REQUEST FOR PROJECT PREPARATION GRANT (PPG)

PROJECT TYPE: MEDIUM-SIZED PROJECT


THE GEF TRUST FUND

Submission date: April 2008 


Re-submission date: November 28, 2008
GEFSEC PROJECT ID1: 3633
GEF AGENCY PROJECT ID:      
COUNTRY(IES): Peru
PROJECT TITLE: Implementation of the National Biosafety Framework of Peru
GEF AGENCY(IES): UNEP,
OTHER EXECUTING PARTNER(S):  CONAM 
GEF FOCAL AREA(S): Medium-sized ProjectBiodiversity,
GEF-4 STRATEGIC PROGRAM(S):  BD- FORMTEXT SP6 
NAME OF PARENT/PROGRAM/UMBRELLA PROJECT: BIOSAFETY PROGRAM

A. PROJECT PREPARATION TIMEFRAME


Start date February 2009
Completion date June 2009
CEO Endorsement/Approval of project August 2009

B. PROJECT PREPARATION ACTIVITIES ($)


Describe the PPG activities and justifications: A). Conduct a coordinated and participatory process
for project formulation, which will include an initial stock-taking exercise as required by the GEF
Strategy, which will provide both a needs assessment (relating to legal, technical, coordination, and
follow-up issues, among others) and a project baseline, a side-by-side comparison to address
complementarities with the WB-GEF projects and respond to GEF SEC review comments, and an
incremental cost analysis. B). Conduct a discussion process to initiate with National Competent
Authorities and relevant stakeholders in order to analyze and validate the project's approach to
biosafety capacity building, beginning with the objectives, components, outcomes, outputs, planned
activities, through to determining appropriate quantitative and qualitative targets and indicators, and a
definitive budget. C). Determine and concur on the details of project implementation, such as
execution arrangements (including institutional roles, an inter-project coordination plan for optimal
integration with the WB-projects and the project coordinator's terms of reference), mechanisms for
monitoring and evaluating project progress and impact, and co-financing responsibilities. Finally,
draft the various inputs required for compilation and presentation to the GEF of an MSP proposal.

List project Output of the PPG activities Project Preparation (a) Co-
PDF- PDF- PPG Total
preparation financing
C=a+b
activities A B/C (b)
A. Carry out Stock-taking exercise and needs  9,200  5,250 14,450
analyses:   analysis; Incremental cost analysis;
Side-by-side comparison table for WB-
GEF projects; Sustainability analysis;
Project baseline
B. Review and Consultation process; Revised project 10,660 5,250 15,910
validate: objectives, components, outcomes,
outputs and planned activities; Targets
1
Project ID number will be assigned initially by GEFSEC. If PIF has been submitted earlier, use the same ID number as PIF.

PPG Template, August 30, 2007 1


and indicators
C. Draft Agreements on execution and co- 4,700 3,500 8,200
contents and financing responsibilities; Stakeholder
approve: participation plan; Project description,
budget and work plan; Costed M&E
Plan; Inter-project (WB /UNEP)
coordination plan; Project Coordinator
TORs; Government approval of project
documentation.
Total project preparation financing 24,560 14,000 38,560

C. PPG REQUESTED BY AGENCY(IES), FOCAL AREA(S) AND COUNTRY(IES)


Country Name/ (in $)
GEF
Agency Focal Area Agency Total
Global
PPG (a) Fee (b) c=a+b
UNEP Biodiversity  Peru    24,560   2,456   27,016 
Total PPG Requested  24,560   2,456   27,016 

D. PPG BUDGET REQUEST


Total Estimated
Person Weeks for GEF ($)
Cost Items Co-financing ($) Total ($)
GEF Grant (PW)

Local consultants *  12 months   19,600  6,000   25,600 


International consultants*                         
Travel                  
Miscellaneous /Office costs   4,960    8,000   12,960 
Total PPG Budget  24,560   14,000   38,560 
* A separate Annex A for Consultant cost details should be included in this PPG Request.

E. GEF AGENCY(IES) CERTIFICATION


This request has been prepared in accordance with GEF policies and procedures and meets the GEF
criteria for project identification and preparation.

Maryam Niamir-Fuller Tea Garcia-Huidobro C.


GEF Agency Coordinator Project Contact Person
Director Division of GEF Coordination DGEF - UNEP
UNEP Regional Office for Latin America and the
Nairobi, Kenya Caribbean (ROLAC)
Panama City, Panama
Date: November 28, 2008 Tel. and Email: (+507) 305 3169
tea.garciahuidobro@unep.ch 

PPG Template, August 30, 2007 2


Annex A

Consultants Financed by the Project Preparation Grant (PPG)

$/ Estimated
Position Titles Person PWs** Tasks to be performed
Week *
Local
PPG  2200 /month 4 months Will lead the project preparation process; organize,
Coordinator conduct meetings and consultations; supervise other
(1 person)  consultants and assistants; ensure information flow;
carry out the initial stock-taking assessment and
determine the project baseline; coordinate the review
and validation process for agreeing on project inputs;
draft and consolidate final project inputs.     
Technical  1000 /month 4 months Will assist the Coordinator in all his functions,
Assistant particularly in organizational matters, information
(1 person)  gathering and document drafting.  
Thematic  1700 /month 2 months Will prepare specific materials for consultation, review,
consultants x2 analysis and inclusion in the project proposal: (a) Needs
(2 persons)  analysis in relation to the Cartagena Protocol with
proposals to tackle specific areas. (b) Financial aspects:
sustainability analysis, incremental cost analysis,
project budget, including co-financing.  
Technical staff 1000 /month 4 months Will supervise overall project preparation process;
(1 person, (Govt support the Coordinator in liaising with other
part-time) funding) institutions, and in obtaining the required information
and inputs; guide the definition of project contents;
ensure final approval of project documentation.
Administrative 500 /month 4 months Will provide part-time administrative, logistical and
assistant (Govt secretarial support
(1 person, funding)
part-time)
International
                       
                       

* Or person month, if applicable. Please indicate clearly.


** Provide weeks or months (as appropriate) that correspond to the rate provided in the previous column.

PPG Template, August 30, 2007 3