Initial Load Test Report
Initial Load Test Report
Initial Load Test Report
Contractor Consultant
Type of Test InitialLoad Test
1 20 13.00 1.520 12.830 1.50 The applied load is slightly lower than the required load
2 40 26.00 3.040 25.659 3.00
10 Stiffeners 16mm
12 Pile concreted on 16/06/2020
12 Test started on 14/07/2020
13 Test completed on 16/07/2020
14 Safe load 65 MT
15 Test load 162.5 MT
16 Ram area of jack 855.3 cm2
17 Total settlement
18 Net settlement
19 Rebound
INITIALVERTICAL LOAD TEST ON PILE
COMMENTS
PROCEDURE
GENERAL
1) The testing of the pile will be carried out according to IS:2911 (Part - IV ) - 1985
Correct the code to IS 2911(Part - IV) 2013
In accordance with the relevant portion of the Indian Standard IS 2911 (part - IV)
2) 1985, the the Initial vertical load test shall be carriedout for a test load of at least
two and a half times the working load.
3) The maximum settlement for initial load test shall not exceed 12 mm. CORRECT IT AS 10% OF THE PILE DIA
METHODOLOGY OF TEST
It is proposed to conduct the load test on pile by application of vertical A minimum of four dal guages to be there symitrically palced and
compression loads on the top of hydraulic jack reacting against a platform the datum bar shall be supperted at a minimum distance of 2m
supporting and the settlements will be recorded by suitably positioned dial from the edge of the pile
guages. Maintained load method as detailed in the IS will be followed.
1) The load application and settlement observations will be made at the pile top
Settlements will be recorded using three dial guages with a least count 0.01mm A minimum of four dal guages to be there symitrically palced and the datum bar
. The guage will be positioned at an equal distance around the piles and will be shall be supperted at a minimum distance of 2m from the edge of the pile
2)
held by datum bars resting on immovable supports at equal distance from the
peripheral edge
LOAD APPLICATION
The test load will be applied by means of hydraulic jack of sufficient capacity
( with a remote control system ). The jack will pull against the jacking girder
1) The efficiency of the jack to be tested before the load test
assembly / bearing against the loaded platform. The jacking grider assembly will
consist of rolled steel beam/plated beams with the flanges well braced.
The test will be carried out by applying a series of vertical incremental loads,
each increment being about 20% of the assumed safe load on the pile. The
2) pressure will be read from pressure guage attached to the hydraulic pump. At
each stage of loading the guage pressure multiplied by the ram area of jack will
be applied load.
At each stage, the loading will be maintained till such time, the rate of movement
Correct this as per the latest code IS 2911 part IV 2013, rate of movement of the
3) of pile head is not more than 0.1mm in the first 30 minutes or 0.2mm in the first
pile head not more than 0.2 mm/hr or 2hr
one hour or for a maximum of 2 hours, whichever occurs first.
Total 8.83 MT
B PREPARATION OF KENTLEDGE