Daily Target ISBL (Aug 14, 2020)
Daily Target ISBL (Aug 14, 2020)
Daily Target ISBL (Aug 14, 2020)
August 20
Tag No. Activity Qty. Start Plan Finish Plan Status
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
AV-3113
Hydrotest
VBT & Inspection 8/10/2020 8/10/2020
Filling Water 8/10/2020 8/12/2020
Holding time 24 hour 8/13/2020 8/13/2020
Full Water Test 8/13/2020 8/13/2020
Dewatering 8/14/2020 8/15/2020
Cleaning After Hydrotest 8/16/2020 8/18/2020
Inspection
Internal Inspection 8/19/2020 8/19/2020
Internal Inpection Killing Punch 8/20/2020 8/21/2020
Final visual inspection with NSCL 8/24/2020 8/24/2020
Killing Punchlist 8/25/2020 8/26/2020
Closing Punchlist with NSCL 8/27/2020 8/27/2020
Hand Over to IKPT 8/28/2020 8/28/2020
AV-3139C
Hydrotest
Cleaning Surface 8/12/2020 8/16/2020
Inspection 1 8/18/2020 8/18/2020
Cleaning After Inspection 8/19/2020 8/20/2020
Inspection 2 8/21/2020 8/21/2020
Pickling 8/22/2020 8/22/2020
Remove Inside Scaffolding 8/23/2020 8/24/2020
VBT & Inspection 8/25/2020 8/25/2020
Filling Water 8/25/2020 8/27/2020
Holding time 24 hour 8/28/2020 8/28/2020
Full Water Test 8/28/2020 8/28/2020
Dewatering 8/29/2020 8/30/2020
Cleaning After Hydrotest 8/31/2020 9/2/2020
Inspection
Internal Inspection 9/3/2020 9/3/2020
Internal Inpection Killing Punch 9/4/2020 9/5/2020
Final visual inspection with NSCL 9/7/2020 9/7/2020
Killing Punchlist 9/8/2020 9/9/2020
Closing Punchlist with NSCL 9/10/2020 9/10/2020
Hand Over to IKPT 9/11/2020 9/11/2020
AV-3150
Hydrotest
Brushing Inside Tank 8/15/2020 8/16/2020
Inspection
Internal Inspection 8/18/2020 8/18/2020
Internal Inpection Killing Punch 8/19/2020 8/20/2020
Final visual inspection with NSCL 8/24/2020 8/24/2020
Killing Punchlist 8/25/2020 8/26/2020
Closing Punchlist with NSCL 8/27/2020 8/27/2020
Hand Over to IKPT 8/28/2020 8/28/2020
AV-3084
Stairway
Fit-up Handrail Stairway 8/12/2020 8/15/2020
Welding Handrail Stairway 8/13/2020 8/16/2020
Hydrotest
Cleaning Surface 8/17/2020 8/24/2020
Inspection 1 8/22/2020 8/22/2020
Cleaning After Inspection 8/23/2020 8/23/2020
Inspection 2 8/24/2020 8/25/2020
Pickling 8/26/2020 8/27/2020
Remove Inside Scaffolding 8/28/2020 8/29/2020
VBT & Inspection 8/30/2020 8/30/2020
Filling Water 8/31/2020 9/2/2020
Holding time 24 hour 9/3/2020 9/3/2020
Full Water Test 9/3/2020 9/3/2020
Dewatering 9/4/2020 9/5/2020
Cleaning After Hydrotest 9/6/2020 9/8/2020
Inspection
Internal Inspection 9/9/2020 9/9/2020
Internal Inpection Killing Punch 9/10/2020 9/11/2020
Final visual inspection with NSCL 9/14/2020 9/14/2020
Killing Punchlist 9/15/2020 9/16/2020
Closing Punchlist with NSCL 9/17/2020 9/17/2020
Hand Over to IKPT 9/18/2020 9/18/2020
AV-3133
Hydrotest
Grind Flush 8/12/2020 8/16/2020
Cleaning Surface 8/17/2020 8/24/2020
Inspection 1 8/22/2020 8/22/2020
Cleaning After Inspection 8/23/2020 8/23/2020
Inspection 2 8/24/2020 8/25/2020
August 20
Tag No. Activity Qty. Start Plan Finish Plan Status
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Pickling 8/26/2020 8/27/2020
Remove Inside Scaffolding 8/28/2020 8/29/2020
VBT & Inspection 8/30/2020 8/30/2020
Filling Water 8/31/2020 9/8/2020
Holding time 24 hour 9/9/2020 9/9/2020
Full Water Test 9/9/2020 9/9/2020
Dewatering 9/10/2020 9/13/2020
Cleaning After Hydrotest 9/14/2020 9/15/2020
Inspection
Internal Inspection 9/16/2020 9/16/2020
Internal Inpection Killing Punch 9/17/2020 9/18/2020
Final visual inspection with NSCL 9/20/2020 9/20/2020
Killing Punchlist 9/21/2020 9/22/2020
Closing Punchlist with NSCL 9/23/2020 9/23/2020
Hand Over to IKPT 9/24/2020 9/24/2020
August 20
Tag No. Activity Qty. Start Plan Finish Plan Status
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
AV-3611A
Shell Nozzle
Nozzle N-11
Marking 8/12/2020 8/12/2020
Cutting 8/12/2020 8/12/2020
Fit-Up Repad 8/13/2020 8/13/2020
Welding Repad 8/14/2020 8/14/2020
Fit-Up Nozzle 8/15/2020 8/15/2020
Welding Nozzle 8/16/2020 8/17/2020
Roof Nozzle
Nozzle N-1
Marking 8/12/2020 8/12/2020
Cutting 8/12/2020 8/12/2020
Fit-Up Repad 8/13/2020 8/13/2020
Welding Repad 8/14/2020 8/14/2020
Fit-Up Nozzle 8/15/2020 8/15/2020
Welding Nozzle 8/16/2020 8/17/2020
Nozzle N-2
Marking 8/12/2020 8/12/2020
Cutting 8/12/2020 8/12/2020
Fit-Up Repad 8/13/2020 8/13/2020
Welding Repad 8/14/2020 8/14/2020
Fit-Up Nozzle 8/15/2020 8/15/2020
Welding Nozzle 8/16/2020 8/17/2020
Nozzle N-3
Marking 8/12/2020 8/12/2020
Cutting 8/12/2020 8/12/2020
Fit-Up Repad 8/13/2020 8/13/2020
Welding Repad 8/14/2020 8/14/2020
Fit-Up Nozzle 8/15/2020 8/15/2020
Welding Nozzle 8/16/2020 8/17/2020
Nozzle N-4
Marking 8/12/2020 8/12/2020
Cutting 8/12/2020 8/12/2020
Fit-Up Repad 8/13/2020 8/13/2020
Welding Repad 8/14/2020 8/14/2020
Fit-Up Nozzle 8/15/2020 8/15/2020
Welding Nozzle 8/16/2020 8/17/2020
Nozzle N-5
Marking 8/12/2020 8/12/2020
Cutting 8/12/2020 8/12/2020
Fit-Up Repad 8/13/2020 8/13/2020
Welding Repad 8/14/2020 8/14/2020
Fit-Up Nozzle 8/15/2020 8/15/2020
Welding Nozzle 8/16/2020 8/17/2020
Nozzle N-13
Marking 8/12/2020 8/12/2020
Cutting 8/12/2020 8/12/2020
Fit-Up Repad 8/13/2020 8/13/2020
Welding Repad 8/14/2020 8/14/2020
Fit-Up Nozzle 8/15/2020 8/15/2020
Welding Nozzle 8/16/2020 8/17/2020
Manhole M-1
Marking 8/12/2020 8/12/2020
Cutting 8/12/2020 8/12/2020
Fit-Up Repad 8/13/2020 8/13/2020
Welding Repad 8/14/2020 8/14/2020
Fit-Up Nozzle 8/15/2020 8/15/2020
Welding Nozzle 8/16/2020 8/17/2020
Stairway
Erection Stringer 8/11/2020 8/11/2020
Fit-up Inner Stringer 8/12/2020 8/12/2020
Fit-up Outer Stringer 8/12/2020 8/12/2020
Welding/Tightening Inner Stringer 8/13/2020 8/13/2020
Welding/Tightening Outer Stringer 8/13/2020 8/13/2020
Fit-up Step Stairway 8/14/2020 8/17/2020
Welding Step Stairway 8/15/2020 8/18/2020
Hydrotest
Grind Flush 8/15/2020 8/18/2020
Cleaning Surface 8/19/2020 8/26/2020
Inspection 1 8/24/2020 8/24/2020
Cleaning After Inspection 8/25/2020 8/25/2020
Inspection 2 8/26/2020 8/27/2020
Pickling 8/28/2020 8/29/2020
Remove Inside Scaffolding 8/30/2020 8/31/2020
VBT & Inspection 9/1/2020 9/1/2020
Filling Water 9/2/2020 9/10/2020
Holding time 24 hour 9/11/2020 9/11/2020
Full Water Test 9/11/2020 9/11/2020
Dewatering 9/12/2020 9/16/2020
Cleaning After Hydrotest 9/17/2020 9/21/2020
Inspection
Internal Inspection 9/24/2020 9/24/2020
Internal Inpection Killing Punch 9/25/2020 9/26/2020
Final visual inspection with NSCL 9/27/2020 9/27/2020
August 20
Tag No. Activity Qty. Start Plan Finish Plan Status
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Killing Punchlist 9/28/2020 9/29/2020
Closing Punchlist with NSCL 9/30/2020 9/30/2020
Hand Over to IKPT 9/30/2020 9/30/2020
August 20
Tag No. Activity Qty. Start Plan Finish Plan Status
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
AV-3601
Hydrotest
Cleaning Surface 8/19/2020 8/24/2020
Inspection 1 8/22/2020 8/22/2020
Cleaning After Inspection 8/23/2020 8/23/2020
Inspection 2 8/24/2020 8/24/2020
Pickling 8/25/2020 8/25/2020
Remove Inside Scaffolding 8/26/2020 8/27/2020
VBT & Inspection 8/27/2020 8/27/2020
Filling Water 8/28/2020 8/30/2020
Holding time 24 hour 8/31/2020 8/31/2020
Full Water Test 8/31/2020 8/31/2020
Dewatering 9/1/2020 9/2/2020
Cleaning After Hydrotest 9/3/2020 9/4/2020
Inspection
Internal Inspection 9/7/2020 9/7/2020
Internal Inpection Killing Punch 9/8/2020 9/9/2020
Final visual inspection with NSCL 9/10/2020 9/10/2020
Killing Punchlist 9/11/2020 9/12/2020
Closing Punchlist with NSCL 9/14/2020 9/14/2020
Hand Over to IKPT 9/15/2020 9/15/2020
VITY
September 20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 12 13 20 21 22 23 24 12 13 27 28 29 30
September 20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 12 13 20 21 22 23 24 12 13 27 28 29 30
September 20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 12 13 20 21 22 23 24 12 13 27 28 29 30
September 20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 12 13 20 21 22 23 24 12 13 27 28 29 30
September 20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 12 13 20 21 22 23 24 12 13 27 28 29 30
DAILY TARGET ISBL AREA AS PER REMAINING ACTIVITY