Professional Documents
Culture Documents
Pipe Pile Foundation Science Direct
Pipe Pile Foundation Science Direct
Pipe Pile Foundation Science Direct
Pipe piles are available in many sizes, and 12-inch diameter pipe piles have a range
of thicknesses.
Related terms:
Bearing Capacity, Steel Pipe, Wellheads, Skin Friction, Concrete Pile, End Bearing,
Friction Angle, Groundwaters
Pile foundations
Ruwan Rajapakse PE, CCM, CCE, AVS, in Geotechnical Engineering Calculations and
Rules of Thumb (Second Edition), 2016
A pipe pile is covered with an end cap. The end cap is welded as shown in Plates
40.4–40.8.
• In the case of closed-end driving, soil heave can occur. There are occasions
where open end piles also generate soil heave. This is due to plugging of the
open end of the pile with soil.
• Pipe piles are cheaper than steel H-piles or concrete piles.
40.5.4 Telescoping
Figure 40.15 shows telescoping to improve driving ability.
Figure 40.15. Telescoping to improve driving ability.
• Due to the smaller diameter of the telescoping pipe pile, the end bearing
capacity of the pile would reduce. To accommodate the loss, the length of the
telescoping pile should be increased.
Bridge foundations
V. Modeer, ... T. Cooling, in Innovative Bridge Design Handbook, 2016
Figure 23.5. Driving 1.82-m-diameter, 85-m-long open-end pipe piles for the New
Tappan Zee Bridge over the Hudson River, New York(courtesy New York State
Thruway Authority).
Figure 23.6. Driving 2.5-m piles for the San Francisco-Oakland Bay Bridge with
hydraulic impact hammer(courtesy California DOT).
Note: H-piles have lesser perimeter area compared to similar pipe piles. Hence,
H-piles would have less downdrag. On the other hand, H-piles are much more
expensive than pipe piles (without bitumen coating). A cost comparison between
bitumen-coated pipe piles and H-piles was done and bitumen-coated pipe piles
were selected.
• Structural steel piles should conform to ASTM A36, ASTM A572, and ASTM
A588.
• Steel pipe piles should conform to ASTM A252.
• Steel-encased cast-in situ concrete piles should conform to ASTM A252, ASTM
A283, ASTM A569, ASTM A570, or ASTM A611.
• The allowable design stress in steel should not be more than 35% of the
minimum yield strength of steel.
• The allowable design stress in concrete should not be more than 1/3 of the
minimum concrete strength.
• The allowable design stress in steel should not be more than 40% of the
minimum yield strength of steel.
• The allowable axial design compressive stress applied to the full cross-section
should not exceed 33% of the specified minimum concrete strength minus
27% of the effective prestressed force.
• Thin shells less than 0.1 in. thick should not be considered as load-carrying
members.
• The allowable design stress in concrete should not be more than 1/3 of the
minimum concrete strength.
• The allowable design stress in steel should not be more than 40% of the
minimum yield strength of steel.
• The allowable design stress in concrete should not be more than 1/3 of the
minimum concrete strength.
• The allowable design stress in steel should not be more than 40% of the
minimum yield strength of steel.
• Maximum driving stress for steel piles = 0.9 fy (for both tension and compres-
sion): fy = yield strength.
• Maximum driving stress for timber piles = 2.5 × (z) (here, z = allowable design
strength of timber piles).
• Maximum driving stress for precast concrete piles = 0.85 fc for compression;
= 3(fc )1/2 for tension; fc = 28 day concrete strength
• Maximum driving stress for prestressed concrete piles = (0.85fc − fpe) for
compression (fpe = effective prestress, force).
• Maximum driving stress for prestressed concrete piles = (3(fc )1/2 + fpe) for
tension (fpe = effective prestress force).
Example 6.7
Calculate the composite pipe pile of Figure 6.22, where the actual moment of inertia
is described as follows:
Figure 6.22. Composite pipe pile of Example 6.7.
Do1=1800 mm
Di1=1730 mm
Do2=1600 mm
Di2=1540 mm
I1=π[(Do1)4 – (Di1)4]/64=7,5601,916,209 mm4
I2=45,607,749,335
It=I1+I2=1.2121×1011 mm4
A1=π[(Do1)2 – (Di1)2]/4=194,071.8862 mm2
A2=147,969.014 mm2
AG=339,998.8649 mm2
I=1.2121×1011 mm4
Do=1800 mm
Di={[I (64)/π] – ( Do)4}0.25=1683.28 mm
t=Do – Di=58.36 mm
Area=π[(Do1)2 – (Di1)2]/4= 319,317.75 mm2
Elastic modulus for steel, Es=210,000 MPa
Elastic modulus for grout, EG=30,000 MPa
Et={Es [(Do1)2−(Di1)2]+Es (Do2)2−(Di2)2}+EG [(Di1)2−(Do2)2]/Do=32,235 MPa
16.2. Monopiles for the North Hoyle wind farm (© RWE Innogy GmbH).
Acting as an extension of the tower into the subsoil, the monopile is the simplest
foundation solution, but at the same time it shows a very complex load transfer
behaviour as it has to carry the whole environmental and operational loading. The
loading is predominantly transferred into the subsoil by lateral bedding as the
amount of vertical loading and torsional moments in contrast to horizontal loading
and bending moments is very small. The pile head is freely supported and the pile is
flexible with a full or partial restraint in the soil. This concept is depicted in Fig. 16.3.
Near-surface soil layers with a sufficient bearing capacity are therefore of vital
importance for the lateral load transfer.
16.3. Load transfer behaviour of monopole foundations.
Up to now monopiles have only been installed in water depths up to about 25 m
with correspondingly moderate wave loading. Deeper water and the accompanying
increase in loading, as well as higher performance wind turbines, directly result
in greater diameters and embedment lengths of a monopile and may lead to
uneconomic and technically unfavourable design solutions.
(4.14)
where = a dimensionless factor and c = undrained shear strength of the soil at the
point in question.
(4.15)
with the constraint that ≤1.0, where = c/p, for the point in question and p is the
effective overburden pressure at the point in question (in kPa). For underconsoli-
dated clays, clays with excess pore pressures undergoing active consolidation, can
usually be taken as 1.0.
The appropriate methods for determining the undrained shear strength, c, and
effective overburden pressure, p , including the effects of various sampling and
testing procedures, are important. As the number of pile-load tests is not enough
in soils having c/p ratios greater than three, Equation (4.15) should be applied with
some engineering judgment for high c/p values. The same engineering judgment
should be applied for deep-penetrating piles in soils with high undrained shear
strength, c, where the computed shaft frictions, f, using Equation 4.14 above, are
generally higher than previously specified in API RP2A. In the case of very long piles,
some reduction in pile capacity occurs, because the shaft friction may reduce to some
lesser residual value on continued displacement.
For piles end bearing in cohesive soils, the unit end bearing, q (in kPa), may be
computed by:
(4.16)
It is obvious that in open-driven piles the shaft friction, f, acts on both the inside and
outside of the pile. The total resistance is the sum of the external shaft friction, the
end bearing on the pile wall annulus and the total internal shaft friction or the end
bearing of the plug, whichever is less.
If the pipe pile is considered to be plugged, the bearing pressure may be assumed
to act over the whole cross-section of the pile. For unplugged piles, the bearing
pressure will be calculated on the pile wall annulus only. Whether a pile is considered
plugged or unplugged may be based on static calculations. For example, a pile could
be driven in an unplugged condition but act plugged under static loading.
In some cases, piles are driven in undersized drilled holes, piles are jetted in place
or (in some minor projects) the piles are drilled and grouted in place. In these
situations, the soil disturbance resulting from installation will affect the shaft friction
values. In general, f should not exceed values for driven piles; however, in some cases
for drilled and grouted piles in overconsolidated clay, f may exceed these values.
In determining f for drilled and grouted piles, the strength of the soil-grout interface,
including potential effects of drilling mud, should be considered. As discussed by
Kraft and Lyons (1974), a further investigation and check should be made of the
allowable bond stress between the pile steel and the grout.
The shaft friction values, f, in the cohesive layers should be as given in Equation
(4.14). End-bearing values for piles tipped in cohesive layers with adjacent weaker
layers may be as given in Equation (4.16), assuming that the pile achieves penetration
of two to three pile diameters or more into the layer in question and the tip is
approximately three pile diameters above the bottom of the layer, to avoid punch
through.
Figure 22.2. The cutting shoe used to close the annular steel casing.
The PCC pile installation sequence is shown in Fig. 22.3. The annular casing is first
erected on the PCC piling machine (Fig. 22.3(a)) and is initially pushed and then
vibro-driven into the ground (Fig. 22.3(b)). The rate of jacking is dependent on the
ground conditions. The length of the piles depends on the design requirement.
After the casing reaches the desired depth, concrete is poured into the annular
of the casing (Fig. 22.3(c)). The slump ratio of the concrete is controlled within
50–100 mm. After this, the steel casing is withdrawn from the ground by vibro means
(Fig. 22.3(d)). When the casing is being pulled up, the plates that seal the tip of the
casing (shown in Fig. 22.2) will be open.
Figure 22.3. PCC pile installation sequence: (a) positioning casing, (b) driving the
casing, (c) pouring concrete, (d) extracting casing, and (e) formation of the pile.
Method
Drilled and grouted (cemented) axial capacity is based on the API RP 2A-WSD static
(time independent) method for computing the ultimate bearing capacity of pipe
piles, casings, and conductors. The ultimate bearing capacity of for a given depth,
Qd, below the seafloor, is the sum of the bearing capacity due to the skin friction on
the conductor's embedded surface and the end bearing capacity on the tip as shown
in Eq. (8.11)
Axial capacity for drilled and grouted pipe installations
When applying the above equation to compute ultimate bearing capacity, the end
bearing capacity is assumed insignificant in comparison to end load result. A
modified formula for total bearing capacity of the installed structural pipe Eq. (8.12)
is used:
(8.12)
The unit skin friction capacity, f, calculated at any point along the pipe, Eq. (8.13):
Modified Unit skin friction capacity, f, at any given point along installed pipe length
For normally consolidated soil conditions, the empirical strength factor is given by
0.5 ≤ ≤ 1.0 in accordance with the API RP 2A-WSD methods.