Professional Documents
Culture Documents
Case-Study 1
Case-Study 1
Case-Study 1
SUBMITTED TO SUBMITTED BY
AR. HIMMAT BHATIA ANIKET (11919196)
KUNAL (11914150)
Firstenburg Community Center
Vancouver, Washington.
Project Summary Building Footprint: 64,003 sf
Location: Vancouver, Washington Cost: $17M
Gross Sf: 80,982 sf Completed: 2007
Site Features
1 Library, Completed 2010
2 Courtyard with Spray Ground
3 Bus Stop
4 Future Lap Pool
5 Bike Parking
6 Firstenburg Community Center
7 Walking Trail / Service Lane
8 Porous Concrete Paving
9 Established Coniferous Forest
10 Future Parking
2
6
12
5 11
10
LEED NC v.2.1 Credits Achieved Wind Colored areas indicate wind direction and speed;
Site 8/ 14 darker colors indicate higher wind frequency
Water 4/5 N N N N
Energy 6/ 17
Materials 6/ 13
Indoor Quality 11/15
Innovation 4/ 5
Total = 39 Credits; Minimum for LEED Gold = 39
Spring Summer Fall Winter
SITE ECOLOGY AND LAND USE
The building takes advantage of the park-like setting with large windows for
daylighting
courtyards to allow interior functions to participate with the natural landscape
Use of alternative transportation is encouraged by building a bus stop and shelter
The parking lot’s organic shape maximizes the number of significant existing trees
retained
Program
1 Community Room 9 Mechanical
2 Game Room 10 Track
3 Juice Bar 11 Fitness
4 Pool 12 Multi-purpose 9 10
5 Locker Room
6 Rock Climbing
7 Gym OPEN TO BELOW
8 Administration
OPEN TO BELOW
11 12
Level 2
WATER
CYCLE
By carefully selecting drought tolerant native plants
Water Use Reduction that can survive the region’s dry summers and using
500,000high efficiency irrigation technology, water use for
irrigation was reduced by over 50%.
domestic
many of the
100,000building’s toilets. Approximately 60,000 gallons of
‘recycled’ graywater are used annually. gallons
per year 0
Monthly Precipitation
7”
Baseline
Firstenburg Community Center
3”
J F M A M J J A S O N D
Total Annual Precipitation = 39.96 inches
ENERGY FLOWS
Sustainability goals identified at an early design charette highlighted maximization
of transparency between spaces, using daylight throughout the entire building
long thin building footprint that allows for exceptional daylight and cross ventilation
Radiant concrete slab floors are heated or chilled to maintain comfortable
temperatures throughout the year while using minimal energy
A central heat pump recovers waste heat in the summer and uses it to heat the
pool and domestic water
energy use is anticipated to be at least 27% less than traditional building
construction.
MATERIALS AND CONSTRUCTION
Materials have been selected for their durability, beauty, and sustainability.
The exterior wood rainscreen system that provides durable protection for the building’s
waterproofing, was constructed with Forest Stewardship Council certified sustainably harvested
wood.
The bamboo community room flooring and acoustical wall paneling made from perforated
wheatboard are quick growing ‘rapidly renewable’ materials.
Recycled materials such as the glass wall tiles used in the locker rooms and natatorium make up
nearly 30% of all construction
Use of unnecessary materials was eliminated with the use of exposed steel structure, ground
face concrete masonry block walls, and concrete floors, and passive heating and cooling
eliminates substantial need for ductwork.
Douglas fir trees were harvested,
locally milled and used throughout the
Center.
29% 56%
Recycled Materials used for Of Wood Base
Construction Building Products are
Forest Stewardship Council Certified
99.4%
Construction Waste was Recycled
41%
Regional Materials
Manufactured within
500 Miles used for
Construction
East-West Section
LEARNING OUTCOMES