globe valve and blinding 2 04-Dec-10 05-Dec-10 0 Disconnection of globe valve and blinding
Disconnection of Steam Generation Line 6 01-Dec-10 07-Dec-10 0
Disconnection of flanges 2 01-Dec-10 02-Dec-10 0 Disconnection of flanges
Shut down of valves 1 01-Dec-10 01-Dec-10 0 Shut down of valves
Isolation of FT83C 1 03-Dec-10 03-Dec-10 0 Isolation of FT83C
Isolation of MOV83C 1 04-Dec-10 04-Dec-10 0 Isolation of MOV83C
Isolation of FE81C and FT81C 1 05-Dec-10 05-Dec-10 0 Isolation of FE81C and FT81C
Removal and lifting of Steam Line 2 06-Dec-10 07-Dec-10 0 Removal and lifting of Steam Line
Boiler Body - Water Drum Instrument Disconnec 5 06-Dec-10 10-Dec-10 0
Disconnection of Pressure Safety Valves exhaust 1 06-Dec-10 06-Dec-10 0 Disconnection of Pressure Safety Valves exhaust
Isolation of Pressure indicator PI117C 1 07-Dec-10 07-Dec-10 0 Isolation of Pressure indicator PI117C
Pressure safety valves isolation PSV115C and PSV11 1 07-Dec-10 07-Dec-10 0 Pressure safety valves isolation PSV115C and PSV118C
Isolation and disconnection of LG98C and LSLL100C 1 08-Dec-10 08-Dec-10 0 Isolation and disconnection of LG98C and LSLL100C
Disconnection of flanges and valves 2 09-Dec-10 10-Dec-10 0 Disconnection of flanges and valves
Water and Chemical Dosing Lines 3 08-Dec-10 10-Dec-10 0
Isolation of valves MOV91C and FV82C 2 08-Dec-10 09-Dec-10 0 Isolation of valves MOV91C and FV82C
Shut down of check valves 1 09-Dec-10 09-Dec-10 0 Shut down of check valves
Disconnection of flanges 1 10-Dec-10 10-Dec-10 0 Disconnection of flanges
Air System Line 2 10-Dec-10 12-Dec-10 0
Shut down of all valves 1 10-Dec-10 10-Dec-10 0 Shut down of all valves
Isolation of Valves UY123C (2 Nos) 1 10-Dec-10 10-Dec-10 0 Isolation of Valves UY123C (2 Nos)
Disconnection of Flanges 2 11-Dec-10 12-Dec-10 0 Disconnection of Flanges
Shut down of flow control valves 1 11-Dec-10 11-Dec-10 0 Shut down of flow control valves
Isolation of 1/2" globe valves 1 11-Dec-10 11-Dec-10 0 Isolation of 1/2" globe valves
Gas Duct 1 12-Dec-10 13-Dec-10 0
Disconnection of flanges from stack 1 12-Dec-10 12-Dec-10 0 Disconnection of flanges from stack
Disconnection of flanges from boiler body 1 12-Dec-10 12-Dec-10 0 Disconnection of flanges from boiler body
Disconnection of O2T86C and TE98C 1 12-Dec-10 12-Dec-10 0 Disconnection of O2T86C and TE98C
Lifting and Removal of gas duct 1 13-Dec-10 13-Dec-10 0 Lifting and Removal of gas duct
Stack 3 13-Dec-10 15-Dec-10 0
Disconnection and lifting of Middle section 1 13-Dec-10 13-Dec-10 0 Disconnection and lifting of Middle section
Disconnection and lifting of Upper section 1 13-Dec-10 13-Dec-10 0 Disconnection and lifting of Upper section
Disconnection and lifting of lower section 2 14-Dec-10 15-Dec-10 0 Disconnection and lifting of lower section
Removal of anchor bolts 1 14-Dec-10 14-Dec-10 0 Removal of anchor bolts

Primary Baseline Remaining Work Milestone Page 1 of 2 TASK filter: All Activities

Actual Work Critical Remaining Work © Primavera Systems, Inc.


Dismantling of Boiler 15-Nov-10 23:44
Dismantling of Boiler
Activity Name Original BL Project BL Project Total Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16
Duration Start Finish Float W W W W W W W W
S M T T F S S M T T F S S M T T F S S M T T F S S M T T F S S M T T F S S M T T F S S M T T F S S MT
Intermittent Blow Down Line 1 14-Dec-10 14-Dec-10 0
Removal of intermittent line 1 14-Dec-10 14-Dec-10 0 Removal of intermittent line
Disconnection of flanges 1 14-Dec-10 14-Dec-10 0 Disconnection of flanges
Shut down of all valves 1 14-Dec-10 14-Dec-10 0 Shut down of all valves
FD Fan and Air Duct 2 15-Dec-10 16-Dec-10 0
Disconnection of FD Fan From Air Duct 1 15-Dec-10 15-Dec-10 0 Disconnection of FD Fan From Air Duct
Isolation of Electric Motor 1 15-Dec-10 15-Dec-10 0 Isolation of Electric Motor
Disconnection of FD Fan From basement 1 15-Dec-10 15-Dec-10 0 Disconnection of FD Fan From basement
Removal of Air Duct 1 16-Dec-10 16-Dec-10 0 Removal of Air Duct
Disconnection of Air Duct from windbox 1 16-Dec-10 16-Dec-10 0 Disconnection of Air Duct from windbox
Disconnection for instruments on Air Duct 1 16-Dec-10 16-Dec-10 0 Disconnection for instruments on Air Duct
Disconnection of Instruments on FD Fan 1 16-Dec-10 16-Dec-10 0 Disconnection of Instruments on FD Fan
Continuous Blow Down Line 2 17-Dec-10 18-Dec-10 0
Disconnection of flanges 2 17-Dec-10 18-Dec-10 0 Disconnection of flanges
Disconnection of Line from Boiler Body 1 17-Dec-10 17-Dec-10 0 Disconnection of Line from Boiler Body
Shut down of valves 1 17-Dec-10 17-Dec-10 0 Shut down of valves
Adjustment of Line for parallel use to other boilers 1 18-Dec-10 18-Dec-10 0 Adjustment of Line for parallel use to other boilers
Guides , Rails, Stairs 4 18-Dec-10 22-Dec-10 0
Disconnection of Upper Platform 2 18-Dec-10 19-Dec-10 0 Disconnection of Upper Platform
Disconnection of Guides, Rails and Stairs 3 20-Dec-10 22-Dec-10 0 Disconnection of Guides, Rails and Stairs
Cables from Instruments to JB 2 22-Dec-10 23-Dec-10 0

Disconnection of all cables from instruments to JB 2 22-Dec-10 23-Dec-10 0 Disconnection of all cables from instruments to JB
Heavy Lifting of old Boiler 13 25-Dec-10 08-Jan-11 0

Surface Preparation 7 25-Dec-10 31-Dec-10 0 Surface Preparation


Positioning of Crane 6 01-Jan-11 06-Jan-11 0 Positioning of Crane
Lifting of Boiler 2 07-Jan-11 08-Jan-11 0 Lifting of Boiler

Primary Baseline Remaining Work Milestone Page 2 of 2 TASK filter: All Activities

Actual Work Critical Remaining Work © Primavera Systems, Inc.