LIFTING & SHIFTING SCHEDULE 2020 rev.

NO PROJCET ITEM LIFTING WEIGHT CRANE TRANSPORTER LIFTING DATE SHIFTING DATE REMARKS

1 ONGC 98/2 CPP LSF ELEVATION TRUSS 3 WITH UPPER CHORD 158.6MT 3 NOS CRANE 400MT TRANSPOTER 200MT 2/4/2020 2/3/2020 DONE

2 ONGC 98/2 CPP LSF ELEVATION TRUSS 5 WITH UPPER CHORD 158.6MT 3 NOS CRANE 400MT 2/17/2020 DONE

3 ONGC 98/2 CPP LSF ELEVATION TRUSS 8 WITH UPPER CHORD 158.6MT 3 NOS CRANE 400MT 2/20/2020 DONE

4 ONGC 98/2 CPP LSF ELEVATION TRUSS 2 WITH UPPER CHORD 158.6MT 3 NOS CRANE 400MT 2/24/2020 DONE

1NOS CRANE CC8800 (LUFFER JIB 36MTR WITH


SUPERLIFT )
5 ONGC 98/2 JACKET TOP PANEL 867.042MT 1NOS CRANE 650 KOBELCO 3/10/2020 DONE
5NOS CRANE 400MT
1NOS CRANE CC8800
6 ONGC 98/2 CPP CELLAR DECK PORTION 1 553.14MT 1NOS CRANE 650 KOBELCO 48 axles + 2 PPU 7/2/2020 7/2/2020
1NOS CRANE LR 750
1NOS CRANE 400MT
1NOS CRANE CC8800
1NOS CRANE 650 KOBELCO
7 ONGC 98/2 CPP CELLAR DECK PORTION 2 673MT 1NOS CRANE LR 750 48 axles + 2 PPU 7/16/2020 7/16/2020
1NOS CRANE 400MT
1NOS CRANE CC8800
8 ONGC 98/2 CPP CELLAR DECK PORTION 3 573.31MT 1NOS CRANE 650 KOBELCO 48 axles + 2 PPU 7/9/2020 7/9/2020
1NOS CRANE LR 750
1NOS CRANE 400MT
1NOS CRANE 400MT
1NOS CRANE KOBELCO 650
9 ONGC 98/2 CPP MAIN DECK 3ND PORTION TBA 1NOS CRANE CC8800 48 axles + 2 PPU 7/30/2020 7/30/2020
1NOS CRANE 400MT
1NOS CRANE CC8800
1NOS CRANE 650 KOBELCO
10 ONGC 98/2 CPP MAIN DECK 1ND PORTION 565.67MT 1NOS CRANE LR 750 48 axles + 2 PPU 8/14/2020 8/14/2020
1NOS CRANE 400MT

11 ONGC 98/2 JACKET TOWER 1A 321.9MT 1NOS CRANE CC8800 30/3/2020 30/3/2020
1NOS CRANE 400MT

1NOS CRANE CC8800


1NOS CRANE 650 KOBELCO
12 ONGC 98/2 CPP MAIN DECK 2ND PORTION 465.85MT 1NOS CRANE LR 750 48 axles + 2 PPU 8/24/2020 8/24/2020
1NOS CRANE 400MT

13 ONGC 98/2 CPP SUB CELLAR ROW (PORTION 1) 253.27MT 2 NOS CRANE 400MT 24 axles + 2 PPU 7/20/2020 7/20/2020

14 ONGC 98/2 CPP SUB CELLAR ROW 6-7 (PORTION 2) 180.46MT 2 NOS CRANE 400MT 24 axles + 2 PPU 7/25/2020 7/25/2020

15 ONGC 98/2 CPP UPPER DECK @PORTION 2 IN PROGRESS 8/10/2020 8/10/2020

16 ONGC 98/2 CPP MEZZANINE DECK @ PORTION 1 IN PROGRESS 9/23/2020 9/23/2020

17 ONGC 98/2 CPP COOLER DECK @PORTION 2 IN PROGRESS 9/29/2020 9/29/2020

1NOS CC8800 (1250MT) 1NOS


18 ONGC 98/2 JACKET TOWER A (LEG 1A & 2A) 321.69MT MANITOWOC 400MT 24 axles + 2 PPU 4/21/2020 4/21/2020

19 ONGC 98/2 JACKET WALKWAY FRAMING -TOWER A IN PROGRESS 5/5/2020 5/5/2020

20 ONGC 98/2 JACKET BOUYANCY TANK - ROW 1 IN PROGRESS 24 axles + 2 PPU 5/15/2020 5/15/2020

21 ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 1&2 (A&B) 164MT&142MT 3 NOS MANITOWOC 400MT 12 axles + 2 PPU 5/19/2020 5/19/2020

22 ONGC 98/2 JACKET CAISSON TOWER A(OPEN DRAIN) 123.9MT 1NOS CC8800 (1250MT) 6/30/2020 6/30/2020
1NOS MANITOWOC 400MT

23 ONGC 98/2 JACKET BOUYANCY TANK CENTER (2 NOS) IN PROGRESS 24 axles + 2 PPU 6/30/2020 6/30/2020

24 ONGC 98/2 JACKET TOWER 1B 321.69MT 1NOS CC8800 (1250MT) 24 axles + 2 PPU 6/3/2020 6/3/2020
1NOS MANITOWOC 400MT
25 ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 6&7 (A&B) 118.66MT 3 NOS MANITOWOC 400MT 12 axles + 2 PPU 6/19/2020 6/19/2020

26 ONGC 98/2 JACKET WALKWAY FRAMING -TOWER B IN PROGRESS 6/23/2020 6/23/2020

27 ONGC 98/2 JACKET BOUYANCY TANK - ROW 7 IN PROGRESS 24 axles + 2 PPU 7/7/2020 7/7/2020

28 ONGC 98/2 JACKET BOAT LANDING - (TRY FIT) - TOWER A&B IN PROGRESS 7/7/2020 7/7/2020

1NOS CC8800 (1250MT)


29 ONGC 98/2 JACKET CAISSON TOWER B 16.02MT 1NOS SCX2800 SUMITOMO 7/14/2020 7/14/2020

30 ONGC 98/2 JACKET J-TUBE IN PROGRESS 7/28/2020 7/28/2020

31 ONGC 98/2 JACKET RISER GUARD (TRY FIT) - TOWER A & B IN PROGRESS 7/31/2020 7/31/2020

32 ONGC 98/2 JACKET BARGE BUMPER (TRY FIT) TOWER A & B IN PROGRESS 8/7/2020 8/7/2020

1NOS KOBELCO 7650


ONGC 98/2 JACKET X-PANEL ROW 1 106MT 1NOS KOBELCO 7250 24 axles + 2 PPU JULY

ONGC 98/2 JACKET X-PANEL ROW 7 106MT 1NOS KOBELCO 7650 24 axles + 2 PPU JULY
1NOS KOBELCO 7250

ONGC 98/2 JACKET X-PANEL ROW 2 88MT 3NOS MANITOWOC 400MT 24 axles + 2 PPU JULY

ONGC 98/2 JACKET X-PANEL ROW 6 88MT 3NOS MANITOWOC 400MT 24 axles + 2 PPU JULY

2NOS SCX2800 SUMITOMO (275MT)


33 ONGC 98/2 LQ INSTALLATION OF LEVEL 1 FRAMING 345.83MT 1NOS MANITOWOC 400MT 48 axles + 2 PPU 7/9/2020 7/9/2020
1NOS KOBELCO 7650

1NOS SCX2800 SUMITOMO (275MT)


34 ONGC 98/2 LQ INSTALLATION OF LEVEL 2 FRAMING 346.75MT 2NOS MANITOWOC 400MT 48 axles + 2 PPU 7/22/2020 7/22/2020
1NOS KOBELCO 7650

2NOS SCX2800 SUMITOMO (275MT)


35 ONGC 98/2 LQ INSTALLATION OF LEVEL 3 FRAMING 242.6MT 1NOS MANITOWOC 400MT 48 axles + 2 PPU 8/4/2020 8/4/2020
1NOS KOBELCO 7650
1NOS KOBELCO 7250S
36 ONGC 98/2 LQ INSTALLATION OF LEVEL 4 FRAMING 265.50MT 1NOS SCX2800 24 axles + 2 PPU 8/17/2020 8/17/2020
2NOS MANITOWOC 400MT

37 ONGC 98/2 LQ INSTALLATION OF LEVEL 5 FRAMING 211.47MT 4NOS MANITOWOC 400MT 24 axles + 2 PPU 8/27/2020 8/27/2020

38 ONGC 98/2 LQ INSTALLATION OF ROOF FRAMING 49.7MT 2NOS MANITOWOC 400MT 9/23/2020 9/23/2020

39 ONGC 98/2 MSF INSTALLATION OF CELLAR DECK ONTO TEMPERORY IN PROGRESS 9/7/2020 9/7/2020
SUPPORT

40 ONGC 98/2 MSF INSTALLATION OF MAIN DECK IN PROGRESS 10/26/2020 10/26/2020

41 ONGC 98/2 TB INSTALLATION OF LEVEL 1 FRAMING 312.82MT 4NOS MANITOWOC 400MT 7/22/2020 7/22/2020

42 ONGC 98/2 TB INSTALLATION OF LEVEL 2 FRAMING 388.36MT 4NOS MANITOWOC 400MT 9/16/2020 9/16/2020

43 ONGC 98/2 TB INSTALLATION OF LEVEL 3 (ROOF) IN PROGRESS 9/25/2020 9/25/2020

61 PEGAGA CPP ERECTION OF LQ BASE FRAME 250T x 2, 280 x 1 nos 48 axles + 2 PPU 9-Jul-20 7/8/2020

81 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 400t x 2 18 axle + 1 PPU 7/16/2020 7/16/2020
(1/4 nos of LQ modules)

82 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 400t x 2 18 axle + 1 PPU 7/17/2020 7/17/2020
(2/4 nos of LQ modules)

83 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 400t x 2 18 axle + 1 PPU 7/18/2020 7/18/2020
(3/4 nos of LQ modules)

63 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE Maxer 400MT TRANSPORTER 7/19/2020 7/18/2020
(EX-8110A) TBC by Engineering

64 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE Maxer 400MT TRANSPORTER 30-Jul-20 7/18/2020
(EX-8110B) TBC by Engineering

65 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE Maxer 400MT TRANSPORTER 31-Jul-20 7/18/2020
(EX-8110C) TBC by Engineering
LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME
84 PEGAGA CPP (4/4 nos of LQ modules) 400t x 2 18 axle + 1 PPU 1-Aug-20 7/19/2020

67 PEGAGA CPP INSTALLATION OF SERVICE DECK Maxer (400MT) x 2 nos. 48 axles + 2 PPU 2-Aug-20 7/22/2020

LIFT & INTEGRATE LEVEL 2 MODULE ONTO LEVEL 1 LQ


89 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 13-Aug-20 30-Jul-20
(1/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 2 MODULE ONTO LEVEL 1 LQ


118 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 14-Aug-20 31-Jul-20
(2/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 2 MODULE ONTO LEVEL 1 LQ


119 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 15-Aug-20 1-Aug-20
(3/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 2 MODULE ONTO LEVEL 1 LQ


120 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 16-Aug-20 2-Aug-20
(4/4nos of LQ modules)

68 PEGAGA CPP INSTALLATION OF COOLER DECK Maxer (400MT) x 2 nos. 36 axles + 2 PPU 27-Aug-20 8/5/2020

LIFT & INTEGRATE LEVEL 3 MODULE ONTO LEVEL 2 LQ


77 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 28-Aug-20 13-Aug-20
(1/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 3 MODULE ONTO LEVEL 2 LQ


78 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 29-Aug-20 14-Aug-20
(2/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 3 MODULE ONTO LEVEL 2 LQ


79 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 30-Aug-20 15-Aug-20
(3/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 3 MODULE ONTO LEVEL 2 LQ


80 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 13-Aug-20 16-Aug-20
(4/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 4 MODULE ONTO LEVEL 3 LQ


85 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 24-Aug-20 27-Aug-20
(1/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 4 MODULE ONTO LEVEL 3 LQ


86 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 25-Aug-20 28-Aug-20
(2/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 4 MODULE ONTO LEVEL 3 LQ


87 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 26-Aug-20 29-Aug-20
(3/4nos of LQ modules)

LIFT & INTEGRATE LEVEL 4 MODULE ONTO LEVEL 3 LQ


88 PEGAGA CPP MODULE 400t x 2 18 axle + 1 PPU 27-Aug-20 30-Aug-20
(4/4nos of LQ modules)
44 PEGAGA CPP INSTALLATION OF PIPE RACK 1 & 2 400MT 6-May-20 Done

45 PEGAGA CPP INSTALLATION OF NITROGEN GENERATION PACKAGE (XZ- 400T 5/19/2020 DONE
6410)

46 PEGAGA CPP INSTALLATION OF NITROGEN RECEIVER (VD-6420) 400T 5/27/2020 DONE

47 PEGAGA CPP INSTALLATION OF PRODUCED WATER TREATMENT SKID 1NOS CC8800 (1250MT) 5/27/2020 DONE
(VZ-4410)

INSTALLATION OF SERVICE WATER FILTER (VF-5070A/B) -


48 PEGAGA CPP SKID IN 250T 5/28/2020 DONE

49 PEGAGA CPP INSTALLATION OF METHANOL INJECTION PACKAGE (PZ- 250T 6/5/2020 DONE
4600) - SKID IN

50 PEGAGA CPP INSTALLATION OF CLOSED DRAIN PUMPS (PD-5730 A/B) - 250T 6/12/2020
SKID IN

51 PEGAGA CPP INSTALLATION OF HP SEPARATOR (VS-2040) 100T 1NOS CC8800 (1250MT) 6/13/2020

52 PEGAGA CPP INSTALLATION OF TEG CONTACTOR (VC-2420) 115T 1NOS CC8800 (1250MT) 6/15/2020

53 PEGAGA CPP INSTALLATION OF SEAWATER FILTRATION PACKAGE (VZ- 400T 6/17/2020


5030) - SKID IN

54 PEGAGA CPP INSTALLATION OF FUEL GAS FILTER (VF-4520 A/B) 6/20/2020 DONE

55 PEGAGA CPP INSTALLATION OF TEG MAKE UP PUMP (PU-3885) 6/22/2020 DONE

56 PEGAGA CPP INSTALLATION OF TEG DRAIN DOWN TANK (TR-3880) 6/22/2020 DONE

57 PEGAGA CPP INSTALLATION OF PEDESTAL CRANE COLUMN WEST 400Tx1, 250Tx1 12 axles +1 PPU 24-Jun-20
(DIESEL STORAGE TANK)

58 PEGAGA CPP INSTALLATION OF AIR DRYER PACKAGE (VZ-6330) - TO BE 400T 6/30/2020 ETA JULY
PENETRATE IN
INSTALLATION OF AIR COMPRESSOR PACKAGE (KZ-6310) -
59 PEGAGA CPP TO BE PENETRATE IN 400T 6/30/2020 ETA JULY

60 PEGAGA CPP ERECT TOP CHORD 400T x 2, 250T x 2 6-Jul-20

62 PEGAGA CPP ERECT OF FLARE DECK AT SERVICE PLATFORMS Maxer (400MT) x 1 no. 17-Jul-20

66 PEGAGA CPP INSTALLATION OF PEDESTAL CRANE COLUMN EAST 400Tx1, 250Tx1 Transporter: opt 1 100T&200T 26-Jul-20
(DIESEL STORAGE TANK)

Maxer (400MT) x 1 nos.


69 PEGAGA CPP INSTALLATION OF GTG EXHAUST STACK/DUCTING TBC by ENGINEERING 9-Sep-20

70 PEGAGA CPP INSTALL COMPLETE FLARE BOOM ON CPP Maxer (400MT) x 2 nos., 400 x 2 nos. 8-Oct-20
TBC by Engineering

71 PEGAGA CPP INSTALLATION OF LQ STAIR TOWER 400MT x 1 no. 10-Oct-20

72 PEGAGA CPP UPENDING & ERECTION OF HELIDECK FRAME C/W 400t x 2 24 axles + 2 PPU 19-Oct-20 Date TBC by
PANCAKE ONTO LQ Production

INSTALLATION OF FLARE IGNITION PACKAGE (FZ-4330) -


73 PEGAGA CPP SKID IN Maxer 400MT 11/17/2020

74 PEGAGA CPP INSTALLATION OF INLET PRE-COOLER (HA-2020) Maxer 400MT 12/4/2020

75 PEGAGA CPP INSTALLATION OF FLARE NITROGEN BOTTLE SKID (FZ- Maxer 400MT 12/7/2020
4430) - SKID IN

76 PEGAGA CPP INSTALLATION OF COOLING MEDIUM EXPANSION VESSEL Maxer 400MT 12/26/2020
(VD-4010) - SKID IN

90 PEGAGA CPP INSTALLATION OF AVIATION FUEL PACKAGE (XZ-6100) After LQ Installation

91 PEGAGA CPP INSTALLATION OF TEG REGENERATION PACKAGE (XZ- Maxer 400MT July ETA 30/6/2020
3800) TBC by Engineering

92 PEGAGA CPP INSTALLATION OF CONDENSATE EXPORT BOOSTER PUMPS 250T June


(PC-3110 A/B/C) - SKID IN
INSTALLATION OF POTABLE WATER HEADER TANK (TC-
93 PEGAGA CPP 5340) 1NOS CC8800 (1250MT) June UPENDING

94 PEGAGA CPP INSTALLATION OF FUEL GAS HEATER (EH-4530 A/B) - SKID 400T September
IN

Maxer 400MT
95 PEGAGA CPP INSTALLATION OF CRANE R32M (MC-7310A) - WEST TBC by Engineering September

96 PEGAGA CPP UPENDING OF HELIDECK FRAME 400MT x 4 nos


TBC by Engineering

INSTALLATION OF SEWAGE TREATMENT (XZ-6610) - SKID


97 PEGAGA CPP IN 250T

98 PEGAGA CPP INSTALLATION OF CRANE R46M (MC-7310B) - EAST Maxer 400MT

99 PEGAGA CPP INSTALLATION OF MONORAIL HOISTS Maxer 400MT

100 PEGAGA CPP INSTALLATION OF EXHAUST STACK Under Study

101 PEGAGA CPP INSTALLATION OF MATERIALS HANDLING EQUIPMENT

102 PEGAGA CPP INSTALLATION OF WATER CHLORINATION PACKAGE (XZ- 250T


5040) - SKID IN

103 PEGAGA CPP INSTALLATION OF REVERSE OSMOSIS UNIT (XZ-5310A/B) - 250T


SKID IN

104 PEGAGA CPP INSTALLATION OF FM 200 CLEAN AGENT SKID (SZ- 250MT
7201/2/3/4/5) - ON MZD - SKID IN

105 PEGAGA CPP INSTALLATION OF POTABLE WATER STORAGE (TR-5320 250T


A/B) - SKID IN

106 PEGAGA CPP INSTALLATION OF POTABLE WATER PUMPS (PC-5330 A/B) 250T
- SKID IN

107 PEGAGA CPP INSTALLATION OF DIESEL TREATMENT PACKAGE (XZ-6260) 400T


- SKID IN
INSTALLATION OF POTABLE WATER FILTERS (VF-5350A/B)
108 PEGAGA CPP - SKID IN 250T

109 PEGAGA CPP INSTALLATION OF CONDENSATE METERING SKID (JZ-3160) 400T ETA 13/11/2020
- SKID IN

INSTALLATION OF FM 200 CLEAN AGENT SKID (SZ-7206/7)


110 PEGAGA CPP - ON CLD Maxer 400MT ETA AUGUST

111 PEGAGA CPP INSTALLATION OF CONDENSATE SUB-COOLER (HT- 400T


2050A/B) - SKID IN

112 PEGAGA CPP INSTALLATION OF FIRE WATER PUMP (SZ-7101A) - SKID IN 400T

113 PEGAGA CPP INSTALLATION OF UV STERILIZATION PACKAGE (XZ- 250T


5360A/B) - SKID IN

114 PEGAGA CPP INSTALLATION OF INLET COOLERS (HT-2035 A/B) @ UPD Maxer 400MT

115 PEGAGA CPP INSTALLATION OF FIRE WATER PUMP (SZ-7101B) - SKID IN 400T

INSTALLATION OF INLET COOLERS (HT-2030 C/D) @


116 PEGAGA CPP SERVICE DECK EL 40.5 Maxer 400MT (TBC)

117 PEGAGA CPP INSTALLATION OF FIREFIGHTING & LIFE SAVING


EQUIPMENT
SPMT ONGC 98/2 PEGAGA TOTAL
12 axles + 2 PPU 2 1 3
18 axles + 1 PPU 0 16 16
24 axles + 2 PPU 13 1 14
36 axles + 2 PPU 0 1 1
48 axles + 2 PPU 9 2 11
TOTAL 24 21 45
12 axles + 2 PPU

PROJCET ITEM
PEGAGA CPP Diesel Storage Tank Row 6
ONGC 98/2
U PEGAGA
TOTAL

LIFTING WEIGHT TRANSPORTER


94MT 12 axle + 1 PPU
2
1
3

SHIFTING DATE REMARKS


19-Aug-20
12 axles + 2 PPU

PROJCET ITEM
ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 1&2 (A&B)
ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 6&7 (A&B)
PEGAGA CPP Diesel Storage Tank Row 6
ONGC 98/2
U PEGAGA
TOTAL

LIFTING WEIGHT TRANSPORTER


118.66MT 12 axles + 2 PPU
118.66MT 12 axles + 2 PPU
94MT 12 axle + 1 PPU
2
1
3

SHIFTING DATE REMARKS


JULY
JULY
19-Aug-20
18 axles + 1 PPU

PROJCET ITEM
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(1/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(2/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(3/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(4/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(1/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(2/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(3/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(4/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(1/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(2/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(3/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(4/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(1/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(2/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(3/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(4/4nos of LQ modules)
ONGC 98/2
U PEGAGA
TOTAL

LIFTING WEIGHT TRANSPORTER

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU

18 axle + 1 PPU
18 axle + 1 PPU

18 axle + 1 PPU
0
16
16

SHIFTING DATE REMARKS

16-Jul-20

17-Jul-20

18-Jul-20

19-Jul-20

30-Jul-20

31-Jul-20

1-Aug-20

2-Aug-20

13-Aug-20

14-Aug-20

15-Aug-20

16-Aug-20

27-Aug-20

28-Aug-20
29-Aug-20

30-Aug-20
24 axles + 2 PPU

PROJCET ITEM
ONGC 98/2 CPP SUB CELLAR ROW (PORTION 1)
ONGC 98/2 CPP SUB CELLAR ROW 6-7 (PORTION 2)
ONGC 98/2 JACKET TOWER A (LEG 1A & 2A)
ONGC 98/2 JACKET TOWER 1B
ONGC 98/2 LQ INSTALLATION OF LEVEL 4 FRAMING
ONGC 98/2 LQ INSTALLATION OF LEVEL 5 FRAMING
ONGC 98/2 JACKET BUOYANCY TANK ROW 1
ONGC 98/2 JACKET BUOYANCY TANK CENTER
ONGC 98/2 JACKET BUOYANCY TANK ROW 7
ONGC 98/2 JACKET X-PANEL ROW 1
ONGC 98/2 JACKET X-PANEL ROW 7
ONGC 98/2 JACKET X-PANEL ROW 2
ONGC 98/2 JACKET X-PANEL ROW 6
PEGAGA CPP UPENDING & ERECTION OF HELIDECK
FRAME C/W PANCAKE ONTO LQ
ONGC 98/2
U PEGAGA
TOTAL

LIFTING WEIGHT TRANSPORTER


253.27MT 24 axles + 2 PPU
180.46MT 24 axles + 2 PPU
321.69MT 24 axles + 2 PPU
321.69MT 24 axles + 2 PPU
265.50MT 24 axles + 2 PPU
211.47MT 24 axles + 2 PPU
216.02MT 24 axles + 2 PPU
198.5MT 24 axles + 2 PPU
216.02MT 24 axles + 2 PPU
106MT 24 axles + 2 PPU
106MT 24 axles + 2 PPU
88MT 24 axles + 2 PPU
88MT 24 axles + 2 PPU
24 axles + 2 PPU
13
1
14

SHIFTING DATE REMARKS


7/20/2020
7/25/2020
4/21/2020
6/3/2020
8/17/2020
8/27/2020
8/4/2020
6/30/2020
7/28/2020
JULY
JULY
JULY
JULY
early october Date TBC by Production
36 axles + 2 PPU

PROJCET ITEM
PEGAGA CPP INSTALLATION OF COOLER DECK
ONGC 98/2
U PEGAGA
TOTAL

LIFTING WEIGHT TRANSPORTER


36 axles + 2 PPU
0
1
1

SHIFTING DATE REMARKS


5-Aug-20
48 axles + 2 PPU

PROJCET ITEM
ONGC 98/2 CPP CELLAR DECK PORTION 1
ONGC 98/2 CPP CELLAR DECK PORTION 2
ONGC 98/2 CPP CELLAR DECK PORTION 3
ONGC 98/2 CPP MAIN DECK 3ND PORTION
ONGC 98/2 CPP MAIN DECK 1ND PORTION
ONGC 98/2 CPP MAIN DECK 2ND PORTION
ONGC 98/2 LQ INSTALLATION OF LEVEL 1 FRAMING
ONGC 98/2 LQ INSTALLATION OF LEVEL 2 FRAMING
ONGC 98/2 LQ INSTALLATION OF LEVEL 3 FRAMING
PEGAGA CPP ERECTION OF LQ BASE FRAME
PEGAGA CPP INSTALLATION OF SERVICE DECK
ONGC 98/2
U PEGAGA
TOTAL

LIFTING WEIGHT TRANSPORTER


553.14MT 48 axles + 2 PPU
673MT 48 axles + 2 PPU
573.31MT 48 axles + 2 PPU
TBA 48 axles + 2 PPU
565.67MT 48 axles + 2 PPU
465.85MT 48 axles + 2 PPU
345.83MT 48 axles + 2 PPU
346.75MT 48 axles + 2 PPU
242.6MT 48 axles + 2 PPU
48 axles + 2 PPU
48 axles + 2 PPU
9
2
11

SHIFTING DATE REMARKS


7/2/2020
7/16/2020
7/9/2020
7/30/2020
8/14/2020
8/24/2020
7/9/2020
7/22/2020
8/4/2020
8-Jul-20
22-Jul-20