Professional Documents
Culture Documents
Concrete Lining Science Direct
Concrete Lining Science Direct
Concrete Lining Science Direct
Related terms:
Grouting is carried out simultaneously with tunneling. There are inbuilt ports in the
tail skin of the TBM. These are used in primary grouting of the annulus (void between
excavation profile and outer face of the precast ring). Grouting is continued up to 3
bars (0.3 MPa) pressure. Excavation is not commenced until the previous lining is
completed. Secondary grouting is also done within 14 days of ring erection. Every
third ring is grouted to a pressure of 3 bars (0.3 MPa). Secondary grouting will fill
up any void left during the primary grout due to its shrinkage.
Although no measurements of the CMODs were taken during the test, the crack
propagation patterns were carefully recorded, as shown in Figure 4.16, in which
the load-displacement relations are also presented. As shown by the test results,
five cracks propagated in the test specimen before the collapse of the tunnel under
compression. The most active crack occurred in the right wall, which was followed
by two progressive cracks in the bottom plate from outside. The crack in the left
wall and the crack in the ceiling area from outside were small and less active. Upon
reaching the peak load, the tunnel specimen failed in a brittle fashion, as indicated in
the load-displacement relations. It was reported that during the experiment a certain
degree of eccentric loading occurred, generating a higher pressure-load on the right
wall. This is evident from the load versus displacement relations separately measured
on the left and right walls, as well as from the unsymmetric crack propagation
patterns recorded on the test specimen.
Figure 4.16. The results of a fracture test on a tunnel specimen: (a) load-displacement
relation and (b) crack propagation chart.
Based on these facts, the right portion of the bottom plate was believed to be under
bending during the experiment, and the corresponding vertical supports in effect
did not function, as indicated in Figure 4.16. In the following, the cracking processes
of the tunnel specimen will be studied by employing two FE models: a half-model
with three initial notches and a full-model with five initial notches. These analyses
will reveal the unique cracking behaviors frequently observed in actual tunnels. The
material properties of the test specimen are summarized in Table 4.2. Notice that
the bilinear tension-softening relation in Figure 4.9 is employed to solve the crack
equations.
Access
D.M. Farrar BSc, MSc, PhD, CEng, MICE, MCIWEM, in Sewers: Rehabilitation and
New Construction Repair and Renovation, 1997
Shaft conversion
Conversion of the shaft is the last stage of the construction sequence. Shafts may
be provided with a secondary concrete lining (generally 100-150 mm thickness) to
provide additional strength, or as a safeguard against water ingress, or for protection
of the bolted segments when storage or surcharging of sewage flows is anticipated.
Alternatively, the segment panel may be fitted with precast concrete ‘pellets’ to give
a smooth finish. Precast concrete landing slabs and roof (reducing) slabs lessen the
time of construction compared with in situ concrete slabs. Reinstatement of the
ground surface requires removal of the top temporary segmental rings, placing of
the reducing slab, construction of the smaller access shaft capped with the manhole
cover and frame, and breaking out part if not all the temporary concrete collar.
Rockbolting Design
Charlie Chunlin Li, in Rockbolting, 2017
Fig. 5.3.13. Sketches illustrating incompatible rock support systems: (A) in civil
tunneling and (B) in mining.
In a satisfactory rock support system, both internal and external devices should be
both strong and deformable. In other words, they should be compatible both in load
and deformation capacities in order to achieve the optimum reinforcement effect.
The behavior of the internal and external support devices in such a system should
be as sketched in Fig. 5.3.14.
Fig. 5.3.14. A sketch illustrating the concept of a compatible rock support system.
While the 300 series, the austenitic and the duplex stainless steels offered excellent
internal corrosion resistance, some failures occurred due to external stress corrosion
cracking (SCC) caused by the chloride-rich atmosphere offshore. The Ni content
plays an important role and the lowest resistance is experienced at about 8% Ni.
While 316 stainless steels are not recommended for temperatures above about 140°F
(60°C), duplex stainless steels have a much better resistance against SCC due to 50%
ferrite content of the structure. Exposed to offshore atmosphere, the 22 Cr duplex
shows resistance to 230°F (110°C). Above 230°F (110°C), 6 Mo or 25 Cr is generally
recommended.
However, chloride stress corrosion cracking temperature limits for the alloys are
always subject to debate. While some operators use 140°F (60°C) as specified above,
others use lower limits and some use higher limits. As an example, the EEMUA 194
publications states that austenitic steel grades such as 316/316L are susceptible to
chloride stress corrosion cracking where the material temperature exceeds about
50°C (122°F) and oxygen and chloride containing water are present. To a lesser extent
duplex stainless steels are also affected, though the threshold temperature increases
to about 120°C (248°F) for the 22% Cr and to about 150°C (302°F) for 25% Cr grades,
dependent upon fluid chloride content, temperature, pH and oxygen level. Oxygen
levels in produced hydrocarbons are usually too low to give rise to this problem.
Where oxygen may be introduced locally as a result of raw seawater ingress or
chemical injection, or where brines are very concentrated, consideration should be
given to the use of nickel alloys resistant to chloride stress cracking. The results
from over 700 stainless steel shell and tube heat exchangers in heating/cooling
water service including boiler water feeds showed that on the water side, chloride
stress corrosion cracking will not occur in austenitic stainless steels exchangers when
the system water temperature is less than 80°C (176°F), regardless of the chloride
content. At a chloride content of <7 mg/L, SCC will not occur regardless of water
temperature. Chitwood and Skogsberg (2004) have reported that 316 stainless steel
can be safely used in deaerated production environments containing upto 0.5 psi
(0.003 MPs) H2S and 50,0000 ppm Cl– at a minimum pH of 3.5 and a maximum
temperature of 175°F. At 0.5 psi H2S, the maximum temperature can be raised to
225°F if the maximum chloride content is reduced to 10,000 ppm. For non-sour
environment, 316 can be used to a maximum temperature of 350°F when the
chloride level is less than 150,000 ppm.
Where a process fluid contains wet H2S and CO2, Incoloy 825 or Inconel 625 are
selected. For components operating at low pressure (<20 bar), internal lining with
an organic/inorganic coatings can be used as an alternative to cladding with 825
or 625. Where H2Sis present, all materials must meet the requirements of NACE
MR0175 and ISO 15156-1/2/ DIS. Low-temperature carbon steel (LTCS) is used for
service down to −40°C and austenitic stainless steel, type 316L/304L, for design
temperatures below this, unless corrosive conditions dictate higher alloy grades.
Aggressive waters (as indicated by the Langelier index, Section 10.41) dissolve the
cement and increase pH, causing water quality problems particularly for small
diameter pipelines. However, the cement lining may be sealed with an approved thin
(150 to 250 μm) layer of epoxy paint. The seal coat provides a barrier to solution of
the cement mortar by aggressive low pH, low calcium waters but it is not particularly
robust. Where pH cannot be raised, for example by dosing with lime or, where
dosing cannot be guaranteed due to materials supply or operational uncertainties,
epoxy or other lining should be used.
Cement mortar linings and concrete linings are thicker than epoxy. They therefore
result in a slight reduction in pipe diameter (or require a slightly larger external
diameter to obtain the same finished internal diameter). Although cement mortar
or concrete linings may, after a while in service and with biofilm formation, attain a
hydraulic roughness similar to epoxy, they in general tend to have a greater initial
hydraulic roughness than epoxy. These factors may lead to epoxy being a more
cost effective solution if energy costs are taken into account, depending on the
circumstances. However, for typical civil engineering applications no distinction
is made between lining types when considering long-term roughness values. The
current trend away from concrete and mortar lining and towards epoxy lining for
new steel pipe may be linked to market forces, and also to the need for material in
contact with water used for the public supply (including raw water mains) to meet
the required approval process. The approval process is time consuming and entails
continued control of materials sources, including cement, as for concrete for water
retaining structures and linings for ductile iron pipes. Epoxy lining on its own would
be an expensive solution for ductile iron due to the surface roughness after grit
blasting; the pipes are cement mortar lined at all sizes and in the UK have a seal coat
on pipes only of DN 800 and smaller.
Bare metal pipe is spun at high speed on rollers and the mortar is poured as a slurry
into the interior. The lining builds up by centrifugal force and when the required
quantity has been poured the speed of rotation of the pipe is increased. The mortar
compacts further and surplus water runs off as the pipe is tilted very slightly. The
mortar mix comprises sand or fine crushed rock aggregate mixed with Portland or
sulphate-resisting cement in the ratio of 2.5:1 or 3:1 by weight. The lining is usually
so well compacted after spinning that the pipe can be immediately taken off the
spinning bed and is then cured in a damp warm atmosphere for 21 days. The mortar
lining thickness for steel is generally thicker than for ductile iron pipes of the same
diameter because of the flexibility of steel pipes compared with ductile iron pipes.
All fittings associated with mortar lined pipes are also mortar lined but this has to be
trowelled on. The discontinuity of the lining at joints in steel pipes should be filled
if the pipe is of large enough diameter to give inside access. Steel pipes which are
not large enough for this should either be jointed using flexible joints or be jointed
by externally welded collar joints. With the latter the lining is brought flush with the
pipe ends which are butted together; the heat input is not sufficient to damage
the lining. The collar is coated before assembly; any water between pipe and collar
is largely stagnant giving low risk of corrosion.
The surrounding rock mass consists mainly of rhyolite, and involves numerous
joints, although intact rock is very hard. Material properties of the intact rocks
obtained by uniaxial and triaxial compression tests are shown in Table 2, and the rock
mass properties obtained by in-situ plate loading tests are in Table 3. Initial stresses
were measured using the overcoring method. The results at the arch crown position
are shown in Table 4.
Vertical y0 -7.12
x0/ y0 = 1.37
In Figure 8 the excavation sequences shown, and Figure 9 gives the locations of
extensometer measurement.
The number of parameters to be identified is 3 for each rock class. There are two
different rock classes, so the total parameters are 6. The finite element mesh is
arranged in a way that the measurement points of extensometers to coincide with
those of finite element nodes as shown in Figure 10. The observation data together
with the calculated results by the damage identification analysis are given in Table 5.
Note that Δu31 implies the relative displacement between the points 3 and 1 shown
in Figure 10. Then, the identified damage tensors for each class are as follows:
Figure 10. FE mesh of the cavern (a part).
Measured Damage
RO3 Δu31 22.32 21.03
unit(mm)
Using the identified damage tensors, the subsequent excavation process of the
cavern is simulated. Here we report a comparison of the predicted response with
those measured when the excavation of the cavern is completed. In Table 6 the
predicted relative displacements of the extensometers are compared with measured
ones. Furthermore, the predictions by the proposed method and the conventional
finite element analysis by using the rock mass properties given by Table 3 are shown
in Figure 11 and compared in Tables 6 and 7. As seen from the tables, the predictions
are greater than those by those of the conventional analysis. Nevertheless, the results
of damage analysis are in good agreement with the measurements.
Relative displacement
R03(3-l) R04(3-4) R05(8-5)
Measured 2.42 0.92 2.19
Damage analysis 1.24 1.28 2.36
Conventional FEM 0.97 2.00 1.89
unit(cm)
Figure 11. Comparison of final displacement.
unit(cm)
Calculations indicated that the addition of a single layer of PBO fiber textile increased
the circumferential flexural strength of the lining by 14% and 4% at the top and side
portions of the tunnel, respectively. The addition of two PBO–TRM layers increased
the flexural strength by 100% in the longitudinal direction on the top portion of
the tunnel lining. The concrete surface was prepared using hydrojetting prior to the
installation of the PBO fibers and the application of a finishing coat of the matrix as
summarized in Figure 17.6.
Figure 17.6. (a) Surface preparation by hydrojetting; (b) application of the inorganic
matrix; and (c) application of the PBO textile reinforcement.Kind permission of
Ruredil SPA.
The cost of the project (in 2008) was around €800,000, which was less than any other
retrofit measure considered. The total area of PBO fibers used was 12,000 m2.
Figure 25.2 shows the effect of pressure-driven flow on a tunnel with a concrete
lining. These processes will be of greatest concern, if the groundwater has salt
in it. Most concrete tunnel segments are reinforced to prevent breakage during
installation, and the chloride will make this corrode and cause spalling. Adsorption
onto the hydrated cement matrix will significantly reduce the flow of chlorides, and
the water reaching the steel will probably have a very low concentration throughout
the design life.