The purpose of this script is to review the features available in EBS Landed Cost Management
new in release 12.1.1. This script focuses on the Landed Cost as a Service or Blackbox method
where the estimated landed costs are calculated after the receipt.
What's New?
Pitfalls
There are two (2) bugs that you should be aware of:
767034 (base ticket 7746477): updated costs not reflected in the Landed Cost
Management workbench. Sometimes when the landed cost calculations (ALC calcs) are
ran, the updated costs might not display in the LCM workbench. A work-around is to
access the LCM workbench via Navigator using Landed Cost Management, Vision Ops >
Workbench > Shipments.
8411594: multiple validations of the landed cost invoice inflate the value in the LCM
workbench. As a work-around follow the steps in the script.
Review repository ticket 288096 to get more information:
http://adsweb.oracleads.com/pls/ads/ads_ticket.details?pticket=288096
Related Documents
Begin Demo
Introduction
1. Overview and benefits
Overview:
Oracle Landed Cost Management enables you to manage estimated and actual landed cost for an
item purchased from a supplier. Landed Cost Management allows you to determine the "real"
costs associated with acquiring items including insurance, transportation, handling, storage costs,
container fees, and import or export charges.
Benefits:
Maximize profit: by illuminating "real" product costs, organizations have the opportunity
to identify areas for potential cost reduction.
Increase competitiveness: when all of the charges, fees, duties and taxes are known,
companies can more strategically source products/components from lower cost foreign
locations and enables companies to better justify contracts with vendors or potential
customers.
Increase visibility: itemizing and tracking all acquisition costs and material cost elements
as they apply to a product enables organizations to better link their product supply flows
with their financial processing and reporting.
Ensure compliance: Oracle Landed Cost Management gives you the option to determine
and calculate estimated landed costs before the receipt of the items into inventory (a
requirement in India, Brazil, and Romania) or after the receipt of the item into inventory.
Pre-receiving: determine and calculate estimated landed costs before the receipt of the
items into inventory. This is a requirement in many foreign countries like India, Brazil,
and Romania.
LCM as a service (Blackbox): determine and calculate estimated landed costs after the
receipt of the item into inventory. This script focuses on the Blackbox or Landed Cost
as a Service method.
Login to EBS
3. Login to EBS
Enter the information as pictured below; make sure to enter a Need By date, and then
Save.
Click the Switch Responsibility button and select the Distribution Manager
responsibility.
Navigate to Receipts using Purchasing > Receiving > Receipts, and select the Los
Angeles Inventory Organization.
You will need to run the Landed Cost Integration Mgr request as the Distribution Mgr, and
then the Shipments Interface Import request as the Landed Cost Mgmt, Vision Ops
responsibility.
Run the Landed Cost Integration Mgr process from View > Requests > Submit a New
Request.
Run Shipments Interface Import request from View > Requests > Submit a New
Request.
7. View the estimated landed cost in the Landed Cost Management workbench
Access the LCM workbench via Navigator using Landed Cost Management, Vision Ops
> Workbench > Shipments.
Enter the pictured data to retrieve the shipment, set the Actions to View Landed Costs,
and then click Go.
Enter the PO (and tab-out of the field to retrieve the PO information), Invoice Date,
Invoice Num, Invoice Amount like pictured (note that the PO amount was $ 1,656.00),
and then click Match.
Select the Match row, enter the Match Amount, and then click Match.
To validate the invoice click the Actions button, check Validate, and then click OK.
Use the Landed Cost Management, Vision Operations responsibility and run Matches
Interface Import.
Enter the values pictured below, set the Actions to View Landed Cost, and then click
Go.
You will see the updated actual cost from the item invoice.
Enter United Postal Service for the Trading Partner, Supplier Site of UPS – HQ, Invoice
Date, Invoice Num, Invoice Amount, make sure the Match Action is set to Receipt, and
then click Match.
Set the Cost Factor Name to LCM Freight Charges, enter the Amount, select the row,
and then click Match.
Secondly, create the invoice line for the landed cost insurance charge.
Back on the Invoice Workbench and within the same row LC freight was entered click
Match again.
Set the Matching Type to Miscellaneous, enter the item supplier, enter the receipt, and
then click Find.
You will be returned back to the Invoice Workbench. Now you will need to validate the
invoice row for landed costs. However, keep in mind, that due to taxes you will need to do
this twice.
Back on the Invoice Workbench click the Actions button, check Validate, and then click
OK.
Because of taxes you will need to re-validate the invoice – the Invoice Amount in the
header must match the Total (General tab) from the lines below. Manually enter the
value from the Total field in the lines into the Invoice Amount in the header and then
Validate again (Actions button, check Validate, OK).
First run Matches Interface Import using the Landed Cost Management, Vision Operations
responsibility.
Click the Switch Responsibility button and select the Landed Cost Management, Vision
Operations responsibility.
Access the LCM workbench via Navigator using Landed Cost Management, Vision Ops
> Workbench > Shipments.
You will now see the actual landed costs (based on the invoice) compared to the estimated
amount as calculated by Advanced Pricing rules.
Demo Support
Please see http://adsweb.oracleads.com > (M) Support > Procedures, for current information
regarding demonstration support.
Introduction
Overview & benefits (1)
Login to EBS
Login to EBS (3)
Review LCM
Blackbox
Create & approve a
P.O. (PO) (4)
Receive items into
Inventory Organization
(5)
Run estimated landed
cost calculations (6)
View estimated landed
cost in Landed Cost
Management
workbench (7)
Enter Item Invoice (8)
Run actual landed cost
calculations (9)
Review actual landed
cost for item in Landed
Cost Management
workbench (10)
Create landed cost
invoices (11)
Run actual landed cost
calculations (12)
View actual landed
costs in workbench (13)