Professional Documents
Culture Documents
SPMT SCHEDULE AS OF 19062020 (Version 1)
SPMT SCHEDULE AS OF 19062020 (Version 1)
NO PROJCET ITEM LIFTING WEIGHT CRANE TRANSPORTER LIFTING DATE SHIFTING DATE REMARKS
1 ONGC 98/2 CPP LSF ELEVATION TRUSS 3 WITH UPPER CHORD 158.6MT 3 NOS CRANE 400MT TRANSPOTER 200MT 2/4/2020 2/3/2020 DONE
2 ONGC 98/2 CPP LSF ELEVATION TRUSS 5 WITH UPPER CHORD 158.6MT 3 NOS CRANE 400MT 2/17/2020 DONE
3 ONGC 98/2 CPP LSF ELEVATION TRUSS 8 WITH UPPER CHORD 158.6MT 3 NOS CRANE 400MT 2/20/2020 DONE
4 ONGC 98/2 CPP LSF ELEVATION TRUSS 2 WITH UPPER CHORD 158.6MT 3 NOS CRANE 400MT 2/24/2020 DONE
11 ONGC 98/2 JACKET TOWER 1A 321.9MT 1NOS CRANE CC8800 30/3/2020 30/3/2020
1NOS CRANE 400MT
13 ONGC 98/2 CPP SUB CELLAR ROW (PORTION 1) 253.27MT 2 NOS CRANE 400MT 24 axles + 2 PPU 7/20/2020 7/20/2020
14 ONGC 98/2 CPP SUB CELLAR ROW 6-7 (PORTION 2) 180.46MT 2 NOS CRANE 400MT 24 axles + 2 PPU 7/25/2020 7/25/2020
20 ONGC 98/2 JACKET BOUYANCY TANK - ROW 1 IN PROGRESS 24 axles + 2 PPU 5/15/2020 5/15/2020
21 ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 1&2 (A&B) 164MT&142MT 3 NOS MANITOWOC 400MT 12 axles + 2 PPU 5/19/2020 5/19/2020
22 ONGC 98/2 JACKET CAISSON TOWER A(OPEN DRAIN) 123.9MT 1NOS CC8800 (1250MT) 6/30/2020 6/30/2020
1NOS MANITOWOC 400MT
23 ONGC 98/2 JACKET BOUYANCY TANK CENTER (2 NOS) IN PROGRESS 24 axles + 2 PPU 6/30/2020 6/30/2020
24 ONGC 98/2 JACKET TOWER 1B 321.69MT 1NOS CC8800 (1250MT) 24 axles + 2 PPU 6/3/2020 6/3/2020
1NOS MANITOWOC 400MT
25 ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 6&7 (A&B) 118.66MT 3 NOS MANITOWOC 400MT 12 axles + 2 PPU 6/19/2020 6/19/2020
27 ONGC 98/2 JACKET BOUYANCY TANK - ROW 7 IN PROGRESS 24 axles + 2 PPU 7/7/2020 7/7/2020
28 ONGC 98/2 JACKET BOAT LANDING - (TRY FIT) - TOWER A&B IN PROGRESS 7/7/2020 7/7/2020
31 ONGC 98/2 JACKET RISER GUARD (TRY FIT) - TOWER A & B IN PROGRESS 7/31/2020 7/31/2020
32 ONGC 98/2 JACKET BARGE BUMPER (TRY FIT) TOWER A & B IN PROGRESS 8/7/2020 8/7/2020
ONGC 98/2 JACKET X-PANEL ROW 7 106MT 1NOS KOBELCO 7650 24 axles + 2 PPU JULY
1NOS KOBELCO 7250
ONGC 98/2 JACKET X-PANEL ROW 2 88MT 3NOS MANITOWOC 400MT 24 axles + 2 PPU JULY
ONGC 98/2 JACKET X-PANEL ROW 6 88MT 3NOS MANITOWOC 400MT 24 axles + 2 PPU JULY
37 ONGC 98/2 LQ INSTALLATION OF LEVEL 5 FRAMING 211.47MT 4NOS MANITOWOC 400MT 24 axles + 2 PPU 8/27/2020 8/27/2020
38 ONGC 98/2 LQ INSTALLATION OF ROOF FRAMING 49.7MT 2NOS MANITOWOC 400MT 9/23/2020 9/23/2020
39 ONGC 98/2 MSF INSTALLATION OF CELLAR DECK ONTO TEMPERORY IN PROGRESS 9/7/2020 9/7/2020
SUPPORT
41 ONGC 98/2 TB INSTALLATION OF LEVEL 1 FRAMING 312.82MT 4NOS MANITOWOC 400MT 7/22/2020 7/22/2020
42 ONGC 98/2 TB INSTALLATION OF LEVEL 2 FRAMING 388.36MT 4NOS MANITOWOC 400MT 9/16/2020 9/16/2020
61 PEGAGA CPP ERECTION OF LQ BASE FRAME 250T x 2, 280 x 1 nos 48 axles + 2 PPU 9-Jul-20 7/8/2020
81 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 400t x 2 18 axle + 1 PPU 7/16/2020 7/16/2020
(1/4 nos of LQ modules)
82 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 400t x 2 18 axle + 1 PPU 7/17/2020 7/17/2020
(2/4 nos of LQ modules)
83 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 400t x 2 18 axle + 1 PPU 7/18/2020 7/18/2020
(3/4 nos of LQ modules)
63 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE Maxer 400MT TRANSPORTER 7/19/2020 7/18/2020
(EX-8110A) TBC by Engineering
64 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE Maxer 400MT TRANSPORTER 30-Jul-20 7/18/2020
(EX-8110B) TBC by Engineering
65 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE Maxer 400MT TRANSPORTER 31-Jul-20 7/18/2020
(EX-8110C) TBC by Engineering
LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME
84 PEGAGA CPP (4/4 nos of LQ modules) 400t x 2 18 axle + 1 PPU 1-Aug-20 7/19/2020
67 PEGAGA CPP INSTALLATION OF SERVICE DECK Maxer (400MT) x 2 nos. 48 axles + 2 PPU 2-Aug-20 7/22/2020
68 PEGAGA CPP INSTALLATION OF COOLER DECK Maxer (400MT) x 2 nos. 36 axles + 2 PPU 27-Aug-20 8/5/2020
45 PEGAGA CPP INSTALLATION OF NITROGEN GENERATION PACKAGE (XZ- 400T 5/19/2020 DONE
6410)
47 PEGAGA CPP INSTALLATION OF PRODUCED WATER TREATMENT SKID 1NOS CC8800 (1250MT) 5/27/2020 DONE
(VZ-4410)
49 PEGAGA CPP INSTALLATION OF METHANOL INJECTION PACKAGE (PZ- 250T 6/5/2020 DONE
4600) - SKID IN
50 PEGAGA CPP INSTALLATION OF CLOSED DRAIN PUMPS (PD-5730 A/B) - 250T 6/12/2020
SKID IN
51 PEGAGA CPP INSTALLATION OF HP SEPARATOR (VS-2040) 100T 1NOS CC8800 (1250MT) 6/13/2020
52 PEGAGA CPP INSTALLATION OF TEG CONTACTOR (VC-2420) 115T 1NOS CC8800 (1250MT) 6/15/2020
54 PEGAGA CPP INSTALLATION OF FUEL GAS FILTER (VF-4520 A/B) 6/20/2020 DONE
56 PEGAGA CPP INSTALLATION OF TEG DRAIN DOWN TANK (TR-3880) 6/22/2020 DONE
57 PEGAGA CPP INSTALLATION OF PEDESTAL CRANE COLUMN WEST 400Tx1, 250Tx1 12 axles +1 PPU 24-Jun-20
(DIESEL STORAGE TANK)
58 PEGAGA CPP INSTALLATION OF AIR DRYER PACKAGE (VZ-6330) - TO BE 400T 6/30/2020 ETA JULY
PENETRATE IN
INSTALLATION OF AIR COMPRESSOR PACKAGE (KZ-6310) -
59 PEGAGA CPP TO BE PENETRATE IN 400T 6/30/2020 ETA JULY
62 PEGAGA CPP ERECT OF FLARE DECK AT SERVICE PLATFORMS Maxer (400MT) x 1 no. 17-Jul-20
66 PEGAGA CPP INSTALLATION OF PEDESTAL CRANE COLUMN EAST 400Tx1, 250Tx1 Transporter: opt 1 100T&200T 26-Jul-20
(DIESEL STORAGE TANK)
70 PEGAGA CPP INSTALL COMPLETE FLARE BOOM ON CPP Maxer (400MT) x 2 nos., 400 x 2 nos. 8-Oct-20
TBC by Engineering
72 PEGAGA CPP UPENDING & ERECTION OF HELIDECK FRAME C/W 400t x 2 24 axles + 2 PPU 19-Oct-20 Date TBC by
PANCAKE ONTO LQ Production
75 PEGAGA CPP INSTALLATION OF FLARE NITROGEN BOTTLE SKID (FZ- Maxer 400MT 12/7/2020
4430) - SKID IN
76 PEGAGA CPP INSTALLATION OF COOLING MEDIUM EXPANSION VESSEL Maxer 400MT 12/26/2020
(VD-4010) - SKID IN
91 PEGAGA CPP INSTALLATION OF TEG REGENERATION PACKAGE (XZ- Maxer 400MT July ETA 30/6/2020
3800) TBC by Engineering
94 PEGAGA CPP INSTALLATION OF FUEL GAS HEATER (EH-4530 A/B) - SKID 400T September
IN
Maxer 400MT
95 PEGAGA CPP INSTALLATION OF CRANE R32M (MC-7310A) - WEST TBC by Engineering September
104 PEGAGA CPP INSTALLATION OF FM 200 CLEAN AGENT SKID (SZ- 250MT
7201/2/3/4/5) - ON MZD - SKID IN
106 PEGAGA CPP INSTALLATION OF POTABLE WATER PUMPS (PC-5330 A/B) 250T
- SKID IN
109 PEGAGA CPP INSTALLATION OF CONDENSATE METERING SKID (JZ-3160) 400T ETA 13/11/2020
- SKID IN
112 PEGAGA CPP INSTALLATION OF FIRE WATER PUMP (SZ-7101A) - SKID IN 400T
114 PEGAGA CPP INSTALLATION OF INLET COOLERS (HT-2035 A/B) @ UPD Maxer 400MT
115 PEGAGA CPP INSTALLATION OF FIRE WATER PUMP (SZ-7101B) - SKID IN 400T
PROJCET ITEM
PEGAGA CPP Diesel Storage Tank Row 6
ONGC 98/2
U PEGAGA
TOTAL
PROJCET ITEM
ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 1&2 (A&B)
ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 6&7 (A&B)
PEGAGA CPP Diesel Storage Tank Row 6
ONGC 98/2
U PEGAGA
TOTAL
PROJCET ITEM
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(1/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(2/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(3/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(4/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(1/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(2/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(3/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(4/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(1/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(2/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(3/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(4/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(1/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(2/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(3/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(4/4nos of LQ modules)
ONGC 98/2
U PEGAGA
TOTAL
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
0
16
16
16-Jul-20
17-Jul-20
18-Jul-20
19-Jul-20
30-Jul-20
31-Jul-20
1-Aug-20
2-Aug-20
13-Aug-20
14-Aug-20
15-Aug-20
16-Aug-20
27-Aug-20
28-Aug-20
29-Aug-20
30-Aug-20
24 axles + 2 PPU
PROJCET ITEM
ONGC 98/2 CPP SUB CELLAR ROW (PORTION 1)
ONGC 98/2 CPP SUB CELLAR ROW 6-7 (PORTION 2)
ONGC 98/2 JACKET TOWER A (LEG 1A & 2A)
ONGC 98/2 JACKET TOWER 1B
ONGC 98/2 LQ INSTALLATION OF LEVEL 4 FRAMING
ONGC 98/2 LQ INSTALLATION OF LEVEL 5 FRAMING
ONGC 98/2 JACKET BUOYANCY TANK ROW 1
ONGC 98/2 JACKET BUOYANCY TANK CENTER
ONGC 98/2 JACKET BUOYANCY TANK ROW 7
ONGC 98/2 JACKET X-PANEL ROW 1
ONGC 98/2 JACKET X-PANEL ROW 7
ONGC 98/2 JACKET X-PANEL ROW 2
ONGC 98/2 JACKET X-PANEL ROW 6
PEGAGA CPP UPENDING & ERECTION OF HELIDECK
FRAME C/W PANCAKE ONTO LQ
ONGC 98/2
U PEGAGA
TOTAL
PROJCET ITEM
PEGAGA CPP INSTALLATION OF COOLER DECK
ONGC 98/2
U PEGAGA
TOTAL
PROJCET ITEM
ONGC 98/2 CPP CELLAR DECK PORTION 1
ONGC 98/2 CPP CELLAR DECK PORTION 2
ONGC 98/2 CPP CELLAR DECK PORTION 3
ONGC 98/2 CPP MAIN DECK 3ND PORTION
ONGC 98/2 CPP MAIN DECK 1ND PORTION
ONGC 98/2 CPP MAIN DECK 2ND PORTION
ONGC 98/2 LQ INSTALLATION OF LEVEL 1 FRAMING
ONGC 98/2 LQ INSTALLATION OF LEVEL 2 FRAMING
ONGC 98/2 LQ INSTALLATION OF LEVEL 3 FRAMING
PEGAGA CPP ERECTION OF LQ BASE FRAME
PEGAGA CPP INSTALLATION OF SERVICE DECK
ONGC 98/2
U PEGAGA
TOTAL