You are on page 1of 6

No.

Main Activities

1 Depot Site Work

1.1 Sampling of bitumen coating for tank-3,4

1.2 Check the pipe sleeper repairing work before apply bitumenn coating

1.3 Check the rebar (first layer) for part-4,5 in Tank-7

1.4 Check the rebar and formwork for pipe support pedestal

1.5 Chceck the formwork for booster pumps wall (second stage)

1.6

1.7

1.8

1.9

1.10

1.11

0
Remarks
1.1 Sampling of bitumen coating for tank-3,4 1.2 Check the pipe sleeper repairing wor

1.3 Check the rebar (first layer) for part-4,5 in Tank-7


1.5 Chceck the formwork for booster pumps wall (second stage)
1.9
1.2 Check the pipe sleeper repairing work before apply bitumenn coating

1.4 Check the rebar and formwork for pipe support pedestal