Professional Documents
Culture Documents
Identification and Quantification of Parameters Influencing The Behavior of Piled Raft Foundation in Layered Sand
Identification and Quantification of Parameters Influencing The Behavior of Piled Raft Foundation in Layered Sand
Identification and Quantification of Parameters Influencing The Behavior of Piled Raft Foundation in Layered Sand
H1/B=0.3 H1/B=0.6
3
displacement. 8
9
10
Load(kg.)
0 2 4 6 8 10 12 14
0
0.5
1
Deformation(mm.)
1.5
2
2.5
3
3.5
L/D = 10 @ H1/B = 0.3 L/D = 10 @ H1/B = 0.6
4
4.5
Load(Kg.)
6
ultimate load of any of the present configurations is
8
greater than the sum of individual capacities of raft and
10
piles. This increase is due to interaction between pile
12
and raft, which is dependent on the parameters
14
considered. This increase is presented in terms of load
16
Load (kg.) improvement ratio for different cases.
Fig. 6 Typical Load deformation plots of piled raft (4
piles, S/D = 5, L/D = 10) Load Improvement Ratio
Load improvement ratio is a non dimensional parameter
0
0 200 400 600 800 1000 1200 1400 1600 1800 which is defined as the ratio of load carried by the piled
2
raft to the load of unpiled raft.
4
The load improvement ratios for piled rafts of different
configurations considered in the present study are
Deformation (mm.)
6 Raft
8
Piled raft summarized in Table 3 and it’s variation at failure load,
10 with respect to various parameters such as thickness of
12 top dense layer H1/B), number of piles (N), length of
14 piles (L) and spacing between piles is shown in fig.8 to
16 fig. 11.
Load (kg.)
From the plots it is clear that, load deformation Load Improvement Ratio
behaviour of all the tests exhibits strain softening case Configuration H1/B = 0.3 H1/B = 0.6
which is characterized by peak stress beyond which At At At At
load decreases with further deformation. Load 6mm Failure 6mm Failure
corresponding to peak is reported as ultimate load Raft+2,5,10 1.23 1.43 1 1.23
carrying capacity. Ultimate loads so obtained for all the
Raft+4,5,10 1.27 1.53 1.37 1.54
tests are summarized in Table 2.
Raft+2,15,10 1.35 1.79 1.05 1.30
Table 2 Ultimate Load carrying capacities Raft+4,15,10 1.92 1.94 1.12 1.60
H1/B = 0.3 H1/B = 0.6
Raft+2,5,40 1.25 1.70 1.54 1.45
Test Ultimate Ultimate Load
Load ( kg ) ( kg ) Raft+4,5,40 1.58 1.75 1.54 1.53
Raft 800 1140 Raft+2,15,40 2.31 2.13 1.66 1.54
Raft + 2, 5, 10 1140 1400
Raft+4,15,40 1.85 2.24 1.41 1.61
Raft + 4, 5, 10 1220 1750
Raft + 2, 15, 10 1430 1480
Raft + 4, 15, 10 1550 1824 Variation of load improvement ratio with thickness
Raft + 2, 5, 40 1360 1650 of top dense layer (H1/B)
Raft + 4, 5, 40 1400 1750 From Fig. 8 it is clear that the thickness of top dense
Raft + 2, 15, 40 1700 1750 layer has significant effect on the load improvement
Raft + 4, 15, 40 1790 1830 ratio. In most of the presented cases load improvement
Pile (L/D = 10) 9.1 13.1 ratio is more when thickness of top dense layer (H 1/B)
Pile (L/D = 40) 13.6 14.7 is 0.3.
(a) L/D=10
Variation of load improvement ratio with length of
piles (L/D)
2.50
2.50
2.00
2.00
Load improvement ratio
1.50
1.50
2.00
Load improvement ratio
1.50
1.00
1.50 Configuration
(at 800kg) (at 1100kg)
1.00 δ SRR δ SRR
N=2 @ H1/B=0.3 N=4 @ H1/B=0.3 Raft 8.6 7.8
0.50
N=2 @ H1/B=0.6 N=4 @ H1/B=0.6
Raft+2,5,10 7.80 0.09 7.6 0.03
Raft+4,5,10 7.20 0.16 6.90 0.12
0.00
4 6 8 10 12 14 16 Raft+2,15,10 7.10 0.17 7.70 0.01
Spacing between piles Raft+4,15,10 4.90 0.43 7.20 0.08
Raft+2,5,40 5.80 0.32 5.40 0.31
(a) L/D = 10
Raft+4,5,40 5.70 0.34 5.20 0.33
2.50
Raft+2,15,40 3.40 0.60 4.80 0.38
Raft+4,15,40 4.70 0.45 5.70 0.27
2.00
Load improvement ratio
0.6
0.00
4 6 8 10 12 14 16 Settlement Reduction Ratio 0.5 N =2@S/D =5 N =4 & S/D = 5
0
0 0.2 0.4 0.6 0.8
Settlement Reduction Thickness of Dense layer
The main objective of piled raft system is to reduce the
settlement of raft by the addition of a minimum number (a) L/D=10
of piles. In the present study the reduction of settlement 0.7
0.5
corresponding settlement reduction ratio values are 0.2 N = 2 & S/D = 5 N = 4 & S/D = 5
presented in table 4 and the variation of settlement 0.1 N = 2 & S/D = 15 N = 4 & S/D = 15
reduction ratio with respect to various parameters such 0
0.2 0.4 0.6 0.8
as thickness of top dense layer H1/B), number of piles
Thickness of Dense layer
(N), length of piles (L) and spacing between piles is
shown in fig. 12 to fig. 15.
(b) L/D=40
Fig. 12 Variation of Settlement reduction ratio
Settlement reduction ratio with thickness of top dense layer
Settlement reduction ratio is a non dimensional
parameter which is defined as the ratio of settlement of From Fig. 12 it is clear that the thickness of top dense
piled raft and unpiled raft at a given load. layer has significant effect on the settlement reduction
ratio when S/D is 15 and minimum effect when S/D is
δr−δpr
Settlement reduction ratio = 5. When H1/B is 0.3 much benefit of settlement
δr
reduction is attained for S/D of 5, where as for H1/B of
whereδr and δpr represents the settlement of unpiled 0.6 the effect of spacing is minimum.
raft and piled raft for a given load.
Variation of Settlement reduction ratio with number
of piles (N) 0.7
0.7
0.6
0.6
0.5
0.4
0.4 S/D = 5@H1/B= 0.6 S/D = 15@H1/B= 0.6
0.3
0.3
0.2 S/D = 5@H1/B= 0.3 S/D = 15@H1/B = 0.3
0.2
0.1
0.1 S/D = 5@H1/B = 0.6 S/D = 15@H1/B= 0.6
0
0 0 10 20 30 40 50
1 2 3 4 5 6
Number of Piles Length of piles
0.1
S/D = 5@H1/B= 0.6 S/D = 15@H1/B= 0.6
Variation of Settlement reduction ratio with spacing
0
1 2 3 4 5 6
between piles (S/D)
Number of Piles 0.7
of piles and when L/D is 40 it showed the same trend Spacing between piles
0.6
Variation of Settlement reduction ratio with length 0.5
of piles (L/D)
Settlement Reduction Ratio
0.4
0.7
0.3
0.6
0.2
0.5 N = 2@H1/B= 0.3 N= 4@H1/B= 0.3
Settlement Reduction Ratio
0.1
0.4 N = 2@H1/B= 0.6 N = 4@H1/B = 0.6
0
0.3 4 6 8 10 12 14 16
S/D= 5@H1/B= 0.3 S/D = 15@H1/B= 0.3
Spacing between the piles
0.2
S/D = 5@H1/B = 0.6 S/D= 15@H1/B= 0.6
0.1
(b) L/D = 40
0
0 10 20 30 40 50 Fig. 15 Variation of Settlement reduction ratio
Length of piles with spacing between piles
(a) 2- Piles
Contrast of ABCD = [(abcd-abc-abd+ab) + (-acd+ac+ad-a)
From fig. 15 it is clear that the settlement reduction + (-bcd+bc+bd-b) + (cd-c-d+1)]
ratio increases with spacing between piles when H 1/B is
Average Effect = (1/8n) [Contrast]
0.3 and when H1/B is 0.6 it decreases with increase in
spacing between piles in most of the presented cases. Sum of Squares = (1/16n) [Contrast]2
Where n is number of replicates in our it is 1.
QUANTIFICATION:
The values obtained on substitution are summarized in table 6
A detailed factorial analysis is required to quantify the
effect of each parameter on the ultimate load carrying and table 7 for ultimate load and settlement of piled raft
capacity of piled raft system and its settlement at a load respectively.
equal to the ultimate load of unpiled raft. In the present
experimental study the main factors considered are
Spacing of piles(S/D), Length of piles (L/D), number of Table 6 Summary of Effect Estimate for ultimate load
piles (N) thickness of top dense layer (H1/B). For the Average Sum of %
factorial analysis the factors under consideration are Factor Contrast Effect Squares contribution
taken at two levels as presented in Table 5 and the data A 1687 210.88 177873.06 24.14
for factorial analysis is as shown in Fig. 16 and Fig. 17 B 1201 150.13 90150.06 12.24
for ultimate load and settlement respectively. (The C 1433 179.13 128343.06 17.42
details of the method can be found in any standard text- D 1841 230.13 211830.06 28.75
book on statistics, one of such books is Design and AB 67 8.38 280.56 0.04
Analysis of Experiments by Montgomery (2005) [5]. AC 139 17.38 1207.56 0.16
AD -1013 -126.63 64135.56 8.71
Table 5 Factors considered for 24 Factorial
BC -587 -73.38 21535.56 2.92
Experimentation
BD 541 67.63 18292.56 2.48
Factor Low High
CD -387 -48.38 9360.56 1.27
Level Level
Spacing of Piles(S/D) 5 15 ABC -1 -0.13 0.06 0.00
Number of Piles(N) 2 4 ABD -113 -14.13 798.06 0.11
Length of Piles(L/D) 10 40 ACD -81 -10.13 410.06 0.06
Thickness of top dense layer 0.3 0.6 BCD -447 -55.88 12488.06 1.70
(H1/B) ABCD -21 -2.63 27.56 0.00
Total 736732.44 100.00