WORKING PROCEDURE
All rights reserved. Neither the whole nor any part of this document may be reproduced, stored in any retrieval
system or transmitted in any form or by any means without written consent of Chiyoda Malaysia Sdn. Bhd.
CHIYODA MALAYSIA SDN. BHD.
1.0 INTRODUCTION
This document describes the activities, responsibilities and interface of documents when performing
inspection and testing during construction stage of the project.
2.0 SCOPE
The scope of this procedure covers the inspection and testing of purchase equipment at shop, receiving
of material/equipment and in-process of works at site up to ready to issue notice for mechanical
completion to Client during construction stage of the project.
CM : Construction Manager
DE : Discipline Engineer
DS : Discipline Supervisor
MC : Material Controller
PM : Project Manager
PO : Purchase Order
4.0 REFERENCES
WP-7007 : Handover
All rights reserved. Neither the whole nor any part of this document may be reproduced, stored in any retrieval
system or transmitted in any form or by any means without written consent of Chiyoda Malaysia Sdn. Bhd.
CHIYODA MALAYSIA SDN. BHD.
5.0 PROCEDURE
i) QAI and/or PM shall plan, invite and hold PIM after the PO received and accepted by the
Fabricator.
ii) QAI shall decide meeting agenda based on Fabricator’s scope of work. Sample of meeting
agenda as shown in Attachment 1.
i) QAI and/or DE shall conduct inspection at Fabricator’s shop after receive AFI from them.
Sample of AFI form as shown in Attachment 2.
ii) QAI or DE shall ensure that the material and Material Certificate are correct and compare with
the drawings for final conformance.
iii) QAI or DE shall endorse Fabricator’s MRI Report and Mill Certificate.
c) In-progress inspection
i) Fabricator shall submit AFI to CMSB on each applicable activities stipulated in approved ITP.
Sample of ITP form as shown in Attachment 3.
ii) QAI and/or DE shall perform inspection, witness the test and review the test reports according
to approved ITP.
iii) QAI or DE shall review and endorse applicable Fabricator’s inspection and test reports
according to approved ITP.
QAI and/or DE shall perform final inspection when receive AFI form from Fabricator.
i) Final inspection shall be in accordance with ITP, drawings, specifications and other applicable
documents.
ii) QAI or DE shall issue IRN to Fabricator when everything is in order and the result was
accepted. Sample of IRN form as shown in Attachment 4.
iii) Without IRN, Fabricator may not allow to pack and deliver the equipment to designed site.
e) Verification by Client
i) Where specified in contract, Client shall be afforded a right to perform inspection activities of
purchase equipment at Fabricator.
ii) To that effect, the activities described in (a), (b), (c) and (d) above may also be carried out with
the presence of Client.
All rights reserved. Neither the whole nor any part of this document may be reproduced, stored in any retrieval
system or transmitted in any form or by any means without written consent of Chiyoda Malaysia Sdn. Bhd.
CHIYODA MALAYSIA SDN. BHD.
f) Nonconformities
a) MC shall issue AFI to QAIor DS after necessary checking, proper segregation and updating of
material list and status was done by him .
b) QAI and/or DS shall perform inspection against Material Certificate, PO Document, material list,
IRN or other relevant documents.
c) QAI or DS shall record inspection result on MRI and keep the report. Sample of MRI Report form
as shown in Attachment 5.
d) QAI or DS shall refer to Control of Nonconformities procedure, WP-8004 if the material /equipment
was found nonconformance.
b) QAI or DS shall notify Client for participation whenever required based on approved ITP.
c) QAI or DS shall perform inspection, witness the test, review and endorsed the inspection and test
report which is prepared by Subcontractor.
d) QAI or DS shall ensure that inspection and test report are kept by Subcontractor in good order, up to
date and easy retrievable.
e) QAI or DS shall report the field inspection and test status to CM periodically.
f) QAI or DS shall refer to Control of Nonconformities procedure, WP-8004 if the inspection item was
found rejectable or nonconformance.
6.0 ATTACHMENTS