Daily Activity Report: - KSA Team

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

- KSA Team

Daily Activity Report


Dated 8/19/2020 Report No. 24

Team Lead Haidar Ali Zaidi Location Work From Home

Team Members Haidar

Project Name Services, Sakaka, Marjan TCF, Sabic HQ

Weekly Planned Activities Daily Planned Activities

S.No Description Status Activities Planned Activities Performed


Services : Submission of techno-commercial offer Services : Submission of revised Services : Submission of revised commercial
1 commercial offer for Denys Arabia Telecom
to Sinopec for Telecom Systems Services case offer for Denys Arabia Telecom Services case

Services : Submission of revised techno- ✘ Services : Costing for Sinopec Telecom System
2 commercial offer to Ma'aden Aluminium Smelter Services : Costing for Sinopec Telecom system in progress. RFQs submitted to MSJ,
System, submission of RFQ to vendors
Plant as per comments received HikVision & Axis for quotations



Marjan : Discussion with Projects team with
3 Marjan : Submission of invoices for April & May Marjan : Finalization of local vendors for regards to industrial switches finalization. OTS
(advance) Industrial Switches
system vendor (Darius) to be reconsidered.

Marjan : Services PR creation & release for OEM Services : Follow up with Ma'aden team for
Services : Follow up with Ma'aden team for
4 services required at site during commissioning submitted offer submitted offer. Ma'aden shall submit queries
stage & revised scope of work shortly.

Sabic HQ : Finalization of Price breakdown (Supply, Services : RFQ floating for pressure switches &
5 Installation, Commissioning) & submission to Services : MAPA quotations collection & instruments for temporary solution for
RFQ floating to vendors shutdown valve. Review of Control valve wiring
Client diagram & designing of solution for the same.

✘ Sakaka : Providing necessary inputs to Logistics


Services : Finalization with MAPA with regards to Services : Sakaka Spares Finalization & RFQ & Procurement for delivery of 48V DC Meanwell
6 Ihsa Water Improvement Project floating to vendors power supplies (Enpower) & 24V AC
Transformers (Aravi) to Sakaka site

Services : Submission of AMC & Spares Supply Services : RFQ floating for pressure Services : Review of CCTV System offer received

7 switches & instruments for temporary from MSJ for Sinopec Service case. Quotations
offer to NOMAC for Sakaka Power Plant solution for shutdown valve awaited from HikVision & Axis
Issues & Bottlenecks Being Faced Work From Home Inputs

S.No Description On Hold With Particulars Yes/No

Sakaka : 48V DC power supplies (Meanwell) not yet dispatched from


Dubai for site. HS Code issues going on between Procurement/QC Procurement/QC & My IS and I know what deliverables we have
1 Yes
and Vendor. If further delayed, site activities going to be severly Vendor (Enpower) planned to complete today
affected for petty amount of 8K SAR

I was able to adhere to my normal work timings Yes


today

I have attended to & returned all phone calls


and have responded to all my internal and Yes
external official mails

There is no action pending with me regarding


my business responsibilities including with a Yes
customer

I have not left my home today Yes

REMARKS :
*Site surveys to Maaden & SWCC , with regards to Services cases, have been postponed by Client due to Covid19 Pandemic. No outsiders are being allowed
presently to visit industrial zones.