Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

4.1.

1     The Contractor shall execute and complete the Works in  The Contractor shall design (to the extent specified in the 
accordance with the Contract and the Employer's  Contract), execute and complete the Works in accordance with 
Representative's instructions, and shall remedy any defects in the  the Contract and with the Engineer's instructions, and shall 
Works in accordance with the Contract remedy any defects in the Works. The Contractor shall provide 
the Plant and Contractor's Documents specified in the Contract, 
4.1.2      The Contractor shall provide the Plant and Contractor's  and all Contractor's Personnel, Goods, consumables and other 
Documents specified in the Contract, and all Contractor's  things and services, whether of a temporary or permanent 
Personnel, Goods, consumables and other things and services,  nature, required in and for this design, execution, completion and 
whether of a temporary or permanent nature, required in and for  remedying of defects. The Contractor shall be responsible for the 
the execution and completion of the Works and remedying of  adequacy, stability and safety of all Site operations and of all 
defects in the Works in accordance with the Contract The  methods of construction. Except to the extent specified in the 
Contractor shall be responsible for the safe storage and adequate  Contract, the Contractor (i) shall be responsible for all 
protection of all Plant, Goods, consumables and all other things  Contractor's Documents, Temporary Works, and such design of 
on the Site necessary for the performance of the Works from the  each item of Plant and Materials as is required for the item to be 
date when they arrive on the Site until the issuance of the Taking  in accordance with the Contract, and (ii) shall not otherwise be 
Over Certificate under Clause 10 [Employer's Taking Over]. In the  responsible for the design or specification of the Permanent 
event of any damage or loss occurring to any Plant, Goods,  Works. The Contractor shall, whenever required by the Engineer, 
consumables or any other things on the Site necessary for the  submit details of the arrangements and methods which the 
performance of the Works from the date when they arrive on the  Contractor proposes to adopt for the execution of the Works. No 
Site until the issuance of the Taking Over Certificate under Clause  significant alteration to these arrangements and methods shall be 
10 [Employer's Taking Over], the Contractor shall replace the  made without this having previously been notified to the 
damaged item or rectify such damage at its own cost and risk and  Engineer. If the Contract specifies that the Contractor shall design 
shall have no entitlement to make any claim against the Employer  any part of the Permanent Works, then unless otherwise stated 
for any costs so incurred or for any extension to the Time for  in the Particular Conditions: (a) the Contractor shall submit to the 
Completion.  Engineer the Contractor's Documents for this part in accordance 
with the procedures specified in the Contract; (b) these 
4.1.3     The Works shall include any work which is necessary to  Contractor's Documents shall be in accordance with the 
satisfy the Specification, Contractor's proposal and Schedules, or  Specification and Drawings, shall be written in the language for 
is implied by the Contract and all works which (although not  communications defined in Sub‐Clause 1 .4 [Law and Language], 
mentioned in the Contract) are necessary for stability or for the  and shall include additional information required by the Engineer 
completion or safe and proper operation of the Works. to add to the Drawings for co‐ordination of each Party's designs; 
(c) the Contractor shall be responsible for this part and it shall, 
4.1.4     The Contractor shall be responsible for the adequacy,  when the Works are completed, be fit for such purposes for 
stability and safety of all Site operations and of all methods of  which the part is intended as are specified in the Contract; and 
manufacture, fabrication, erection, installation, construction,  (d) prior to the commencement of the Tests on Completion, the 
completion, and execution of the Works and the remedying of  Contractor shall
defects of the Works in accordance with the Contract. Except to  submit to the Engineer the "as‐built" documents and operation 
the extent specified in the Contract,the Contractor (i) shall be  and maintenance manuals in accordance with the Specification 
responsible for all Contractor's Documents, Temporary Works,  and in sufficient detail for the Employer to operate, maintain, 
and such design of each item of Plant and Materials as is required  dismantle, reassemble, adjust and repair this part of the Works. 
for the item to be in accordance with the Contract, and (ii) shall  Such part shall not be considered to be completed for the 
not otherwise be responsible for the design or specification of the  purposes of taking‐over under Sub‐Clause 10.1 [Taking Over of 
Permanent Works unless otherwise stated in the Contract.  the Works and Sections] until these documents and manuals have 
been submitted to the Engineer.
4.1.5     The Contractor shall prior to the commencement of any 
part of the Works and whenever required by the Employer's 
Representative, submit details of the arrangements and methods 
which the Contractor proposes to adopt for the execution and 
completion of such part of the Works (including method 
statements and a statement of how the Contractor plans to 
execute and complete such part of the Works identifying the 
Contractor's Equipment and other resources which the 
Contractor intends to use). No material alteration to these 
arrangements and methods shall be made by the Contractor 
without this having previously been notified to the Employer's 
Representative.

4.1.6     if the Contract specifies that the Contractor shall design 
any part of the Works then: 
(a) the Contractor shall be responsible for the whole of the design 
of that part of the Works and designs such part of the Works as 
stated in the Contract so that such part satisfies the requirements 
stated in the Contract
(b) the Contractor shall integrate and co‐ordinate such design 
with the design of any other part of the Works prepared by or on 
b h lf f h E l di h C h i
behalf of the Employer as stated in the Contract or otherwise as 
instructed by the Employer's Representative; 
(c) the Contractor shall submit to the Employer's Representative 
for his approval the Contractor's Documents for the design of the 
part of the Works in accordance with the procedures and 
requirements stated in Sub ‐Clause 4.28 [Approval Process and 
Requirements]. If such design is instructed by the Employer's 
Representative as a Variation, the Contractor shall within 28 days 
of the Employer's Representative's instruction submit the 
Contractor's Documents for such design for approval in 
accordance with Sub ‐Clause 4.28 [Approval Process and 
Requirements]. The Contractor shall not proceed with the 
relevant work (including the ordering or manufacture of any Plant 
Contractor's General Obligations 

Contractor's General Obligations 
and Materials) until the Employer's Representative has approved 
such design contained in the Contractor's Documents in 
accordance with Sub ‐Clause 4.28 [Approval Process and 
Requirements]; 
(d) the Contractor's Documents shall be in accordance with the 
4.1

4.1
Specification and Drawings and shall unless specified in the  No difference risk on contractor
Contract be written in the language for communications defined 
under sub  Clause 1.4 [Law and Language]. The Contractor's 
Documents shall include such additional information, including 
design criteria, data, calculations and such other information 
requested by the Employer's Representative to add to the 
Drawings for the integration and co‐ordination of the 
Contractor's designs for such part of the Permanent Works with 
the designs of the Permanent Works prepared by or on behalf of 
the Employer, 
(e) the Contractor shall subject to Sub ‐Clause 2.3 [Employer's 
Claims] pay the costs incurred by the Employer resulting from any 
Errors in the design of the part of the Permanent prepared by the 
Contractor; 
(f) the Contractor shall be responsible for the whole design of 
such part of the Works and such part of the Works shall, when 
the whole of the Works are completed, be Fit For Purpose; and
(g) prior to the commencement of the Tests on Completion, the 
Contractor shall submit to the Employer's Representative the "as ‐
built" documents in accordance with Sub ‐Clause 4.25 [As ‐Built 
Documents], the appropriate training in accordance with Sub ‐
Clause 4.26 [Training] and the operation and maintenance 
manuals in accordance with Sub ‐Clause 4.27 [Operation and 
Maintenance Manuals]. Such part shall not be considered to be 
completed for the purposes of taking ‐over under Sub ‐Clause 
10,1 [Taking Over of the Works and Sections] until the Contractor 
has complied with these Sub ‐Clauses. 

4.1.7     The Contractor shall before commencing the relevant 
work (including the ordering or manufacture of any Plant and 
Materials) examine and review the Contract Documents and any 
Drawings or instructions issued by the Employer’s Representative 
and notify the Employer's Representative of any Errors in or 
between any of the Contract Documents and such Drawings or 
instructions. Upon receipt of the said notice, the Employer's 
Representative shall issue instructions under Sub ‐Clause 3.4 
[instructions of the Employer’s Representative].  

4.1.8     The Contractor shall before commencing the relevant 
work (including the ordering or manufacture of any Plant and 
Materials) examine and review the Contract Documents and any 
Drawings or instructions issued by the Employer's Representative 
for any non‐compliance with the Applicable Codes and Standards, 
Permits and Approvals or the applicable . The Contractor shall 
notify the Employer's Representative of such non compliance and 
upon receipt of the said notice the Employer's Representative 
shall issue instructions under Sub ‐Clause 3.4 [Instructions of the 
Employer's Representative]
Employer s Representative]. 

4.1.9     If there are any Errors in the design of any part of the 
Permanent Works prepared by or on behalf of the Employer 
(excluding the design prepared by the Contactor), such design 
shall be rectified or corrected at the Employer’s cost.

4.2.1     Parent Company Guarantee: The Contractor shall obtain (at his cost) a Performance Security 
4.2.1.1      If the Contractor or any of the entities comprising the  for proper performance, in the amount and currencies stated in 
Contractor is a subsidiary of, or owned by,  another company, the  the Appendix to Tender. If an amount is not stated in the 
Contractor shall (at the request of the Employer or Employer's  Appendix to Tender, this Sub Clause shall not apply. The 
Representative) provide the Parent Company Guarantee(s) from  Contractor shall deliver the Performance Security to the Employer 
each ultimate parent company of each entity comprising the  within 28 days after receiving the Letter of Acceptance, and shall 
Contractor and deliver such Parent Company Guarantee(s) to the  send a copy to the Engineer. The Performance Security shall be 
Employer within 14 days of such request and shall send a copy to  issued by an entity and from within a country (or 
the Employer's Representative. otherjurisdiction) approved by the Employer, and shall be in the 
form annexed to the Particular Conditions or in another form 
4.2.1.2     The Employer or Employer's Representative may at any  approved by the Employer. The Contractor shall ensure that the 
time request the financial accounts, records or other financial  Performance Security is valid and enforceable until the 
statement information of such ultimate parent company as is the  Contractor has executed and completed the Works and remedied 
Employer or Employers Representative may consider is  any defects. If the terms of the Performance Security specify its 
reasonably required to confirm the financial strength and stability  expiry date, and the Contractor has not become entitled to 
of the ultimate parent company. receive the Performance Certificate by the date 28 days prior to 
the expiry date, the Contractor shall extend the validity of the 
4.2.1.3     The delivery of such requested Parent Company  Performance Security until the Works have been completed and 
Guarantee(s) shall be a condition precedent to the Employer's  any defects have been remedied. The Employer shall not make a 
obligation to make payment to the Contractor under the Contract. claim under the Performance Security, except for amounts to 
which the Employer is entitled under the Contract in the event of: 
4.2.2     Performance Security (a) failure by the Contractor to extend the validity of the 
4.2.2.1     The Contractor shall obtain (at his cost) a Performance  Performance Security as described in the preceding paragraph, in 
Security in the initial amount calculated Contract Price by the  which event the Employer may claim the full amount of the 
percentage (%) stated in the Appendix to Contract. If a  Performance Security, (b) failure by the Contractor to pay the 
percentage Appendix to Contract, this Sub ‐Clause shall not apply.  Employer an amount due, as either agreed by the Contractor or 
determined under Sub‐Clause 2.5 [Employer's Claims] or Clause 
4.2.2.2     The Contactor shall deliver the Performance Security to  20 [Claims, Disputes and Arbitration], within 42 days after this 
the Employer within 14 days of the Effective date shall send a  agreement or determination, (c) failure by the Contractor to 
the contract add:If 
copy to the Employer's Representative. The Performance Security  remedy a default within 42 days after receiving the Employer's 
the Contract Price 
shall be issued by an entity and from within a country (or other  notice requiring the default to be remedied, or (d) circumstances 
as at the Effective 
jurisdiction) approved by the Employer. The Contractor's  which entitle the Employer to termination under SubClause 15.2 
Date is increased 
compliance with the‐ Sub ‐Clause 4.22 shall be a condition  [Termination by Employer], irrespective of whether notice of 
uarantee and Performance Security 

uarantee and Performance Security 

during the 
precedent to the Employer's obligation to make payment to the  termination has been given. The Employer shall indemnify and 
performance of 
Contractor under the Contract.  hold the Contractor harmless against and from all damages, 
the Works by more 
losses and expenses (including legal fees and expenses) resulting 
than twenty 
4.2.2.3     The Contractor shall ensure that the Performance  from a claim under the Performance Security to the extent to 
percent (20%), the 
Security is valid and enforceable until the Performance Certificate  which the Employer was not entitled to make the claim. The  Performance 
Employer's 
is issued under the Contract in accordance with Sub ‐Clause 11.9  Employer shall return the Performance Security to the Contractor  Certificate :the 
Representative 
[Performance Certificate]. The Contractor shall take all steps  within 21 days after receiving a copy of the Performance  contract: 14 days , 
may request the 
necessary to ensure the Performance Security remains valid and  Certificate. the fidic:  28 days. 
4.2

4.2

Contractor to 
enforceable until the Performance Certificate is issued under the  Performance 
provide a 
Contract in accordance with Sub ‐Clause 11.9 [Performance  Security: the 
replacement 
Certificate] contract: 28 days
Certificate].  contract: 28 days , 

Parent Company Gu

Parent Company Gu
Performance 
the fidic:  21 days.
Security to the 
4.2.2.4     The Employer shall be entitled to make a claim under 
Employer in a sum 
the Performance Security without further notice to the 
equal to the 
Contractor. 
percentage stated 
in the Appendix to 
4.2.2.5     If the Contract Price as at the Effective Date is increased 
Contract 
during the performance of the Works by more than twenty 
multiplied by the 
percent (20%), the Employer's Representative may request the 
adjusted Contract 
Contractor to provide a replacement Performance Security to the 
Price.
Employer in a sum equal to the percentage stated in the 
Appendix to Contract multiplied by the adjusted Contract Price. 
The Contractor shall provide such replacement Performance 
Security to the Employer within ten (10) days of such a request 
from the Employer's Representative.

4.2.2.6     If requested by the Contractor and subject to the terms 
of the Performance Security, the Employer shall return the 
Performance Security to the Contractor within 28 days after 
receiving a copy of the Performance Certificate issued by the 
Employer's Representative in accordance with Sub ‐Clause 11.9 
[Performance Certificate).

4.3.1     The Contractor shall appoint the Contractor's  The Contractor shall appoint the Contractor's Representative and 
Representative and shall give him all authority necessary to act  shall give him all authority necessary to act on the Contractor's 
on the Contractor's behalf under the Contract  behalf under the Contract. Unless the Contractor's 
Representative is named in the Contract, the Contractor shall, 
4.3.2     Unless the Contractor's Representative is named in the  prior to the Commencement Date, submit to the Engineer for 
Appendix to Contract, the Contractor shall, prior to the  consent the name and particulars of the person the Contractor 
Commencement Date, submit to the Employer's Representative  proposes to appoint as Contractor's Representative. If consent is 
for his approval the name and particulars of the person the  withheld or subsequently revoked, or if the appointed person 
Contactor proposes to appoint as Contractor's Representative.  fails to act as Contractor's Representative, the Contractor shall 
The Contractor shall not appoint such person unless the  similarly submit the name and particulars of another suitable 
Employer's Representative has given such approval. The  person for such appointment. The Contractor shall not, without 
Contractor's Representative (including any replacement) shall be  the prior consent of the Engineer, revoke the appointment of the 
qualified and have experience of projects similar in size, scope  Contractor's Representative or appoint a replacement. The whole 
and complexity to the Works. If approval is withheld or  time of the Contractor's Representative shall be given to directing 
subsequently revoked, or if the appointed person fails to act as  the Contractor's performance of the Contract. If the Contractor's 
Contractor's Representative, the Contractor shall similarly submit  Representative is to be temporarily absent from the Site during 
the name and particulars of another suitable person for such  the execution of the Works, a suitable replacement person shall 
appointment to the Employer's Representative for his approval.  be appointed, subject to the Engineer's prior consent, and the 
Engineer shall be notified accordingly. The Contractor's 
4.3.3     The Contractor shall not, without the prior approval of  Representative shall, on behalf of the Contractor, receive 
the Employer's Representative, revoke the appointment of the  instructions under Sub‐Clause 3.3 [Instructions of the 
Contractors Representative or appoint a replacement.  Engineer].The Contractor's Representative may delegate any 
powers, functions and authority to any competent person, and 
4.3.4     The whole time of the Contractor's Representative shall  may at any time revoke the delegation. Any delegation or 
be given to directing the Contractor's performance of the  revocation shall not take effect until the Engineer has received 
Contract If the Contractor's Representative is to be temporanily  prior notice signed by the Contractor's Representative, naming 
absent from the Site during the execution of the Works, a  the person and specifying the powers, functions and authority 
suitable replacement person shall be appointed, subject to the  being delegated or revoked. The Contractor's Representative and 
Contractor's Representative 

Contractor's Representative 

Employer’s Representative's prior approval, and the Employer's  all these persons shall be fluent in the language for 
Representative shall be notified accordingly.  communications defined in Sub‐Clause 1 .4 [Law and Language].

4.3.5     The Contractor's Representative shall, on behalf the 
4.3

4.3

no difference
Contractor, receive instructions under Sub ‐Clause 3.4 
[Instructions of the Employer's Representative]. 

4.3.6     The Contractor's Representative may delegate any 
powers, functions and authority to any competent and 
experienced person, and may at any time revoke the delegation. 
Any delegation or revocation shall not take effect until the 
Employer's Representative has received prior notice signed by the 
Contractor's Representative, naming the person and specifying 
the powers, functions and authority being delegated or revoked. 

437 The Contractor's Representative and all these persons


4.3.7     The Contractor s Representative and all these persons 
shall be fluent (written and oral) in English and in any other 
language for communications defined in Sub ‐Clause 1.4 [Law and 
Language].

4.4.1     The Contractor shall not subcontract the whole of the  The Contractor shall not subcontract the whole of the Works.
works. The Contractor shall be responsible for the acts or defaults of any 
Subcontractor, his
4.4.2     The Contractor shall be responsible for the acts,  agents or employees, as if they were the acts or defaults of the 
omissions or defaults of any Subcontractor, his agents or  Contractor. Unless
employees, as if they were the acts, omissions or defaults of the  otherwise stated in the Particular Conditions:
Contractor. Unless otherwise stat Contract  (a) the Contractor shall not be required to obtain consent to 
(a) the Contractor shall be required to obtain the approval of the  suppliers of Materials,
Employees Representative in respect of suppliers of Plant or  or to a subcontract for which the Subcontractor is named in the 
Materials, unless such are named in the Appendix to Contract or  Contract;
Vendors List  (b) the prior consent of the Engineer shall be obtained to other 
(b) the Contractor shall not be required to obtain the approval of  proposed
the Employer's Representative in respect of Subcontractor  Subcontractors;
providing only labour for the Works;  (c) the Contractor shall give the Engineer not less than 28 days' 
(c) the prior approval of the Employer's Representative shall be  notice of the
obtained to all of the other proposed Subcontractors at the  intended date of the commencement of each Subcontractor's 
request of the Employer's Representative within a reasonable  work, and of the
time so as not to cause delay, impediment or prevention to the  commencement of such work on the Site; and
Contractor, except Subcontractors providing labour for the  (d) each subcontract shall include provisions which would entitle 
Works; (d) the Contractor shall give the Employer's  the Employer to
Representative not less than 28 days' notice of.  require the subcontract to be assigned to the Employer under 
(i) the identity of the proposed Subcontractor and the nature of  Sub‐Clause 4.5
its work; and  [Assignment of Benefit of Subcontract] (if or when applicable) or 
(ii) the intended date of the commencement of each  in the event of
Subcontractor's work and the duration of the work. termination under Sub‐Clause 15.2 [Termination by Employer].
(e) each subcontract shall include provisions which 
(i) may be reasonably necessary to enable the Contractor to fulfil 
its obligations to the Employer under the Contract 
(ii) entitle the Employer to require the Contractor and the 
Subcontractor to consent to the assignment of the subcontract to 
be assigned to the Employer under Sub ‐Clause 4.5 [Assignment 
of Benefit of Subcontract] (if or when applicable) or in the event 
of termination under Sub ‐Clause 15.2 [Termination by Employer] 
or Sub ‐Clause 15.5 [Employees Entitlement to Termination 
(iii) require the Subcontractor (and any employees of the 
Subcontractor) to waive (to the maximum extent permitted by 
Law) any and all claims it (or its employees) may have against the 
Employer for any unpaid sums due to the Contractor under the 
Contract and 
(f) if requested by the Employer at its sole discretion, the 
Contractor shall no later than seven (7) days after the date of 
such request execute and deliver to the Employer a collateral 
warranty from the relevant Subcontractor in favour of the 
Employer and any stakeholders identified in the Appendix to
Employer and any stakeholders identified in the Appendix to 
Contract in the specimen form(s) identified in Schedule 4 or such 
other form as may be approved by the Employer at its sole 
discretion. The Contractor shall deliver a copy of such collateral 
warranty from the relevant Subcontractor to the Employer's 
Representative. If the Contractor does not deliver such collateral 
warranty from the relevant Subcontractor as required by this Sub 
‐Clause then the Employer shall be entitled to withhold payment 
to the Contractor under the Contract for such amount relating to 
that Subcontractor until the Contractor has delivered such 
collateral warranty from the relevant Subcontractor to the 
Employer and the Employer's Representative in accordance with 
this Sub ‐Clause.

4.4.3     The Employer's Representatives approval of a 
Subcontractor under Sub ‐Clause 4.42 shall be obtained in 
accordance with the approval process and requirements set out 
in Sub ‐Clause 423 [Approval Process and Requirements]. At the 
request of the Employer or Employer's Representative, the 
Contractor shall within 21 days of such request deliver a 
complete and executed copy of the subcontract of any 
Subcontractor to the Employer or Employer's Representative. The 
Contractor may redact commercially sensitive information from 
such subcontract prior to delivering the same. 

4.4.4     Any approval, disapproval or any comments made by the 
Employer's Representative (or any failure by the Employer's 
Representative to do any of the foregoing) in this Sub ‐Clause 4.4, 
or Subcontractor appointed by thr contractor from the Vendors 
List or otherwise, shall not affect the Contractor's obligations, 
responsibilities or liabilities under or in connection with the 
Contract 

4.4.5      Before issuing a Payment Certificate which includes an 
amount payable to a Subcontractor, the Employer's 
Representative may request the Contractor to supply reasonable 
evidence that the Subcontractor has received all amounts due in 
Subcontractors

Subcontractors

accordance with previous Payment Certificates, less applicable 
deductions for retention or otherwise.  the contract add 
4.4

4.4

additional 
4.4.6     unless the Contractor  requirements
(a) submits this reasonable evidence to the Employer's 
Representative, or 
(b) (i) satisfies the Employer's Representative in writing that the 
Contractor is reasonably entitled to withhold or refuse to pay 
these amounts, and 
(ii) submits to the Employer's Representative reasonable 
evidence that the Subcontractor has been notified of the 
Contractor's entitlement, 
the Employer shall be entitled to give notice in writing to the 
Contractor that he intends to make such payment directly to the 
Subcontractor. 

4.4.7     If after 14 days of the notice given under Sub ‐Clause 
4.4.6 the payment is still withheld, and the Contractor has failed 
to furnish adequate reason why the payment should be withheld 
from the Subcontractor, the Employer may at its sole discretion, 
except in the event that the Employer knows that the Contractor 
is Insolvent, make such payment to the Subcontractor. Amounts 
paid by the Employer to the Subcontractor may be set‐off or 
deducted from any sums otherwise due from the Contractor in 
accordance with Clause 14 [Contract price and Payment] and/or 
will be a debt due from the Contractor to the Employer. 

4.4.8     Amounts paid by the Employer to the Subcontractor 
pursuant to Sub ‐Clause 4 4 7 may be set‐off or deducted from
pursuant to Sub  Clause 4.4.7 may be set off or deducted from 
any sums otherwise due from the Contractor in accordance with 
Clause 14 [Contract Rice and Payment ] and/or will be a debt due 
from the Contractor to the Employer. 

4.4.9     The Employer shall not, on account of making any such 
payments, assume any responsibility of any nature for the 
sufficiency, adequacy Of contractual compliance of the 
Subcontractor's works and shall not be deemed to have accepted 
such works. These issues shall at all times remain the risk and 
responsibility of the Contractor. Rather, the Employer shall not, 
by making such payments, assume any ongoing responsibility or 
liability to make any further or additional direct payments to any 
Subcontractors.  In the event that the Employer makes a payment 
to a Subcontractor in accordance with Sub ‐Clause 4.4.7, the 
Contractor shall indemnify the Employer in respect of any sums 
so paid (including in circumstances where it is subsequently 
proven that the Subcontractor was not in fact entitled to such 
sums). 

4.4.11      Irrespective of whether or not the Employer elects to 
make direct payments to any Subcontractor in accordance with 
Sub ‐Clause 4.4.7, such election to either pay or not pay, and the 
consequences that may arise as a result of such election, shall not 
entitle the Contractor to any additional payments under the 
Contract and shall not entitle the Contractor to any extension to 
the Time for Completion.

4.5.1     If a Subcontractor's obligations extend beyond the expiry   If a Subcontractor's obligations extend beyond the expiry date of 
date of the relevant Defects Notification Period and the  the relevant Defects Notification Period and the Engineer, prior 
Employer's Representative, prior to this date, instructs the  to this date, instructs the Contractor to
Contractor to assign the rights and benefit of such obligations of  assign the benefit of such obligations to the Employer, then the 
the subcontract to the Employer, then the Contractor shall do so  Contractor shall do
by executing (and procuring that such Subcontractor executes)  so. Unless otherwise stated in the assignment, the Contractor 
the assignment agreement in the specimen forrm set out in  shall have no liability to
Schedule 4 within 14 days of the date of such request Unless  the Employer for the work carried out by the Subcontractor after 
otherwise stated in the assignment agreement, the Contractor  the assignment
shall have no liability to the Employer for any work carried out by  takes effect.
the Subcontractor after the assignment agreement takes effect in 
Assignment of Subcontract 

Assignment of Subcontract 

accordance with its terms but the Contractor shall continue to 
remain liable for any work carried out by the Subcontractor prior 
to the assignment agreement taking effect 
risk removed from 
4.5

4.5

no difference
4.5.2     In the event of termination under Sub ‐Clause 15.2  contractor
[Termination by Employer] or Sub ‐Clause 15.5 [Employer's 
Entitlement to Termination], the Employer may at its sole 
discretion request that the Contractor assigns, transfers or 
novates any subcontract to the Employer or any third party 
notified to the Contractor. The Contractor shall execute (and shall 
procure that such Subcontractor executes) the assignment 
p ) g
agreement in the form set out in Schedule 4 within 14 days of the 
date of such request.

4.6.1     The Contractor shall allow appropriate opportunities for  The Contractor shall, as specified in the Contract or as instructed 
carrying out work to: by the Engineer,
(a)the Employer's Personnel,  allow appropriate opportunities for carrying out work to:
(b) any other contractors, consultants, operators or other entities  (a) the Employer's Personnel,
or persons employed by the Employer, and  (b) any other contractors employed by the Employer, and
(c) the personnel of any Authorities,  (c) the personnel of any legally constituted public authorities,
who may be employed in the execution on or near the Site of any  who may be employed in the execution on or near the Site of any 
work not included in the contract. work not included
in the Contract.
4.6.2     The Contractor shall be responsible for co‐ordinating,  Any such instruction shall constitute a Variation if and to the 
interfacing and integrating his activities on site with those of the  extent that it causes the
parties referred to in Sub ‐Clause 4.6.1 (a), (b) and (c). The  Contractor to incur Unforeseeable Cost. Services for these 
Contractor shall allow such parties are use of the Contractor's  personnel and other
existing facilities and utilities on the Site at no additional cost to  contractors may include the use of Contractor's Equipment, 
the Employer. Temporary Works or
access arrangements which are the responsibility of the 
4.6.3     The Contractor shall subject to Sub ‐Clause 2.3  Contractor.
[Employees Claims] pay to the Employer any costs incurred by the  If, under the Contract, the Employer is required to give to the 
Employer as a result of any prevention, hindrance, interference or  Contractor possession
delay to the parties referred to under Sub‐ Clause 4.6.1 (a), (b) or  of any foundation, structure, plant or means of access in 
(c) which may be caused by the Contractor or any of the  accordance with
Contractor's Personnel. Any costs incurred by the Employer and  Contractor's Documents, the Contractor shall submit such 
payable by the Contractor under this Sub ‐Clause shall be in  documents to the
addition to any delay damages payable by the Contractor or such  Engineer in the time and manner stated in the Specification.
other amounts stated under Sub ‐Clause 8.7 [Delay Damages]. 

4.6.4      If the Contractor is prevented, hindered, suffers 
interference or is delayed as a result of the entities or persons 
referred to in Sub ‐Clause 4.6,1 (a), (b) or (c), or as a result of 
complying with this Sub ‐Clause 4.6, and such prevention, 
hindrance, interference or delay is Unforeseeable, and the 
Contractor suffers delay in completion of the Works or a Section 
for the purposes of Sub ‐Clause 10.1 [Taking Over of the Works 
the contract add: if 
and Sections] within the relevant Time for Completion and/or 
the delay is caused 
incurs Cost as a result of the same, the Contractor shall give 
by the contractor , 
notice to the Employer's Representative of such prevention, 
the Contractor 
hindrance, interference or delay and shall give a further notice to 
shall not be 
the Employer's Representative and shall be entitled, subject to 
entitled to any 
Sub ‐Clause 20.1 [Contractor's Claims], to: 
Co‐operation

Co‐operation

extension of the 
(a) an extension of time for any such delay, if completion is or will 
Time for 
4.6

4.6

be delayed under Sub ‐Clause 8.4 [Extension of Time for  No difference
Completion or any 
Completion and of Milestone Dates]; and 
Milestone Date 
(b) payment of any such Cost shall be added to the Contract Price. 
nor additional 
payment in 
4.6.5      After receiving this notice, the Employer's Representative 
respect of such 
shall proceed in accordance with Sub ‐Clause 3.6 
Cost or any other 
[Determinations] to agree or determine (i) if the Contractor has 
adjustment to the 
been prevented, hindered, suffered interference or been delayed 
Contract Price.
as a result of the entities or persons referred to in Sub ‐Clause 
4.6.1 (a), (b) or (c and (ii) the matters described in Sub ‐Clause 
4.6.4 (a) and (b) above. 

4.6.6     However, if and to the extent that such prevention, 
hindrance, interference or delay (as referred to in Sub ‐Clause 
4.6.4) was caused by: (i) any error or delay by the Contractor, 
including an error in, or delay in the submission of, any of the 
Contractor's Documents; or (ii) a failure to submit a prograrmme 
or revised programme under Sub‐Clause 8.3 [Programme]; or (iii) 
any breath by the Contractor of this Sub ‐Clause 4.6 [Co‐
operation]; or (iv) any other default, breath or negligence of the 
Contactor or any omission or default by the Contractor's 
Personnel, the Contractor shall not be entitled to any extension 
of the Time for Completion or any Milestone Date nor additional 
payment in respect of such Cost or any other adjustment to the 
Contract Price.
4.7.1     The Contractor shall set out the Works in relation to  The Contractor shall set out the Works in relation to original 
original points, lines and levels of reference specified in the  points, lines and levels of reference specified in the Contract or 
Contract or notified by the Employer’s Representative. The  notified by the Engineer. The Contractor shall be
Contractor shall be responsible for the correct positioning of all  responsible for the correct positioning of all parts of the Works, 
parts of the Works, and shall rectify any error in the positions,  and shall rectify any
levels, dimensions or alignment of the Works.  error in the positions, levels, dimensions or alignment of the 
Works.
4.7.2     The Employer shall be responsible for any errors in these  The Employer shall be responsible for any errors in these 
specified or notified items of reference, but the Contractor shall  specified or notified items of
take such reasonable steps as are required to verify their  reference, but the Contractor shall use reasonable efforts to 
accuracy before they are used.  verify their accuracy
before they are used.
4.7.3     If the Contractor suffers delay and/or incurs Cost from  If the Contractor suffers delay and/or incurs Cost from executing 
executing work which was necessitated by an error in these items  work which was
of reference , and an experienced, prudent contractor exercising  necessitated by an error in these items of reference, and an 
the Standard of Care could not reasonably have discovered such  experienced contractor
error and avoided this delay and/or Cost, the Contractor shall  could not reasonably have discovered such error and avoided this 
give notice to the Employer’s Representative of such error and  delay and/or Cost,
Setting Out 

Setting Out 

shall give a further notice to the Employer’s Representative and  the Contractor shall give notice to the Engineer and shall be 
shall be entitled subject to Sub ‐Clause 20.1 [Contractor's Claims]  entitled subject to SubClause 20.1 [Contractor's Claims] to:
4.7

4.7

No difference
to:  (a) an extension of time for any such delay, if completion is or will 
(a) an extension of time for any such delay, if completion is or will  be delayed,
be delayed under Sub ‐Clause 8.4 [Extension of time for  under Sub‐Clause 8.4 [Extension of Time for Completion], and
Completion and of Milestone dates]; and  (b) payment of any such Cost plus reasonable profit, which shall 
(b) payment of any such Cost, which shall be added to the  be included in the
Contract Price.  Contract Price.
After receiving this notice, the Engineer shall proceed in 
4.7.4      After receiving this notice, the Employer’s Representative  accordance with SubClause 3.5 [Determinations] to agree or 
shall proceed in accordance with Sub Clause 3.6 [Determinations]  determine (i) whether and (if so) to what extent
to agree or determine (i) whether and (if so) to what extent the  the error could not reasonably have been discovered, and (ii) the 
error could not reasonably have been discovered by an  matters described
experienced, prudent contractor exercising the Standard of Care  in sub‐paragraphs (a) and (b) above related to this extent.
and (ii) matters described in Sub ‐Clause 4.7.3 (a) and (b).

The Contractor shall:  The Contractor shall:
(a) comply with all applicable Authorities safety regulations and  (a) comply with all applicable safety regulations,
the Employer’s Health and Safety Policy, (b) take care for the safety of all persons entitled to be on the 
(b) take care for the safety of all entities or persons entitled to be  Site,
on the Site, (c) use reasonable efforts to keep the Site and Works clear of 
(c)use reasonable efforts to keep the Site and works clear of  unnecessary
unnecessary obstruction so as to avoid danger to these persons, obstruction so as to avoid danger to these persons,
(d) provide fencing, lighting, guarding and watching of the Works  (d) provide fencing, lighting, guarding and watching of the Works 
Safety Procedures 

Safety Procedures 

until completion and taking over of the whole of the Works under  until completion
Clause 10 [Employer's Taking Over], and and taking over under Clause 10 [Employer's Taking Over], and
(e) provide any Temporary Works (including roadways, footways,  (e) provide any Temporary Works (including roadways, footways, 
4.8

4.8

No difference
guards and fences) which may be necessary for the execution and  guards and
completion of the Works and the remedying of any defects in the fences) which may be necessary, because of the execution of the 
Works in accordance with the Contract, for the use and  Works, for
protection of the public and of owners and the use and protection of the public and of owners and occupiers 
occupiers of adjacent land. of adjacent
land.
4.9.1     The Contractor shall institute a quality assurance system  The Contractor shall institute a quality assurance system to 
to demonstrate compliance with the requirements of the  demonstrate compliance with
Contract. The system shall be in accordance with the details  the requirements of the Contract. The system shall be in 
stated in the Contract. The Employer and any representatives for  accordance with the details
and on behalf of the Employer and the Employer’s Representative  stated in the Contract. The Engineer shall be entitled to audit any 
shall be entitled to audit any aspect of the system during the  aspect of the system.
normal working hours under Sub ‐Clause 6.5 [Working Hours].  Details of all procedures and compliance documents shall be 
submitted to the
4.9.2     Details of all procedures and compliance documents shall  Engineer for information before each design and execution stage 
be submitted to the Employer’s Representative for information  is commenced.
before each design and execution stage is commenced. When any  When any document of a technical nature is issued to the 
document of a technical nature is issued to the Employer’s  Engineer, evidence of the
Representative, evidence of the prior approval by the Contractor  prior approval by the Contractor himself shall be apparent on the 
Quality Assurance 

Quality Assurance 
himself shall be stamped, signed, dated and made apparent on  document itself.
the document itself.  Compliance with the quality assurance system shall not relieve 
4.9

4.9
the Contractor of any No difference
4.9.3     Compliance with the quality assurance system shall not  of his duties, obligations or responsibilities under the Contract.
relieve the Contractor of any of his duties, obligations, 
responsibilities or liabilities under the Contract

4.10.1     The Contractor warrants, undertakes and represents to  The Employer shall have made available to the Contractor for his 
the Employer that it has satisfied itself and obtained all necessary  information, prior to
information as to risks, contingencies, matters and other  the Base Date, all relevant data in the Employer's possession on 
circumstances which may influence or affect the completion and  sub‐surface and
execution of the Works and the remedying of defects of the  hydrological conditions at the Site, including environmental 
Works in accordance with the Contract. The Employer does not  aspects. The Employer shall similarly make available to the 
warrant the sufficiency, accuracy or validity of the Site  Contractor all such data which come into the
Information or any other data provided to the Contractor by or  Employer's possession after the Base Date. The Contractor shall 
on behalf of the Employer and the Contractor shall have no claim  be responsible for the contract :risk 
against the Employer for any cost, loss or damage (including  interpreting all such data. on contractor ,the 
delay) suffered by the Contractor on account of relying on the  To the extent which was practicable (taking account of cost and  fidic:risk on 
Site Information or other data provided by or on behalf of the  time), the Contractor employer’s 
Contractor.  shall be deemed to have obtained all necessary information as to  representative 
risks, contingencies and
4.10.2      The Contractor shall be deemed to have inspected and  other circumstances which may influence or affect the Tender or 
examined the (i) Site, Enabling Works and Existing Works (if any)  Works. To the same
and their surroundings; (ii) the Site Information; (iii) publicly  extent, the Contractor shall be deemed to have inspected and 
available information in the Country; and (iv) other information  examined the Site, its
which an experienced, prudent contractor exercising the  surroundings, the above data and other available information, 
Standard of Care could reasonably be expected to have or to  and to have been satisfied
obtain and to have satisfied itself (and the Contractor  before submitting the Tender as to all relevant matters, including 
acknowledges and warrants undertakes and represents to the  (without limitation):
Employer that it has satisfied itself) before entering into the  (a) the form and nature of the Site, including sub‐surface 
Contract as to all relevant matters, including (without limitation):  conditions,
(a) the form and nature of the Site, Enabling Works and Existing  (b) the hydrological and climatic conditions,
Works (if any) and their surroundings, including sub ‐surface,  (c) the extent and nature of the work and Goods necessary for 
geological and geo‐technical conditions,  the execution and
(b) the hydrological, environmental and climatic conditions, completion of the Works and the remedying of any defects,
(c) the extent and nature of the work and Goods necessary for  (d) the Laws, procedures and labour practices of the Country, and
the execution and completion of the Works and the remedying of  (e) the Contractor's requirements for access, accommodation, 
any defects in the Works,  facilities, personnel,
Site Data

Site Data
4.10

4.10

(d) the Laws, procedures and labour practices of the Country, and  power, transport, water and other services.
(e) the Contractor's requirements for access, accommodation, 
facilities, personnel power transport water and other services 
necessary for the execution and completion of the Works and the 
remedying of any defects in the Works. 

4.10.3     Except as otherwise stated in the Contract 
(a) the Contractor shall be deemed to have obtained all necessary 
information as to risks, contingencies, matters and other 
circumstances which may influence or affect the completion and 
execution of the Works in accordance with the Contract;
execution of the Works in accordance with the Contract; 
(b) by executing the Contract, the Contractor accepts total 
responsibility for having foreseen all risks, difficulties and costs of 
completing and executing the Works and remedying of defects in 
the Works in accordance with the Contract and 
(c) the Contract Price, the Time for Completion and any Milestone 
Date shall not be extended or adjusted to take account of any 
unforeseen risks, difficulties or costs and nor shall the Contractor 
be entitled to any additional payment from the Employer to deal 
with such unforeseen risks, difficulties or costs.

4.11.1     The Contractor shall be deemed to:  The Contractor shall be deemed to (a) have satisfied himself as to 
(a) have satisfied himself (and the Contractor acknowledges and  the correctness and sufficiency of the Accepted Contract Amount, 
warrants, undertakes and represents to the Employer that it has  and (b) have based the Accepted Contract Amount on the data, 
satisfied itself) as to the correctness and sufficiency of the  interpretations, necessary information, inspections, examinations 
Contract Price, and  and satisfaction as to all relevant matters referred to in Sub‐
Sufficiency of the Contract Price

Sufficiency of the Contract Price
(b) have based the Contract Price on the data, interpretations,  Clause 4.10 [Site Data]. Unless otherwise stated in the Contract, 
necessary information, inspections, examinations and satisfaction  the Accepted Contract Amount covers all the Contractor's 
as to all relevant matters referred to in Sub ‐Clause 4.10 [Site  obligations under the Contract (including those under Provisional 
Data] and any further data relevant to the Contractor's design (if  Sums, if any) and all things necessary for the proper execution 
any). and completion of the Works and the remedying of any defects.
4.11

4.11

No difference
4.11.2      Except as otherwise stated in the Contract, the Contract 
Price covers all the Contractor's obligations under the Contract 
and all things necessary for the execution and completion of the 
Works and the remedying of any defects in the Works in 
accordance with the Contract.

4.12.1      In this Sub ‐Clause, "physical conditions" means physical  In this Sub‐Clause, "physical conditions" means natural physical 
conditions (whether natural or man‐made) and other physical  conditions and man made and other physical obstructions and 
obstructions, hydrological, environmental conditions at the Site  pollutants, which the Contractor
except weather conditions or conditions due to weather  encounters at the Site when executing the Works, including sub‐
conditions or any part of the Works themselves which the  surface and hydrological conditions but excluding climatic 
Contractor encounters when he is executing the Works under and  conditions.
in accordance with the Contract.  If the Contractor encounters adverse physical conditions which 
he considers to have been
4.12.2      If the Contractor encounters adverse physical  Unforeseeable, the Contractor shall give notice to the Engineer as 
conditions which are Unforeseeable, the Contractor shall give  soon as practicable.
notice to the Employer’s Representative as soon as practicable  This notice shall describe the physical conditions, so that they can 
and in any event within 21 days of encountering such adverse  be inspected by
physical conditions. The Contractor's notice shall describe the  the Engineer, and shall set out the reasons why the Contractor 
physical conditions, so that they can be inspected by the  considers them to be
Employer’s Representative, and shall set out the reasons why the  Unforeseeable. The Contractor shall continue executing the 
Contractor considers them to be Unforeseeable. The Contractor  Works, using such proper
shall continue to execute the Works under the Contract, using the  and reasonable measures as are appropriate for the physical 
proper measures as are appropriate for the physical conditions,  conditions, and shall
and shall comply with any instructions which the Employer's  comply with any instructions which the Engineer may give. If an 
Representative may give under Sub ‐Clause 3.4 [Instructions of  instruction constitutes
the Employer's Representative].  a Variation, Clause 13 [Variations and Adjustments] shall apply.
If and to the extent that the Contractor encounters physical
If and to the extent that the Contractor encounters physical 
4.12.3      If the arrangements and methods previously notified to  conditions which are Unforeseeable, gives such a notice, and 
the Employer's Representative under Sub ‐Clause 4.1  suffers delay and/or incurs Cost due to these conditions,
[Contractor's General Obligations] need to be altered as a result  the Contractor shall be entitled subject to Sub‐Clause 20.1 
of the adverse physical conditions the Contractor shall, as soon as  [Contractor's Claims] to:
practicable and in any event within 21 days of encountering such  (a) an extension of time for any such delay, if completion is or will 
adverse physical conditions submit details of the altered  be delayed,
arrangements and methods which the Contractor intends to  under Sub‐Clause 8.4 [Extension of Time for Completion], and
adopt for the execution and completion of the Works, including  (b) payment of any such Cost, which shall be included in the 
method statements and a statement of how the Contractor plans  Contract Price.After receiving such notice and inspecting and/or 
to execute and complete the Works identifying the Contractor's  investigating these physical
Equipment and other resources which the Contractor intends to  conditions, the Engineer shall proceed in accordance with Sub‐
use for the execution and completion of the Works to reflect such  Clause 3.5
adverse physical conditions.  [Determinations] to agree or determine (i) whether and (if so) to 
what extent these
4.12.4     If and to the extent that the Contractor encounters  physical conditions were Unforeseeable, and (ii) the matters 
adverse physical conditions which are Unforeseeable, the  described in subparagraphs (a) and (b) above related to this 
Contractor has given the relevant notice(s) as required by Sub ‐ extent.
Clause 4.12.2, and is not otherwise in default of this Sub ‐Clause  However, before additional Cost is finally agreed or determined 
4.12 [Unforeseeable Physical Conditions] and suffers delay  under subparagraph (ii), the Engineer may also review whether 
and/or incurs Cost due to these conditions, the Contractor shall  other physical conditions in
give a further notice to the Employer's Representative ' and  similar parts of the Works (if any) were more favourable than 
entitled subject to Sub  Clause 20.1 [Contractor's Claims] to: could reasonably have
(a) an extension of time for any such delay, if completion is or will  been foreseen when the Contractor submitted the Tender. If and 
be delayed under Sub Clause 8.4 [Extension of Time for  to the extent that
Completion and of Milestone Dates]; and  these more favourable conditions were encountered, the 
(b) payment of any such Cost, which shall be added to the  Engineer may proceed in
Contract Price.  accordance with Sub‐Clause 3.5 [Determmations] to agree or 
determine the
4.12.5     After receiving such notices and inspecting and/or  reductions in Cost which were due to these conditions, which 
investigating these physical conditions, the Employer's  may be included (as
Representative shall proceed in accordance with Sub ‐Clause 3.6  deductions) in the Contract Price and Payment Certificates. 
[Determinations] to agree or determine (i) whether and Of so) to  However, the net effect of
what extent these physical conditions were Unforeseeable, and  all adjustments under sub‐paragraph (b) and all these reductions, 
(i) the matters described in Sub ‐Clause 4.12.4 (a) and (b).  for all the physical
conditions encountered in similar parts of the Works, shall not 
Unforeseeable Physical Conditions

Unforeseeable Physical Conditions

4.12.6     However, before any extension to the Time for  result in a net reduction
Completion or to any Milestone Date or any additional Cost is  in the Contract Price.
finally agreed or determined under Sub ‐Clause 4.12.4 (a) and (b),  The Engineer may take account of any evidence of the physical 
the Employer's Representative may also review whether other  conditions foreseen
physical conditions in similar parts of the Works (if any) were  by the Contractor when submitting the Tender, which may be 
4.12

4.12

more favourable than those in the Site Information. The  made available by the No difference risk on employer


Contractor shall supply records and such other information as the  Contractor, but shall not be bound by any such evidence.
Employer's Representative requires so the Employer's 
Representative may carry out this review. If and to the extent 
that these more favourable conditions were encountered, the 
Employer's Representative may proceed in accordance with Sub ‐
Clause 3.6 [Determinations] to agree or determine any 
reasonable reductions in the extension to the Time for 
Completion or to any Milestone Date or any reasonable 
deductions of any additional Cost otherwise due to these physical 
conditions, which may be included as reductions in the Time for 
Completion and/or Milestone Dates and/or deductions in the 
Contract Price and the Payment Certificates for the purpose of 
achieving a financial equilibrium between the Parties which 
reflects local construction industry norms. However, the net 
effect of all adjustments under Sub ‐Clause 4.12.4 (a) and/or (b) 
and at of these reductions or deductions, as the case may be, for 
all the physical conditions encountered in similar parts of the 
Works shall not result in a net reduction in the Time for 
Completion or to any Milestone Date or a deduction in the 
Contract Price 
The Contractor

4.12.7     In judging to what extent the physical conditions were 
Unforeseeable, the Contractor is assumed to have taken into 
4

account 
(a) the Site Information; 
(b) publicly available information in the Country; 
(c) information obtainable from a visual inspection of the Site and 
its surroundings; and 
(d) other information which an experienced, prudent contractor 
could reasonably expected to have or to obtain had it exercised 
the Standard of Care,
 and only the difference between the physical conditions 
encountered and those for which it would have been reasonable 
to have allowed is taken into account in determining any such 
extension to the Time for Completion or to any Milestone Date or 
any additional Cost, as the case may be. 

4 12 8 Thi S b Cl 4 12 [U f bl Ph i l
4.12.8     This Sub ‐Clause 4.12 [Unforeseeable Physical 
Conditions] shall not affect the Contractor's rights and remedies 
under Sub ‐Clause 424 [Fossils].

The Contractor shall bear all costs and charges for special and/or  The Contractor shall bear all costs and charges for special and/or 
temporary rights of‐way which he may require, including those  temporary rights of‐way which he may require, including those 
Rights of Way and Facilities

for access to the Site. The Contractor shall also obtain, at his risk  Rights of Way and Facilities for access to the Site. The Contractor shall also obtain, at his risk 


and cost, any additional facilities outside the Site which he and cost, any additional facilities outside the Site which he may 
may require for the purposes of the Works and in connection  require for the purposes of the Works.
4.13

4.13

with the contract. no difference

4.14.1     The Contractor shall not interfere unnecessarily or  The Contractor shall not interfere unnecessarily or improperly 
improperly with: with:
(a) the convenience of the public, or (a) the convenience of the public, or
(b) the access to and use and occupation of all roads and  (b) the access to and use and occupation of all roads and 
footpaths, irrespective of whether they are public or in the  footpaths, irrespective of whether they are public or in the 
possession of the Employer or of possession of the Employer or of
Avoidance of Interference

Avoidance of Interference

others. others.
The Contractor shall indemnify and hold the Employer harmless 
4.14.2     The Contractor shall indemnify and hold the Employer  against and from all
4.14

4.14

harmless against and from all losses resulting from any such  damages, losses and expenses (including legal fees and expenses)  No difference


unnecessary or improper interference. resulting from any
such unnecessary or improper interference.

4.15.1     The Contractor shall be deemed to have been satisfied  The Contractor shall be deemed to have been satisfied as to the 
as to the suitability and availability of access routes to and from  suitability and
the Site. The Contractor shall prevent any road, bridge or other  availability of access routes to the Site. The Contractor shall use 
structure from being damaged by the Contractor's traffic or by  reasonable efforts to
the Contractor's Personnel or otherwise being damaged in  prevent any road or bridge from being damaged by the 
connection with the execution and completion of the Works and  Contractor's traffic or by the
the remedying of defects in the Works. These efforts shall include  Contractor's Personnel. These efforts shall include the proper use 
the proper use of appropriate vehicles and routes having regard  of appropriate
to the size, scope and complexity of the Works. vehicles and routes.
Except as otherwise stated in these Conditions:
4.15.2    Except as otherwise stated in the Contract:  (a) the Contractor shall (as between the Parties) be responsible 
(a) the Contractor shall (as between the Parties) be responsible  for any
for any maintenance which may be requited for his use of access  maintenance which may be required for his use of access routes;
routes and for repairing any damage to any highway, bridge or  (b) the Contractor shall provide all necessary signs or directions 
other structure as a result of the Contractor's traffic or by the  along access
Contractor's Personnel or for moving of loads or otherwise being  routes, and shall obtain any permission which may be required 
damaged in connection with the execution and completion of the  from the
Works and the remedying of defects in the Works;  relevant authorities for his use of routes, signs and directions;
(b) the Contractor shall provide all necessary signs or directions  (c) the Employer shall not be responsible for any claims which 
along access routes, and shall obtain any permission which may  may arise from the
be required from the relevant authorities or owner for his use of  use or otherwise of any access route, (d) the Employer does not 
routes, signs and directions;  guarantee the suitability or availability of particular
, g ; g y y p
(c) the Employer shall not be responsible for any claims which  access routes, and
may arise from the use or otherwise of any access route, (e) Costs due to non‐suitability or non‐availability, for the use 

Access Route

Access Route
(d) the Employer does not warrant or give any representations  required by the
nor give any guarantees as to the suitability or availability of  Contractor, of access routes shall be borne by the Contractor.
4.15

4.15
No difference risk on contractor
particular access routes, and 
(e) Costs due to non ‐suitability or non  availability, for the use 
required by the Contractor, of access routes shall be borne by the 
Contractor. 

4.15.3      The Contactor shall indemnify and hold the Employer 
harmless against and from all Losses resulting from the special 
protection or strengthening of such highway, bridge or other 
structure and from any road, bridge or other structure from being 
damaged by the Contractor's traffic or by the Contractor's 
Personnel or otherwise being damaged in connection with the 
execution and completion of the Works and the remedying of 
defects in the Works.

Unless otherwise stated in the Particular Conditions: Unless otherwise stated in the Particular Conditions:
(a) the Contractor shall give the employer’s representative not  (a) the Contractor shall give the Engineer not less than 21 days' 
less than 14 days' notice of the date on which any Plant or a  notice of the date on which any Plant or a major item of other 
major item of other Goods will be delivered to the Site; Goods will be delivered to the Site;
(b) the Contractor shall be responsible for packing, loading,  (b) the Contractor shall be responsible for packing, loading, 
transporting, receiving, unloading, storing and protecting all  transporting, receiving, unloading, storing and protecting all 
Goods and other things required for the Works; and Goods and other things required for the Works; and
(c) the Contractor shall indemnify and hold the Employer  (c) the Contractor shall indemnify and hold the Employer 
Transport of Goods

Transport of Goods

harmless against and from all damages, losses and expenses  harmless against and from all damages, losses and expenses 
(including legal fees and expenses) resulting from the transport of  (including legal fees and expenses) resulting from the transport of  the contract: 14 
4.16

4.16

Goods, and shall negotiate and pay all claims Goods, and shall negotiate and pay all claims days , the fidic:  21 


arising from their transport. arising from their transport. days 

The Contractor shall be responsible for all Contractor's  The Contractor shall be responsible for all Contractor's 
Equipment. When brought on to the Site, Contractor's Equipment  Equipment. When brought on to the Site, Contractor's Equipment 
shall be deemed to be exclusively intended for the execution of  shall be deemed to be exclusively intended for the execution of 
the Works. The Contractor shall not remove from the Site any  the Works. The Contractor shall not remove from the Site any 
Contractor's Equipment

Contractor's Equipment

major items of Contractor's Equipment without the consent of  major items of Contractor's Equipment without the consent of 
the employer’s representative. However, consent shall not be  the employer’s representative. However, consent shall not be 
required for vehicles transporting Goods or Contractor's  required for vehicles transporting Goods or Contractor's 
4.17

4.17

No difference
Personnel off Site. Personnel off Site.
4.18.1      The Contractor shall prevent any damage to the  The Contractor shall take all reasonable steps to protect the 
environrnent (both on and off the Site) and shall limit damage  environment (both on and off the Site) and to limit damage and 
and nuisance to people and property resulting from pollution,  nuisance to people and property resulting from
noise and other results of his operations. The Contractor shall  pollution, noise and other results of his operations.
indemnify and hold the Employer harmless against and from all  The Contractor shall ensure that emissions, surface discharges 
Losses resulting from any damage to the environment and  and effluent from the
nuisance to people and property resulting from pollution, noise  Contractor's activities shall not exceed the values indicated in the 
and other results of his operations.  Specification, and
shall not exceed the values prescribed by applicable Laws.
4.18.2     The Contractor shall ensure that missions, surface 
discharges and effluent from the Contractor's activities shall not 
exceed the values indicated in the Contract and shall not in any 
event exceed the values prescribed by applicable Laws. The  the contract add: 
Contractor shall indemnify and hold the Employer harmless  The Contractor 
against and from all Losses and Indirect Losses resulting from the  shall indemnify 
emissions, surface discharges and effluent from the Contractor's  and hold the 
Protection of the Environment

Protection of the Environment
activities exceeding the values prescribed by applicable Laws.  Employer harmless 
against and from 
4.18.3      On or before the Commencement Date, the Contractor  all Losses and 
shall notify any Authority (including any local government  Indirect Losses 
4.18

4.18
Authorities) responsible for the administration of any  No difference resulting from the 
environmental Laws that it has, or will be taking control of (and  emissions, surface 
shall be responsible for) the Works from the Commencement  discharges and 
Date until the Time for Completion. This notice shall also request  effluent from the 
that the relevant Authority liaises directly with the Contractor on  Contractor's 
all matters relating to environmental compliance on and  activities 
immediately around the Site during this time, and while the  exceeding the 
contractor is performing any Works on or around the Site. The  values prescribed 
Contractor shall promptly provide copies of all such notices  by applicable Laws
issued, as well as any responses received from any Authorities, to 
the Employer's Representative.

The Contractor shall be responsible for, and shall bear all Costs  The Contractor shall, except as stated below, be responsible for 
associated with, the provision of all power, water ,gas and other  the provision of all  power, water and other services he may 
services and utilities he may require to execute and complete the  require. The Contractor shall be entitled to use for the purposes 
Works and to remedy any in the Works or as may be otherwise  of the Works such supplies
required by the Contractor to perform and discharge his  of electricity, water, gas and other services as may be available on 
obligations under or in connection with the Contract until the  the Site and of which details and prices are given in the 
Electricity, Water and Gas

Electricity, Water and Gas

whole of the Works are taken over by the Employer under Sub ‐ Specification. The Contractor shall, at his risk and cost, provide 
Clause 10.1 [Taking Over of the Works and Sections], except in  any apparatus necessary for his use of these services and for 
respect of permanent power required for commissioning  measuring the quantities consumed. The quantities consumed 
4.19

4.19

purposes, which shall be the risk and responsibility of the  and the amounts due (at these prices) for such services shall be  No difference


Employer. For the avoidance of doubt the Contractor will  agreed or determined by the Engineer in accordance with Sub‐
however be responsible for the provision of any temporary  Clause 2.5 [Employer's Claims] and Sub‐Clause 3.5 
utilities that may be required for testing purposes. [Determinations]. The Contractor shall pay
these amounts to the Employer.

4.20.1     The Employer may make the Employer's Equipment, if  The Employer shall make the Employer's Equipment (if any) 
any, available for the use by the Contractor in the execution and  available for the Contractor in the execution of the Works in 
completion of the Works in accordance with such details,  accordance with the details, arrangements
arrangements and prices notified to the Contractor by the  and prices stated in the Specification. Unless otherwise stated in 
Employer or the Employer's Representative (as the case may be).  the Specification:
The Employer shall not be responsible for any defect in or  (a) the Employer shall be responsible for the Employer's 
inadequacy of the Employer's Equipment, nor does the Employer  Equipment, except that (b) the Contractor shall be responsible for 
give any representation or warranty, either express or implied, in  each item of Employer's Equipment
respect of the suitability of the Employer's Equipment. The  whilst any of the Contractor's Personnel is operating it, driving it, 
Contractor shall be responsible for each item of Employer's  directing it or
Equipment whilst any of the Contractor's Personnel is operating  in possession or control of it.
it, driving it, directing it or in possession or control of it. The appropriate quantities and the amounts due (at such stated 
prices) for the use of
4.20.2     The Contractor shall use the Employer's Equipment at its  Employer's Equipment shall be agreed or determined by the 
own risk and shall indemnify and hold the Employer harmless  Engineer in accordance
against and from all Losses arising out of the Contractor and the  with Sub‐Clause 2.5 [Employer's Claims] and Sub‐Clause 3.5 
Contractor's Personnel use of the Employer's Equipment [Determinations]. The
Contractor shall pay these amounts to the Employer.
4.20.3     The appropriate quantities to be provided and the  The Employer shall supply, free of charge, the "free‐issue 
d f h C ( h d i )f h i l " (if )i
amounts due from the Contractor (at such stated prices) for the  materials" (if any) in
use of Employer's Equipment shall be agreed or determined by  accordance with the details stated in the Specification. The 
the Employer's Representative in accordance with Sub ‐Clause 2.3  Employer shall, at his risk
[Employer's Claims] and Sub ‐Clause 3.6 [Determinations]. The  and cost, provide these materials at the time and place specified 
Contractor shall pay these amounts to the Employer without any  in the Contract. The
deduction or set‐off. Contractor shall then visually inspect them, and shall promptly 
give notice to the
4.20.4     The Employer may supply to the Contractor, free of  Engineer of any shortage, defect or default in these materials. 
charge, "free ‐issue material" in accordance with the Contract as  Unless otherwise
well as any other "free ‐issue materiar as may be instructed by  agreed by both Parties, the Employer shall immediately rectify 
the Employer's Representative during the execution and  the notified shortage,
completion of the Works ("Free ‐Issue Materials"). The Employer  defect or default.
shall, at his risk and cost, provide the Free Issue Materials to the  After this visual inspection, the free‐issue materials shall come 
Contractor at the place and manner stated in Contract and by the  under the care, custody
later of the date stated in the Contract and the date for supplying  and control of the Contractor. The Contractor's obligations of 
the Free ‐Issue Materials in the Contract at which time the Free  inspection, care,
Issue Materials shall come under the care, custody and control of  custody and control shall not relieve the Employer of liability for 
the Contractor and the Contractor shall ensure such Free ‐Issue  any shortage, defect
Materials are protected against loss, damage or deterioration.  or default not apparent from a visual inspection.

4.20.5     The Contractor shall inspect the Free Issue Materials 
within 21 days upon taking custody of the Free‐issue Materials 
for any shortage, defect or default and for any non‐compliance 
with the Applicable Codes and Standards, Permits and Approvals 
and the relevant Laws and shall notify the Employer's 
Representative promptly (and in any event within 5 days of so 
Employer's Equipment and Free‐Issue Material

discovering), if any shortage, defect, default or non compliance is  Employer's Equipment and Free‐Issue Material
discovered in the Free ‐Issue Materials. The Contractor may at its 
sole discretion either (a) reject such Free‐ Issue Materials after 
issuing such notice; or (b) remedy such shortage, defect, default 
or non‐compliance in the Free ‐Issue Materials as soon as 
reasonably practicable.
4.20

4.20

No difference
4.20.6     If the Contractor suffers delay and/or Incurs additional 
Cost as a result of the Employer failing to provide the Free ‐Issue 
Materials by the date stated in the Contract (if any) or as a result 
of any shortage, defect, default or non‐compliance in the Free ‐
Issue Materials, the Contractor shall not be entitled to an 
extension to the Time for Completion or any Milestone Date, or 
to any additional payment or adjustment to the Contract Price.

4.20.7      The Employer may enter into framework arrangements 
or similar arrangements with specific third party suppliers for the 
ongoing purchase and supply of items of Plant or Materials for 
use in respect of the Works which are similar or equivalent to the 
Plant or Materials that are identified in the Bill of Quantities 
("Category Management Framework Agreements"). The Category 
Management Framework Agreements shall stipulate the rates 
and prices for such items of Plant or Materials. 

4.20.8     If the Employer enters into any Category Management 
Framework Agreements and the rate a price for the items of Plant 
or Materials in the Category Management Framework 
Agreements are less than the rate for the same items of Plant or 
Materials in the Bill of Quantities, the Contractor agrees to: 
(a) procure such items of Plant or Materials using the Category 
Management Framework Agreements in connection with the 
Works but not for any other project or purpose; and 
(b) vary the rate or price in the Bill of Quantities to match the rate 
or price in the Category Management Framework Agreements for 
the same items of plant or Materials.
4.21.1     Unless otherwise stated in the Contract, progress  Unless otherwise stated in the Particular Conditions, monthly 
reports shall be prepared every month by the Contractor with  progress reports shall be
two copies to be submitted to the Employer and one copy to be  prepared by the Contractor and submitted to the Engineer in six 
submitted to the Employer's Representative. Each copy of the  copies. The first
progress report shall be a soft copy in editable portable  report shall cover the period up to the end of the first calendar 
document format and Primavera P6 format, and a hard copy. The  month following the
first progress report shall cover the period up to the end of the  Commencement Date. Reports shall be submitted monthly 
first month following the Commencement Date. Reports shall be  thereafter, each within 7
submitted every month thereafter, each within 3 days after the  days after the last day of the period to which it relates.
last day of the period to which it relates. Reporting shall continue until the Contractor has completed all 
work which is known to be
4.21.2     Reporting shall continue until the Contractor has  outstanding at the completion date stated in the Taking‐Over 
completed all work which is known to be outstanding at the  Certificate for the Works.
completion date stated in the Taking ‐Over Certificate for the  Each report shall include:
Works.  (a) charts and detailed descriptions of progress, including each 
stage of design (if
4.21.3     Each report shall include:  any), Contractor's Documents, procurement, manufacture, 
(a) charts, detailed descriptions and summary of progress,  delivery to Site,
including each stage of design (if any), Contractor's Documents,  construction, erection and testing; and including these stages for 
procurement, manufacture, delivery to Site, constnrction,  work by each
erection and testing; and including these stages for work by each  nominated Subcontractor (as defined in Clause 5 [Nominated 
nominated Subcontractor (as defined in Clause 4.5A [Nominated  Subcontractors]),
Subcontractors],  (b) photographs showing the status of manufacture and of 
(b) photographs showing the status of the Works, each Section  progress on the Site;
and Milestone on and off the Site;  (c) for the manufacture of each main item of Plant and Materials, 
(c) for the manufacture of each item of Plant and Materials, the  the name of the
name of the manufacturer, manufacture location, percentage  manufacturer, manufacture location, percentage progress, and 
progress, and the actual or expected dates of  the actual or
(i) commencement of manufacture,  expected dates of:
(ii) Contractor's inspections,  (i) commencement of manufacture,
(iii) tests, and  (ii) Contractor's inspections,
(iv) shipment and arrival at the Site:  (iii) tests, and
(d) the details described in Sub ‐Clause 6.11 [Records of  (iv) shipment and arrival at the Site;
Contractor's Personnel and equipment]   (d) the details described in Sub‐Clause 6.10 [Records of 
(e) copies of quality assurance documents, test results and  Contractor's Personnel
certificates of Materials  and Equipment];
(f) list of notices given under Sub ‐Clause 2.3 [Employer’s Claims]  (e) copies of quality assurance documents, test results and 
and notices given 20.1 [Contractor's Claims];  certificates of
(g) safety statistics, including details of any hazardous incidents  Materials;
and activities relating to environmental aspects and public  (f) list of notices given under Sub‐Clause 2.5 [Employer's Claims] 
relations; and notices
(h) comparisons of actual against planned progress, with details  given under Sub‐Clause 20.1 [Contractor's Claims];
of any events or circumstances which may jeopardise the  (g) safety statistics, including details of any hazardous incidents 
Progress Reports

Progress Reports

completion in accordance with the Contract, and the measures  and activities
being (or to be) adopted to overcome delays;  relating to environmental aspects and public relations; and (h) 
4.21

4.21

(i) notice of the events or circumstances referred to at Sub ‐ comparisons of actual and planned progress, with details of any  No difference


Clause 8.3.8; events or
(j) summary of commercial matters, including invoices, payment,  circumstances which may jeopardise the completion in 
notices, instructions, Variations and claims; and  accordance with the
(k) such other information as stated in the Contract  Contract, and the measures being (or to be) adopted to overcome 
delays.
4.21.4     In addition to the requirements in Sub ‐Clauses 4.21.1 to 
4.21.3 above, the Contractor shall submit to the Employer's 
Representative an updated programme on a weekly basis in 
accordance with Sub ‐Clause 4.21.5, and such updated 
programme shall: 
(a) indicate the progress of each activity in relation with the 
Programme; 
(b) take into account any extension of time approved by the 
Employer's Representative;
(c) incorporate any changes in methods, time and sequence 
approved by the Employer's Representative; 
(d) resolve or amend any errors identified from previous updates; 
(e) include any additional works instructed by the Employer's 
Representative (including Variations); 
(f) show all work to be completed; 
(g) be in accordance with all the other programming 
requirements in Sub ‐Clause 8.3.2; 
(h) be accompanied by a labour schedule that conforms to the 
Programme; and 
(i) be properly referenced with update number and date. 

4.21.5     Such updated programme shall be submitted in three 
hard copies and one soft copy (including the native Primavera P6 
file and all supplemental documents). The updated programme 
shall be submitted one week after the acceptance of the first 
programme in accordance with Sub ‐Clause 8.3.1 and weekly 
thereafter.
Unless otherwise stated in the Particular Conditions: Unless otherwise stated in the Particular Conditions:
(a) the Contractor shall be responsible for keeping unauthorised  (a) the Contractor shall be responsible for keeping unauthorised 
persons off the Site, and persons off the Site, and
Security of The Site

Security of The Site
(b) authorised persons shall be limited to the Contractor's  (b) authorised persons shall be limited to the Contractor's 
Personnel and the Employer's Personnel; and to any other  Personnel and the Employer's Personnel; and to any other 
4.22

4.22
personnel notified to the Contractor, by the Employer or the  personnel notified to the Contractor, by the Employer or the  No difference
employer’s representative , as authorised personnel of the  employer’s representative , as authorised personnel of the 
Employer's other contractors ,consultants or operators  on the  Employer's other contractors ,consultants or operators  on the 
Site. Site.

4.23.1     The Contractor shall confine his operations to the Site,  The Contractor shall confine his operations to the Site, and to any 
and to any additional areas which may be obtained by the  additional areas which may be obtained by the Contractor and 
Contractor and agreed by the Employer's Representative as  agreed by the Engineer as working
working areas. The Contractor shall take all necessary precautions  areas. The Contractor shall take all necessary precautions to keep 
to keep Contractor's Equipment and Contractor's Personnel  Contractor's
within the Site and these additional areas, and to keep them off  Equipment and Contractor's Personnel within the Site and these 
adjacent land.  additional areas, and
to keep them off adjacent land.
4.23.2     During the execution of the Works, the Contractor shall  During the execution of the Works, the Contractor shall keep the 
keep the Site free from all unnecessary obstruction , and shall  Site free from all
store or dispose of any Contractor's Equipment or surplus  unnecessary obstruction, and shall store or dispose of any 
Contractor's Operations on Site

Contractor's Operations on Site

materials. The Contractor shall clear away and remove from the  Contractor's Equipment or
Site any wreckage, rubbish and Temporary Works which are no  surplus materials. The Contractor shall clear away and remove 
longer required.  from the Site any
wreckage, rubbish and Temporary Works which are no longer 
4.23.3     Upon the issue of a Taking ‐Over Certificate, the  required.
4.23

4.23

No difference
Contractor shall clear away and remove, from the part of the Site  Upon the issue of a Taking‐Over Certificate, the Contractor shall 
and Works to which the Taking ‐Over Certificate refers, all  clear away and
Contractor's Equipment, wreckage, rubbish and Temporary  remove, from that part of the Site and Works to which the Taking‐
Works. The Contractor shall leave that part of the Site and the  Over Certificate
Works im a clean and safe condition. However, the Contractor  refers, all Contractor's Equipment, surplus material, wreckage, 
may retain on Site, during the Defects notification period, such  rubbish and Temporary
Goods as are required for the Contractor to fulfil obligations  Works. The Contractor shall leave that part of the Site and the 
under the Contract. Works in a clean and
safe condition. However, the Contractor may retain on Site, 
during the Defects Notification Period, such Goods as are 
required for the Contractor to fulfil obligations under
the Contract.

4.24.1     All fossils, coins, articles of value or antiquity, and  All fossils, coins, articles of value or antiquity, and structures and 
structures and other remains or items of geological or  other remains or
archaeological interest found on the Site shall be placed under  items of geological or archaeological interest found on the Site 
the care and authority of the Employer. The Contractor shall take  shall be placed under
all necessary precautions to prevent Contractor's Personnel or  the care and authority of the Employer. The Contractor shall take 
other entities or persons from removing or damaging any of  reasonable
these findings.  precautions to prevent Contractor's Personnel or other persons 
from removing or
4.24.2    Upon the discovery of any such finding, the Contractor  damaging any of these findings.
shall:  The Contractor shall, upon discovery of any such finding, 
(a) take all necessary precautions to protect the finding and its  promptly give notice to the
immediate surrounds;  Engineer, who shall issue instructions for dealing with it. If the 
(b) comply with all Laws applying to the finding immediately upon  Contractor suffers delay
its discovery; and/or incurs Cost from complying with the instructions, the 
(c) give notice to the Employer's Representative within 24 hours  Contractor shall give a
of the discovery; further notice to the Engineer and shall be entitled subject to Sub‐
(d) immediately notify the Employer's Representative of any  Clause 20.1
instructions it has received from any Authority in relation to the  [Contractor's Claims] to:
finding; and (a) an extension of time for any such delay, if completion is or will 
(e)comply with any instructions of the Employer's Representative  be delayed,
or any Authority in relation to the finding.  under Sub‐Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost, which shall be included in the 
s

s
( )p y y ,

Fossils

Fossils
4.24

4.24
If the Contractor suffers delay and/or incurs Cost from complying  Contract Price. No difference
with the instructions of either the Employer's Representative or  After receiving this further notice, the Engineer shall proceed in 
any Authority, the Contractor shall give a further notice to the  accordance with SubClause 3.5 [Determinations] to agree or 
Employer's Representative and shall be entitled subject to Sub ‐ determine these matters.
Clause 20.1 [Contractor's Claims] to:

(a) an extension of time for any such delay, if completion is or will 
be delayed under Sub ‐Clause 8.4 [Extension of Time for 
Completion and of Milestone Dates]; and
(b) payment of any such Cost, which shall be added to the 
Contract Price. 

4.24.3     After receiving this further notice, the Employer's 
Representative shall proceed in accordance with Sub ‐Clause 3.6 
[Determinations] to agree or deterrnine the matters described in 
Sub ‐Clause 4.24.2 (a) and (b)

The Contractor shall prepare and submit for the Employer's 
Representative approval in accordance with Sub‐ clause 4.28 
[.Approval Process and Requirements]:
(a) provisional (marked‐up) as‐built documents; and
(b) final as‐built documents showing the exact as‐built locations, 
sizes and details of the work as executed,

at the time and in the manner set out in the Contract and 
As‐Built Documents

thereafter keep those documents at Site In accordance with Sub‐
Clause 1.8 [Care and Supply of Documents]. Two (2) copies shall 
be supplied to the Employer's Representative prior to the 
4.25

Not in FIDIC
commencement of the Tests on Completion. The Works er a 
Section shall not be considered as complete for the purpose of 
taking over under Sub‐Clause 10.1 [Taking Over of the Works and 
Sections) until the Employer's Representative has received and 
approved the as‐built documents in accordance with the Contract 
and this Sub‐Clause 4.25 (As‐Built Documents]. 

The Contractor shall train the Employer's Personnel or other 
operational contractors employed by the Employer in the 
operation and maintenance of the Works in accordance with the 
Contract The Works or a section shall  
not be considered as complete for the purposes of taking over 
under Sub‐Clause 10.1 [Taking Over of the Works and Sections] 
until such time as the training has been completed in accordance 
Training
4.26

with the Contract and this Sub‐Clause 4.26 [Training].  Not in FIDIC

The Contractor shall supply to the Employer's Representative 
Operation and Maintenance Manuals

operation and maintenance manuals in acc0ltlance with the 
requirements of the Contract. The Works or a Section shall not be 
considered as complete for the purposes of taking over under 
Sub‐Clause 10.1 [Taking Over of the Works and Sections] until the 
Employe(s Representative has received and approved all of the 
operation and maintenance manuals in accordance with this Sub‐
4.27

Not in FIDIC
Clause 4.27 (Operation and Maintenance Manuals]. 
4.28.1     The Contractor's Documents Which are to be submitted 
to the Employer's Representative for approval (including the 
documents described in Sub‐Clauses 4.1.5(c), 4.25 and 4.27) and 
the Contractor's proposed appointment of Subcontractor in 
accordance with Sub‐Clause 4.4 [Subconbactors], shall be subject 
to the process and requirements set out in this Sub Clause 4.28 
[Approval Process and Requirements]. 

4.28.2     The Employer's Representative shall, within 14 days of 
receipt of the Contractor's Document or receiving such 
information or documentation under Sub Clause 
4.4.2(c)[Subcontractor] (as the case may be), give notice to the 
Contractor that a Contractor's Document or Subcontractor: 

(a) is approved; or
(b) is rejected and giving reasons for such rejection.

4.28.3     The Employer's Representative shall not unreasonably 
withhold approval of a Contractor's Documents or a 
Subcontractor.

4.28.4     The execution of any part of the Waks that is subject to 
the approval of the relevant Contractor's Documents by the 
Employer's Representative shall not commence until the 
Employer's Representative has provided such approval. 

4.28.5     The execution of such parts of the Waks shall be in 
accordance with the reviewed and approved Contractor's 
Documents. 

4.28.6     If The Contractor wishes to modify or alter any design or 
document which has previously been submitted for approval, the 
Contractor shall immediately give notice to 1he Employer's 
Representative. Thereafter, The contractor shall submit revised 
documents to the Employer's Representative in accordance with 
the procedure in Sub‐Clause 4.28.2. The process in this Sub‐
Approval Process and Requirements

Clause 428 shall be repeated until the Contractor's Document or 
a Subcontractor (as the case may be) is approved. 

4.28.7     If a Contractor's Document or Subcontractor is rejected, 
the Contract Document or information or documentation under 
4.28

Sub‐Clause 4.4.2(c) [Subcontractors], as the case may be, shall (at  Not in FIDIC
the Contractor's cost and risk) be rectified and resubmitted 
within 21 days of the Employer's Representative's notice under 
Sub‐Clause 4.28.2(b) fa approval in accordance with this Sub‐
Clause 4.28. 

4.28.8     If the Employer's Representative has complied with the 
requirements of this Sub‐Clause 4.28, the Contractor shall have 
no entitlement to an extension of the Time for Completion 
and/or Milestone Date or to any additional payment or 
adjustment to the Contract Price, including where the Contractor 
suffers delays or including any costs due to the Employer's 
rejection of a Contractor's Document or Subcatractor. 

4.28.9     If the Employer's Representative instructs that further 
documents are required, the contractor shall prepare them 
promptly. Any such approval or consent. or any review (under 
this Sub‐Clause 4.28 or otherwise), shall not relieve the 
Contractor tan any of its duties, obligations, responsibilities, or 
liabili es arising out of, under, or in connec on with the Contract. 
4.29.1     Without in any way limiting Sub‐Clause 4.1 [Contractor's 
General Obligations], 4.10 [Site Data], and 4.11 [Stiffciency of 
Contract Price], the Contractor shall procure the performance 
and issuance of the Works Condition Report, and shall review and 
examine the Existing Works, within 30 days after the relevant 
date or dates upon which the Contractor is provided access to 
such parts of the Site as are necessary for the performance of the 
Works Condition Report 

4.29.2     If the Works Condition Report identifies or discloses any 
defends or damage in the Existing Works or if the Contractor 
itself identifies such defects or damage, which require 
remediation or rectification to enable the performance of the 
Works or to otherwise enable the Contractor to discharge its 
other obligations under the Contract, the Contractor shall notify 
the Employer's Representative in writing of such issues and the 
remediation or rectification works required, within 45 days after 
the relevant date or dates upon which the Contractor is provided 
access to such parts of the Site as are necessary for the 
performance of the Works Condition Report The Contractor shall, 
within such time also notify the Employer's Representative of any 
extension to the Time for Completion that the Contractor will 
require to undertake the required remediation or rectification 
works and the additional cost of such works. 

4.29.3     The Employer's Representative shall then review the 
notification from the Contractor issued under Sub‐Clause 4.29.2 
and determine whether or not, in its reasonable opinion, such 
proposed remediation or rectification works are required. If the 
Employer's Representative reasonably considers that such 
remediation or rectification works are required, such works shall 
be instructed as a Variation under Clause 13 [Variations and 
Adjustments]. The Contractor shall then be entitled to an 
adjustment to the Contract Price, if a1y, as determined in 
accordance with the procedure contained in Sub‐Clause 13.8 
[Valuation of Variations] and, subject to the Contractor's 
compliance with Sub‐Clause 20.1 (Contractor's Claims], such 
extension of the Time for Completion and/or Milestone Date(s) as 
the Contractor may be entitled under Sub‐Clause 8.4 (Extension 
of Time for Completion and of Milestone Dates). 

4.29.4     Due to the mutual benefit for the Parties in promptly 
identifying any defects and damage in the Existing Works as early 
as possible, the Contractor shall have no entitlement to an 
extension of the Time for Completion and/or at Milestone Date 
nor any entitlement to additional payment or adjustment to the 
Contract Price arising out of: 
Existing Works

(a) any defects or damage in the Existing Works which are not 
4.29      

notified to the Employer's Representative within the period 
Not in FIDIC
noted in, and in accordance with the procedure contained in, Sub‐
Clause 4.29.2; or
(b) the remediation or rectification of any defects or damage in 
the Existing Works which is not identified and notified to the 
Employer's Representative within the period noted in, and in 
accordance with the procedure contained in, Sub‐Clause 4.29.2.

4.29.5     But for any defects or damage notified to the Employer's 
Representative in accordance with Sub‐Clause 4.29.2 above, the 
Contractor shall take full responsibility for the adequacy, stability, 
and sufficiency of the design and construction of the Existing 
Works (if any) from the Commencement Date, whereupon the 
Existing Works shall become the responsibility of the Contractor 
as if the Existing Works had been designed and constructed by 
the Contractor. 
4.29.6     The Contractor acknowledges and agrees that it shall: 
(a) have no claim or entitlement to an extension of the Time fa 
Completion and/or any Milestone Date nor any adjustment to the 
Contract Price, except for such claims or entitlements to which 
the Contractor may be entitled in accordance with Sub‐Clause 
4.29.3 above; and
(b) not in any way be relieved from its representations, 
warranties, obligations and liabilities under the Contract,

on account of, arising out of, or in connection with the adequacy 
or suitability of the Existing Works Design, the Existing works 
and/or any acts, omissions or defaults of the Existing Works 
Contractor and/or Sub‐contractors and their agents or employees. 

4.30.1      Without in any way limiting Sub‐Clauses 4.1 
[Contractor's General Obligations], 4.10 [Site Data], and 4.11 
[Sufficiency of Contract Price], the Contractor shall procure the 
performance and issuance of the Works Condition Report, and 
shall review and examine the Enabling Works, within 30 days 
after the relevant date or dates upon which the Contractor is 
provided access to such parts of the Site as are necessary for the 
performance of the Works Condition Report 

4.30.2      If the Works Condition Report identifies or discloses any 
defects or damage in the Enabling Works or if the Contractor 
itself identifies such defects or damage, which require 
remediation or rectification to enable the performance of the 
Works or to otherwise enable the Contractor to discharge its 
other obligations under the Contract, the Contractor shall notify 
the Employer's Representative in writing of such issues and the 
remediation or rectification works required, within 45 days after 
the relevant date or dates upon which the Contractor is provided 
access to such parts of the Site as are necessary for the 
performance of the Works Condition Report The Contractor shall, 
within such time also notify the Employer's Representative of any 
extension to the Time for Completion that the Contractor will 
require to undertake the required remediation or rectification 
works and the additional cost of such works. 

4.30.3     The Employer's Representative shall then review the 
notification from the Contractor issued under Sub‐Clause 4.30.2 
and determine whether or not. in its reasonable opinion, such 
proposed remediation or rectification works are required. If the 
Employer's Representative reasonably considers that such 
remediation or rectification works are required, such works shall 
be instructed as a Variation under Clause 13 [Variations and 
Adjustments]. The Contractor shall then be entitled to an 
adjustment to the Contract Price, if any, as determined in 
accordance with the procedure contained in Sub‐Clause 13.8 
[Valuation of Variations] and, Subject to the Contractor's 
compliance with Sub‐Clause 20.1 [Contractor's Claims], such 
extension of the Time for Completion and/or Milestone Date(s) as 
the Contractor may be entitled under Sub‐Clause 8.4 [Extension 
of Time for Completion and of Milestone Dates]. 

4.30.4     Due to the mutual benefit for the Parties in promptly 
identifying any defects and damage in the Enabling Works as 
early as possible the Contractor shall have no entitlement to an
early as possible, the Contractor shall have no entitlement to an 
extension of the Time for Completion and/or any Milestone Date 
nor any entitlement to additional payment or adjustment to the 
Enabling Works  Contract Price arising out of:
(a) any defects or damage in the Enabling Works, which are not 
4.30 

notified to the Employer's Representative within the period  Not in FIDIC
noted in, and in accordance with the procedure contained in Sub‐
Clause 4.30.2; or
(b) the remediation a rectification of any defects or damage in 
the Enabling Works v.hich is not identified and notified to the 
Employer's Representative within the period noted in, and in 
accordance with the procedure contained in Sub‐Clause 4.30.2.

4.30.5     But for any defects or damage notified to the Employer's 
Representative in accordance with Sub‐Clause 4.30.2 above, the 
Contractor shall take full responsibility for the adequacy, stability, 
and sufficiency of the design and construction of the Enabling 
Works, if any, from the Commencement Date, whereupon the 
Enabling Works shall become the responsibility of the Contractor 
as if the Enabling Works had been designed and constructed by 
the Contractor. 

4.30.6 The Contractor acknowledges and agrees that it shall: 
(a) have no claim or entitlement to an extension of the Time for 
Completion and/or Milestone Date nor adjustment to the 
Contract Price, except for such claims or entitlements to which 
the Contractor may be entitled in accordance with Sub‐Clause 
4.30.3 above; and
(b) not in any Way be relieved from its representations, 
warranties, obligations, and liabilities under the Contract.

on account of, arising out of, or in connection with the adequacy 
or suitability of the Enabling Works Design, the Enabling Works, 
and/or any acts, omissions or defaults ct the Enabli'lg Works 
Contractor and/or its sub‐ contractors and their agents or 
employees. 

4.31.1     At the request and sole discretion of the Employer, the 
Employer may assign, transfer or novate the Enabling Works 
Contract, if any, to the Contractor, and the Contractor expressly 
consents to the Employer having such right and discretion and 
agrees that in such circumstances, it shall within 21 days of such 
Transfer of Enabling Works Contract 

request execute and deliver an assignment agreement in the 
specimen fam set out in Schedule 4 which shall record the 
Contractor's agreement to having the Enabling Works Contract 
assigned, transferred or novated to it and shall give effect to such 
assignment, transfer, or novation. 
4.31 

4.31.2     In such circumstances, the Contractor and the Employer 
shall do all other things necessary to effect the assignment, 
transfer or novation, including in respect of notifying and, if 
required, securing the consent of the Enabling Works Contractor. 

You might also like