PURCHASER STR DGN OF TT "DA (0 DEG.

)" WITH HTLS


RS INFRA PROJECT 132 KV D/C Kusaha – Biratnagar TL
NEA CONDUCTOR (WZ 4)

Calculation of Wind Loads


Narrow Front Wind
Tower Actual Gross Solidity Drag Gust Wind Over Ult Wind Loads Ult Wind Loads Ult Wind Loads
Panel Face Projected Area Ratio Coefficient Response Pressure Load θ= 0 θ= 45 θ= 90
Descreption Area [Aa]/[Ag] Factor Factor F wt TRANS F wt LONGI F wt TRANS F wt LONGI F wt TRANS F wt LONGI

[Aa] [Ag] [ø] [Cdc] [Gt] [Pd]


(sqm) (sqm) (Kg/sqm) (Kg) (Kg) (Kg)

Peak
to Trans 1.014 3.246 0.312 2.463
1.00 354.6 1.02 903 0 766 1455 0 1715
TXA Long 1.842 6.546 0.281 2.574

TXA
to Trans 1.431 5.715 0.250 2.698
1.00 354.6 1.02 1396 0 1185 1943 0 2290
MXA Long 2.285 9.842 0.232 2.771

MXA
to Trans 1.694 6.745 0.251 2.695
1.00 354.6 1.02 1651 0 1401 2239 0 2639
BXA Long 2.600 11.627 0.224 2.806

BXA
to Trans 8.228 69.375 0.119 3.307
1.00 354.6 1.02 9841 0 8350 8350 0 9841
NT Long 8.228 69.375 0.119 3.307

NT
to Trans 3.701 39.584 0.093 3.426
1.00 354.6 1.02 4586 0 3891 3891 0 4586
+6M BE Long 3.701 39.584 0.093 3.426

+6M BE
to Trans 6.067 75.065 0.081 3.477
1.00 354.6 1.02 7629 0 6474 6474 0 7629
+9M LE Long 6.067 75.065 0.081 3.477

RS/NEA/132KV/STR-DGN/DA/01 Page 15