EARTHWORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
2.3 Mechanical Excavation
Common Earth 13.34 MH/CM 6.67 MH/CM 5.34 MH/CM
Rock w/ Jackhammer 33.34 MH/CM 16.67 MH/CM 13.34 MH/CM
2.4 Backfilling
Common Manual 1.64 MH/CM 0.82 MH/CM 0.66 MH/CM
Gravel Fill Manual 10.00 MH/CM 5.00 MH/CM 4.00 MH/CM
2.5 Trenching and Backfilling of Underground
2.6 piping using excavation materials manual
from 0 - 2mtrs depth 2.50 MH/LM 1.25 MH/LM 1.00 MH/LM
2 - 3mtrs depth 3.34 MH/LM 1.67 MH/LM 1.34 MH/LM
3 - 4mtrs depth 5.00 MH/LM 2.50 MH/LM 2.00 MH/LM
4 - 5mtrs depth 6.66 MH/LM 3.33 MH/LM 2.66 MH/LM
2.7 Placing Binder - Gravel 0.21 MH/CM 0.11 MH/CM 0.08 MH/CM
2.8 Escombro Backfilling 0.42 MH/CM 0.21 MH/CM 0.17 MH/CM
2.9 Spreading, Tamping, and Grading 0.96 MH/SM 0.48 MH/SM 0.38 MH/SM
3 Mechanical Compaction, Plate Compaction 0.11 MH/CM 0.06 MH/CM 0.04 MH/CM
3.1 Manual Clearing and Grubbing
Clearing undergrowth and tress 12" 0.10 MH/SM 0.05 MH/SM 0.04 MH/SM
Clearing undergrowth and scrubs 0.06 MH/SM 0.03 MH/SM 0.02 MH/SM
3.2 Disposal of Soil 3.38 MH/CM 1.69 MH/CM 1.35 MH/CM
3.3 Hauling of Soil 2.00 MH/CM 1.00 MH/CM 0.80 MH/CM
3.4 Gravel Fill 4.14 MH/CM 2.07 MH/CM 1.66 MH/CM
3.5 Excavation - crane and Clampshell
with 8-men and 2-carpenters 2.14 MH/CM 1.07 MH/CM 0.86 MH/CM