Field Test Report of 20 mm Stone Grit

Name of Work :- C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

C.B. No. :- 27/SE-Barabanki Circle/2018-19 Date 12-06-2018

Chainage :- Km

Total Wieght :- 3371 g Date of Testing:-

Sieve As per
Material Cummulative Cummulative Passing
S.No. Size in Required Remark
Retained Retained Retained % %
mm %

1 40 0 0 0.00 100.00 100


2 20 67 67 2.00 98.00 95-100
3 10 1618 1686 50.00 50.00 25-55
4 4.75 1686 3371 100.00 0.00 0-10
Note:- Three Samples for each quarry source.

J.E. A.E.
Field Test Report of 20 mm Stone Grit
Name of Work :- C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

C.B. No. :- 27/SE-Barabanki Circle/2018-19 Date 12-06-2018

Chainage :- Km

Total Wieght :- 4372 g Date of Testing:-

Sieve As per
Material Cummulative Cummulative Passing
S.No. Size in Required Remark
Retained Retained Retained % %
mm %

1 40 0 0 0.00 100.00 100


2 20 131 131 3.00 97.00 95-100
3 10 1924 2055 47.00 53.00 25-55
4 4.75 2273 4328 99.00 1.00 0-10
Note:- Three Samples for each quarry source.

J.E. A.E.
Field Test Report of 20 mm Stone Grit
Name of Work :- C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

C.B. No. :- 27/SE-Barabanki Circle/2018-19 Date 12-06-2018

Chainage :- Km

Total Wieght :- 4231 g Date of Testing:-

Sieve As per
Material Cummulative Cummulative Passing
S.No. Size in Required Remark
Retained Retained Retained % %
mm %

1 40 0 0 0.00 100.00 100


2 20 85 85 2.00 98.00 95-100
3 10 2031 2116 50.00 50.00 25-55
4 4.75 2115 4231 100.00 0.00 0-10
Note:- Three Samples for each quarry source.

J.E. A.E.
Test For Aggregate Impact Value of Aggregate
Name of Work :- C/o 3x18.00 m span minor bridge on Baheri Nala at Baheri Link Road.

C.B. No. :- 27/SE-Barabanki Circle/2018-19 Date 12-06-2018

Chainage :- Km

Test Nos.
S.No. Observations Average
1 2 3
1 Weight of Aggregate Sample (Passing through
12.5mm & Retained on 10mm IS Sieve)Filled in the
Cylinder = W1 (gm) 621 621 621 621.00

2 Weight of Aggregate Passing 2.36 mm Seive After


15 Nos. of Blow = W2 (gm)
64 63 63 63.33

3 A I V = (W2 / W1) X100 10.31 10.14 10.14 10.20

Note- 1- Cylindrical Measure shall be filled in 3 Layers by tamping 25 blow.


2- One Test per source of supply. If AIV is more than 18%, Stone Grit should be rejected.

J.E. A.E.