Professional Documents
Culture Documents
304.PMP Lesson Learned
304.PMP Lesson Learned
1- During the developing the project charter, the PM fined that, the organization cares about
the KPI, what the pm must do.
A- Include the KPI as a success criteria in the project charter
2- Key stakeholder rejects the deliverable and said the project does not meet its objectives any
more. What document will you review with the key stakeholder.
A- Project charter
3- Sponsor told you that project is behind schedule; you review the progress and get the
following results. SPI 1.2/ CPI =1.1 what you will give the sponsor to solve the
misunderstand.
A- Earned value reports
4- Your sponsor has requested you to come up with a cost estimate for all the activates which
are defined in the project schedule he make sure that you are taking uncertainty into
consideration what is the technique for this.
A- beta distribution
5- A formatted and arranged information gathered at the end of initiating or SOON LATER.
ill
nw
A- Project Charter
iro
6- The Sponsor call the PM and Shout at him, why did you send the reports to the Financial
Manager, what should have been done to prevent this.
A- Review communication plan
7- The Stakeholders called the PM and said they did not receive any answer for their change
requests, what will help to solve the problem.
A- Review perform integrated change control process
9- The project manager asks for help from POM this is:
A- Expert Judgments
10- Buy or rent question: Buy cost is 210000 rent cost is 10000 plus 2000 per month, when buy
is better than rent.
A- 101 days
CONFIDENTIAL 1
11- During conduct procurement, the buyer team choose one supplier. Before signing the
contract the supplier asks for down payment, what will you do as a PM.
B- Procurement plan
12- During closing the project, the customer refuse to accept the deliverables and he said that
something missing from the scope, what will you do.
A- Validate the scope against the baseline
13- EV is less than AC and PV, What is the situation in the project?
A- The project is going slower than planned
14- A question talks about random scenario then he asks you where you find the stakeholders
roles.
A- Stakeholders register
15- One team member talks about ignoring the one point estimates in estimating during
meeting, what the project member talks about.
A- normal distribution
B- Beta
C- Cumulative distribution
ill
D- triangular
nw
iro
16- Stakeholders ask some changes to the deliverables that will affect both time and cost, PM
tell the stakeholders about the impacts, what’s the best way the PM will use to solve the
issue with the stakeholders
A- Collaborating
17- One of your supplier’s PM submits a proposal to one of your team member that will improve
the work, the team member told you about the proposal. The pm asks the team member to
ignore the proposal and continue with the same project plan. The PM use.
A- Forcing
18- A new project manager was assigned to the almost finished project; a project schedule was
aggressive and there are more than 1000 stakeholders on it. What should the pm do to
communicate to all stakeholders.
A- Classify the stakeholders into groups, so you can send him their required information
19- Scenario question BLAblaBla…. then he asks what’s the tool used in classifying stakeholders
A- Power/Influence grid
CONFIDENTIAL 2
20- During review the deliverables with the supplier, the PM wants to know the Quality
Specifications, where does he can find this one.
A- SOW
21- During review meetings one of your team members suppose an adjustment that will
improve the process that he works on, what is the primary input to this process.
A- Process improvement plan
22- One of your suppliers exceed the allowable cost stated in the contract, what the PM should
have been done to prevent this issue.
A- Plan procurement (So he can choose the best type of contract)
23- (2)Questions talk about changing in market conditions, what you will do.
A- Make benefit analysis.
24- During receiving proposal from the bidders, you found two offers, the first is low and the
second is high price, what tool you will choose to solve this issue.
A- Independent estimates
25- A Quality team take an action to solve some problems without the PM know about these
ill
A- Change request
iro
26- Supplier reports to the Buyer PM that he cannot deliver ALL deliverables, what should have
been done to prevent this
A- More strict selection criteria
27- As a PM and you are collecting the requirements using group creativity matrix and you are
classifying your ideas, what are you using.
A- Affinity Diagram
28- As a PM, the customer reject one of the deliverables, what should have been done to
prevent this.
A- Allow the customer to anticipate in validate scope
29- Of the total projects in the organization, it’s decided to cancel one of the projects due to
ineffective The Sponsor tells the project manager about decision ... team lose morale
because they heard the news and tell the project manager and expressed their concern
about the loss of their jobs. What a project manager should do.
A- Ask project team to update lesson learned and OPA
CONFIDENTIAL 3
30- As a project manager and you want to close the project and keep your files and records,
which tool is good for this situation.
A- Record Management system
31- You are the project manager in an aircraft manufacturing company developing a new range of
supersonic fighter planes. Since government approval and involvement are essential, you hire a lobbying
firm to get government support to prevent unnecessary changes in your project. Which process is this
an example of.
A- Perform Integrated Change
32- Project manager present the project management plan to the stakeholder according to applicable
policies and procedures. This happens at the end of.
A- Planning
34- One of your team members tells you that his activity takes more than what was planned, you as the
PM told the team that this activity is not exist in the scope. To prove this to your team what will you
review with them.
A- Project scope statement
ill
35- As a pm and you need to control the changes in your project, what is the best reference for that
nw
goal.
iro
36- A scenario about the network diagram, he will give you 3 activities and asks what the type of
dependencies is? (The question from programming field talking about programming a software and it is
difficult)
A- A&B finish to start, B&C finish to finish
37- A question about the chain method (direct question the word BUFFER is clear in the question)
39- A question about bottom-up estimation calculation of cost and materials you should have.
A- WBS
40- An experience project manager give you an advice to check the OPA for the estimation, what will
you use.
A- Analogous estimation
CONFIDENTIAL 4
41- Optimistic= 5, pessimistic=10, most likely= 8, using beta estimation.
A- 7.83
42- As a pm you request an extra money to speed up the project, what will you use.
A- Crashing
43- The sponsor told you that there is a problem in money in the next 3 months, what should have been
done to prevent this problem
44- you are the project manager, one of your team member tell you that the environment of the
production is different than that in the other country where the end user will use the product, how can
you discover this relationship.
A- Scatter diagram
45- 10 points, 5 of them above the mean and 1 point above the UL and 4 under the mean, what is the
situation
A- Out of control
ill
nw
46- You are the pm and you are determining the factors that will affect the final product, what are you
iro
using or working with your team to provide a solution for the problem and product a good quality
product.
A- Design of Experiments
47- A scenario question asks you to connect the steps with the final objectives; or you have defined a
goal for each of the process on what they are accomplishing. You have instructed your team to carefully
understand the steps for getting to the goal, which technique you will use.
48- You are determining whether the project activities comply with organizational and project policies.
This will be done as part of
A- Quality audit
49- The sponsor wants to decrease the HR on the project, what will you review.
A- HR management plan
50- Your team consists of 2 members and you need 6 members, your company didn't allow the
acquisition, what will you do to solve the situation.
CONFIDENTIAL 5
51- One of your team member always finish his work early and leave he’s aggressive with other team
members. What is the reason.
52- Direct question about the develop project team what’s the output.
53- Which project document is used for documenting and monitoring elements under discussion or in
dispute between project stakeholders.
A- Issue log
55- The PM want to send the change request response to the Multinational Stakeholders, what is the
best way to send it.
A- Interactive communication
B- Pull communication
56- As a pm you develop an intranet website, what is the type you are using.
ill
nw
A- Pull communication
iro
57- One of the stakeholders get wrong information about the project, what will you do as a PM.
A- Review communication management plan
58- One of the stakeholders said that he did not receive any report about the project so far, what is the
problem.
A- Communication management plan
59- Direct question on probability and impact, choose the riskiest case.
B 0.5 5 = 2.5
60- Which tool gives you the most impactive risk on the project.
A- Tornado diagram
CONFIDENTIAL 6
61- A project of 3 years, after one and half year a new project manager take was assigned. The team
members told him that a huge water flow will happen and it will effect on the equipment. What will you
do as a first step.
A- Review risk management plan
62- A project have recurring problem in electricity, and you have a server update so you rent a new
generator, what is the type of the response.
A- Mitigation
63- Your contractor takes another work with another customer, what will you do as a project manager
to ensure that his performance does not change.
A- Procurement performance review
64- The project team told you that the cement will be late on arriving to the site and they need to
implement a contingency plan.
A- Workaround
65- A scenario question talks about a risk and you buy insurance, what is the type of the response.
A- Transfer
66- As a project you are controlling the risks, eliminating the old ones and add a new risk, what is the
tool you are using?
ill
A- Risk reassessment
nw
iro
67- As a project manager you are evaluating the risk response strategies, what are you doing.
A- Risk audit
68- A supplier ask you increase on price cause the price of this material is going up and you agree or long
term contracts, what's the type of the contract.
A- FP-EPA
69- The most critical contract type on the buyer, and when the requirements are clear.
A- FFP
70- What is the type of contract with sharing ration term inside it.
A- CPIF
72- Your supplier's performance is going down, what you will do as a pm to check the situation.
A- Procurement performance review
73- You are facing a problem with one of your contractors, and you did not reach an agreement by
negotiation, what is the next step.
A- Arbitration
CONFIDENTIAL 7
74- At the end of the project, your team record just the successful lessons learned what is the next step.
A- Meet with your team and explain to them that's it’s very important to record everything including
the failure ones
75- While you are identifying the stakeholders you use a toll for classifying, what is that tool.
A- Stakeholder analysis
76- You are a project manager in an important project in the organization, and the IT department always
late about delivering their deliverables. You contact the IT manager and he did not resolve the problem,
what is the next step.
A- Escalate the problem for communication plan
77- What is the Document that is used to connect the requirements to their origins.
A- Requirements traceability matrix
78- In a project, all the team do a strike because of the problem in their payrolls, what will you do as a
PM.
A- What if analysis
79- One of the stakeholder was busy and he didn’t attend the early meeting in the starting phase, and
when you reach deliverables acceptance step he reject the deliverables, What should have been done to
prevent this situation.
ill
A- You have to clarify the roles and responsibilities for all stakeholders early in the project
nw
iro
80- The Sponsor asks you to start a project the develop a new software for the company, what is the
first step you will do.
A- Project charter
81- You are a new PM in a project instead of old PM, and you start sending reports to the CEO every
week, your sponsor call you and he said you must correct your action by reviewing.
A- Communication management plan
82- What is the tool you use to arrangement the sub-goals or ideas.
A- Prioritization matrix
83- Key supplier ask the PM that he want to start transferring the material and equipment before
signing the contract, what's your decision as a PM.
A- Review company policy
84- The sponsor call you and he said you should close the project immediately, one of your supplier start
sending his material. What will you do as a PM.
A- Tell the supplier to stop sending his materials immediately
CONFIDENTIAL 8
85- In the project, the pm always accept the customer change request so he make the customer
satisfied, after one month the pm find that the budget is over. What should have been done to prevent
this issue.
A- Follow change management plan
86- A question about the communication methods that requires a feedback from the receiver.
A- Interactive communication
87- A question said that you send an email to the customer, what you should do to ensure the customer
received the email.
A- Follow the email
B- Ask for acknowledge
88- The customer asks a change that affects the SOW, what should you do?
A- Reject the change request
89- A scenario talks about buying material from the market, the price of the material at the start of the
project is 10000, and during the project the price changes from 6000 to 16000
A- The right answer is 10.33
90- The sponsor calls the PM and he said that you are fired because you fail in communication. What is
the main problem.
ill
91- The sponsor asks the PM to give him a new thought about the project management plan, what the
PM should do.
A- Meet with key stakeholders and start brainstorming
92- A new problem has arisen between two of project team, what the PM should do.
A- Meet with the two-team members
93- In one of the project meeting, the PM did not reach an agreement with one of the key stakeholders
and the issue becomes more complicated, what should the PM do.
A- Close the meeting and meet with the concerned key stakeholder
94- While executing the project works what is the main responsibility of the project manager
95- There is change request has been discussed through CCB and has been approved official what is the
next step.
A- Take authorize from sponsor (you will select this if the sponsor not include in CCB)
CONFIDENTIAL 9
96- If you implement risk response and raise risk as a direct outcome
A- Secondary risk
A- Prevention cost
99- The project charter has not yet been approve and one week before it was approved, a new law was
passed which affects the project which document you will review.
A- SOW
100- A product you want to see if the has measurement are compatible with the customer’s
requirements and you find the product can give more which type of risk you will take.
A- Exploit
102- Transfer the ownership of deliverables to the ……… in accordance with the project plan in order to
facilitate project closer.
A- Assigned stakeholder
103- The sponsor complained, the IT manager inform the project manager the sponsor not satisfied.
A- Function organization
104- One can use different methodologies, tools agile, and waterfall to implement the project
management framework.
105- The test for product need special tests and is no capable people in the company and it is costly
from outside and will delay the project.
106- To develop the quality process to understand and calculate the cost of quality in the project use.
A- Flowchart
CONFIDENTIAL 10
107- After CCB approved any change request you should update.
A- Lessen learned
109- Where you can find Assumption, Constrains and the Key deliverables.
A- Sponsor
111- A question about an activity of work package the budget 2000$ after two third of project the
project manager exchange 1500$ what is the stats of budget.
A- Over Budget
A- Incomplete
ill
nw
A- Project charter
A- Fast track
A- -25 to +75
116- What is the tool using for benefit prioritization, or most frequent failures or most priority or 20/80.
A- Pareto chart
117- To go over the project risks to make sure if they are still valid or not, if required you also change the
risk response strategy based upon the project performance.
A- Risk assessment
CONFIDENTIAL 11
118- Keep track of the quality of the parts being produced or make balance limited which tool to be the
best.
A- Control chart
119- Your team stuck with problem and you recommended them to consider the problem as a gap that
needs to be closed, you also tell them to find list of all the probable causes (root causes) due to which
the problem has occurred, what tool you use.
A- Ishikawa diagrams
120- Your project is hit by an unidentified risk which was never planned (risk is realized) what type of
this.
A- Workaround
121- You are PM and track your project setup weekly meeting for the activities which are completed and
which planned and the states of reports and discuss any problem need immediate attention, which
document you will use.
A- Issue log
122- What is the tool use for qualitatively analyze risk or concentrating only on the main risk.
ill
nw
A- Execution
124- To avoid the risk in the long term projects prefer to use which of the following contract type.
A- FP-EPA
126- An intentional activity that ensues the future performance of the project work is aligned with
project management plan you can use.
A- Preventive action
127- An intentional activity that realigns the performance of the project work with project management
plan you can use.
A- Corrective action
CONFIDENTIAL 12
128- Manage changes to the project by following the change management plan in order to ensure that.
129- You are in the process to get the final acceptance on the deliverables to make sure project scope
and deliverables are achieved.
130- You are in the process to obtaining the feedback from stakeholder to evaluate their satisfaction
from project, which process.
A- Closing
131- You are working in your project so the sponsor informed you the funding for this project is given
to some other project what will you do.
132- Your project has been hit by lot of risks these days and you are worried for your project, you plan
to reviewing the issue log and determine any corrective actions if required, what is the primary
purpose to doing this.
133- You are a project manager and you are in the closing stages of the project, the sponsor has
requested you to make sure that you are archiving project documents and materials, what is the
primary purpose of doing this.
134- What is the primary purpose of identifying key deliverables based upon the project requirements.
135- You are a project manager and you are working with stakeholders to conduct the benefit analysis,
what is the purpose of doing that.
136- You are working on a very large project involves multiple departments, each department head are
interested in seeing work packages or project activities that are assigned to their respective department
on the project, which you will need for this.
CONFIDENTIAL 13
137- You have identified the project risks, based upon customers recommendation you have also
prioritized the risk based upon the probability and impact, however the customer is not convinced and
want you to reprioritize the project risks with some information and analysis, which process next.
138- Team have a list of meaningful requirements, and then the team will do voting to prioritize the
requirements, which tool.
139- If your project is running behind schedule and over budget, the sponsor is not happy for this
situation and has requested you to provide him earned value number and you report him that the
sponsor not able to understand this reporter and he ask for more explanation, what reported did you
send.
A- S-curve report
140- An external supplier delays in the delivery the contract with him by hour, what you will do as
project manager.
141- One stockholder was identified in the executed stage what you will first.
nw
iro
142- A team member resigned in the middle of the project, the project team informed the project
manager to complete the project without replace him, what did you do.
143- The sponsor ask the project manager to repeat the information to help him to deliver it to SH.
144- There are number of projects in the company, one of them will be terminate what is the following.
145- The project manager discovered that some of WBS were missing what is the following.
146- The changes which causing scope creep its main there is problem in.
CONFIDENTIAL 14
147- The changes that affect the budget its main there is problem in.
148- If the seiner management informed you to terminate the project you must update the following
before they leave the project.
A- Lessen learned
149- If the customer ask for project terminated before the planned time at lest you should do.
150- If the project manager is informed that the project does not meet the objectives and is not in line
with the organizations strategy, you should make.
151- The senior management discuss some project for purpose of benefiting to organization.
A- Business case
153- You are the project manager for your organization. You have just been assigned a new project
with a predetermined budget of $250,000. This is an example of which one of the following.
A- Constraint
154- Project A will arrange some purpose with project B what is project A need from project B.
A- SOW
155- Question some values in big table include AC =8200, EV = 7500, PV = 8700 what is the stats of
project.
A- Initiation
157- You are project manager and involved in developing a project charter what information you need.
A- SOW
CONFIDENTIAL 15
158- Project manager calculate the duration of the activates and seek help from others who the best
can help him.
159- The customer ask for some orders and he will not accept the deliverables until he gets his order
what is the project manager should review.
A- Scope baseline
160- If a third person is appointed to make an independent assessment what is that mean.
161- The company make RFP and the sellers are apply what is the first thing the project team can do.
A- Select seller
162- These is a problem between two-team member and the project manager failed to fix it.
A- Compromise
164- Project Weakness, Strength and team recommendation, where we can store this.
165- A project in planning stage the project sponsor has been resigned, the new sponsor delay the
project two months because lack of scope what is the project manager can do.
A- Meeting with the project sponsor and the team to find out the impact of delaying on time,
cost and personal affairs
166- A client contracted with a subcontractor for a 12-months building project after 3 months the
customer request to close the project within 6 months what is the next action.
A- Negotiate with the client to increase the cost and apply for change request
167- One team member suggested working on an initial model that would prevent future change from
a proposal that would increase the cost what is the project manager could do next.
CONFIDENTIAL 16
168- The first project expert informs the project manager that there is a slight change to the product
but does not affect the schedule and cost what is the next action.
169- The Project Manager decides to make two sessions each session has number of tests after the start
of the first course of the test. The project manager tells the team that there will be a delay at the end of
the project. One of the team members suggests reducing the number of tests so that the project will not
delayed in the schedule what is the next action.
170- A project for a customer where the user's access numbers are updated and the numbers are sent to
customers and the project will be closed what is the next action.
171- The senior management asking a project manager to study several projects and record
observations and problems. This resulted in several projects how to choose between them.
172- A project manager who is working with vender to create the deliverable of the project from
ill
quality background he often make sure that the thoroughly tests the processes and deliverable which
nw
173- You have identified the risks and identified the planned responses for those risks, your project is
hit by many risks but it did not effect, you have decided to perform control risk more often, which
document has the most probability of getting updated as a consequence of performing control risk
process.
A- Risk register
174- A company has projects are always delayed in schedule and increase in cost than budget , the
customer has requested for changes you are not sure which all change requests should go through,
which document can help.
175- How the project manager protect the projects from cost overruns.
A- Change request
CONFIDENTIAL 17
176- An external vendor sends error information to the project manager, which causing the project
manager not to communicate the correct status of the stakeholders what is the project manager do.
177- If you discovered from the phase review that the project does not achieve the goal.
178- One of the key stakeholders asked for a verbal change the project manager registered that with
the change management system, what kind of change request is in case it is implemented as an activity
that ensures that the work in the project is reconfigured to conform to the baseline.
A- Corrective action
179- A team member told you there was a delay in the project and the project manager reviewed
everything with the critical path, what is the next action.
A- Compress schedule
180- If there is conflict between key stockholder and the project manager what you will do.
CONFIDENTIAL 18