IRN - 18.07.2019 - Harshad Panchal - Revision-0 - Furnace Fabrica - JNK - PORVAIR - RIL PDF
IRN - 18.07.2019 - Harshad Panchal - Revision-0 - Furnace Fabrica - JNK - PORVAIR - RIL PDF
Project Name & Porvair Filter Cleaning Skids TUVIPL Branch Ahmedabad
Location Name:
TUVIPL Client Name: M/s. JNK India Pvt. Ltd., Mumbai End User Name: M/s. Reliance Industries Limited,
Jamnagar
DEC / PMC / EPC Not Applicable DEC / PMC / EPC Not Applicable
Name: (If Applicable) Asgmt. Number:
Vendor Name & M/s. Furnace Fabrica (India) Limited P.O. Number: PO No.: JNKI-014-PO-023
Location: (Client on Vendor) Date: 19.03.2018
Sub Vendor Name & Not Applicable P.O. Number: Not Applicable
Location: (If applicable) (Vendor on Sub Vendor)
Item Description:
Cumulative
PO P.O. Offered Accepted
Item Code & accepted
Item Quantity Quantity Quantity
Item Description Quantity
No.
Unit: Nos.
Fabrication and Supply of
Pre Filter
01 as per MR-Specification, TQ, ITP Provided 02 02 02 02
Mfg. Sr. No: F201803-1, F201803-2
Tag No.: MF-GCG200-F801, MF-GCG200-F803
Fabrication and Supply of
Final Filter
02 as per MR-Specification, TQ, ITP Provided 02 02 02 02
Mfg. Sr. No: F201803-3, F201803-4
Tag No.: MF-GCG200-F802, MF-GCG200-F804
Reference Documents:
Disclaimer: The inspection by TUV India Pvt. Ltd., review of Test Certificates / Reports and issue of Inspection Release Note / Certificate does not relieve the Client/ End User/ Supplier /
Manufacturer from their responsibility towards the Client / End User to supply / Use the genuine material / item(s) and document(s) in full compliance with applicable Order, Specification,
Technical, Quality, Quantity, Warranty, Guarantee requirements. Supplier / Manufacturer / stockist is wholly legally responsible for genuineness of the material / item (s) supplied and
document(s) submitted. TÜV India’s responsibility is only limited to correctness of inspection results including review of the documents, within its agreed scope against written requirements and
neither TUV India nor any of its group companies, associates or employees are in any way/ legally responsible for genuineness of the material / item(s) and document(s).
Copyright: This document is the property of TUV India and should not be reproduced, except in full without the consent of TUV India Pvt. Ltd.
TUV IPL (TÜV NORD GROUP): (REGD. & HEAD OFFICE), 801, Raheja Plaza - I, LBS Marg, Ghatkopar (West), Mumbai – 400086, Maharashtra, India.
Tel: + 91 22 66477000, Email: inspection@tuv-nord.com Website: www.tuv-nord.com/in
Form No. : F / INSP / IRN / 03 – R4; Revision Date: 28/09/2018 Page 1 of 3
TUV INDIA PRIVATE LIMITED
INSPECTION RELEASE NOTE / CERTIFICATE
Number: 8116967838-03 – IRN – 18.07.2019 – HARSHAD PANCHAL – Revision 0
Stages Witnessed:
Verified Spares for the Pre Filter Vessels and Final Filter Vessels. Found acceptable.
9) QAP Sr. No.: 5.6
Carried out Visual inspection of Root Run weld for the Shell to Nozzle Pipe joints. Found acceptable.
10) All measuring instruments/ equipment were verified for continued suitability for intended use, proper identification,
calibration status, traceability to national standards & found satisfactory.
Disclaimer: The inspection by TUV India Pvt. Ltd., review of Test Certificates / Reports and issue of Inspection Release Note / Certificate does not relieve the Client/ End User/ Supplier /
Manufacturer from their responsibility towards the Client / End User to supply / Use the genuine material / item(s) and document(s) in full compliance with applicable Order, Specification,
Technical, Quality, Quantity, Warranty, Guarantee requirements. Supplier / Manufacturer / stockist is wholly legally responsible for genuineness of the material / item (s) supplied and
document(s) submitted. TÜV India’s responsibility is only limited to correctness of inspection results including review of the documents, within its agreed scope against written requirements and
neither TUV India nor any of its group companies, associates or employees are in any way/ legally responsible for genuineness of the material / item(s) and document(s).
Copyright: This document is the property of TUV India and should not be reproduced, except in full without the consent of TUV India Pvt. Ltd.
TUV IPL (TÜV NORD GROUP): (REGD. & HEAD OFFICE), 801, Raheja Plaza - I, LBS Marg, Ghatkopar (West), Mumbai – 400086, Maharashtra, India.
Tel: + 91 22 66477000, Email: inspection@tuv-nord.com Website: www.tuv-nord.com/in
Form No. : F / INSP / IRN / 03 – R4; Revision Date: 28/09/2018 Page 2 of 3
TUV INDIA PRIVATE LIMITED
INSPECTION RELEASE NOTE / CERTIFICATE
Number: 8116967838-03 – IRN – 18.07.2019 – HARSHAD PANCHAL – Revision 0
Documents Reviewed:
Identification: Above Inspected Pre Filter Vessels and Final Filter Vessels Identified and Single Die Hard
Stamped as " " on Name plate and on Equipment Body Flange Near Manufacturer
Marking.
Conclusion: All items were inspected within the scope defined in approved QAP/ITP & found to meet the
requirements of Purchase Order & Specifications.
HARSHAD PANCHAL
and on behalf of Mr. Nilesh Panchal, Mr.
Kamal Dhandha, Mr. Kalpesh Raval, Mr.
GirirajShinh Gohil, Mr. Tejas Tank, Mr. Shiva
Narayan
Surveyor(S) to TUV India Private Limited
Distribution List: TUVIPL Client/End User TUVIPL Executing Branch/TUV Originating Branch Vendor/Sub Vendor
Revision – 0 (If Applicable) – Type Justification. This Document Supersedes IRN No. type Number Dated 00.00.0000
Disclaimer: The inspection by TUV India Pvt. Ltd., review of Test Certificates / Reports and issue of Inspection Release Note / Certificate does not relieve the Client/ End User/ Supplier /
Manufacturer from their responsibility towards the Client / End User to supply / Use the genuine material / item(s) and document(s) in full compliance with applicable Order, Specification,
Technical, Quality, Quantity, Warranty, Guarantee requirements. Supplier / Manufacturer / stockist is wholly legally responsible for genuineness of the material / item (s) supplied and
document(s) submitted. TÜV India’s responsibility is only limited to correctness of inspection results including review of the documents, within its agreed scope against written requirements and
neither TUV India nor any of its group companies, associates or employees are in any way/ legally responsible for genuineness of the material / item(s) and document(s).
Copyright: This document is the property of TUV India and should not be reproduced, except in full without the consent of TUV India Pvt. Ltd.
TUV IPL (TÜV NORD GROUP): (REGD. & HEAD OFFICE), 801, Raheja Plaza - I, LBS Marg, Ghatkopar (West), Mumbai – 400086, Maharashtra, India.
Tel: + 91 22 66477000, Email: inspection@tuv-nord.com Website: www.tuv-nord.com/in
Form No. : F / INSP / IRN / 03 – R4; Revision Date: 28/09/2018 Page 3 of 3