Professional Documents
Culture Documents
11-Building Information Modeling Based Time PDF
11-Building Information Modeling Based Time PDF
and the project duration is automati- scheduling and cost data. At the end of in AEC industry. The considered exam-
cally determined from the generated the step, the project time and cost plan- ple is based on the Vico Office R4 soft-
network plan. BIM applications repre- ning process is completed and the 5D ware application. Here, the BIM based
sent location-based systems (LBS) for BIM model of the construction object is project time and cost planning was
project management which are oriented developed. Note also that the module 4D performed for a shelter building of
on planning, scheduling and controlling Simulation, a part of Vico Office R4 soft- the Medical Faculty that was recently
the project by the location. In this way, it ware, enables the execution and presen- built in Maribor, see red shaded area
is significant to achieve the work crew's tation of an animation of the scheduled in Figure 3.
productivity rate by moving from location construction. The shelter building is a part of
to location and to minimize the wastes Medical Faculty complex that also
on time, possibility of conflicts etc. Application Example includes the main building and the cor-
In the final step, the BIM model of In this section, an application example ridor to the University Clinical Centre
the construction object is completed by is presented to demonstrate the advan- of Maribor. It is a reinforced concrete
upgrading the 3D model with defined tages of BIM technique implementation structure composed from the foundation
concrete slab, the ground slab, the planning for the shelter construction Afterwards, the next task was to
retaining external walls, the internal was executed through several steps. import the 3D model of the shelter build-
walls, the internal columns and the roof In the first step, the 3D model for the ing into the Vico Office R4 system over
slab. Figure 4 shows the architectural shelter building was developed using the added menu in the main modeling
design of the shelter building with main ArchiCAD modeling software. Figure 5 software ArchiCAD, see Figure 6.
construction elements. shows ground floor plan for the shelter As soon as the import procedure
The BIM based project time and cost building and its 3D model. has been completed, the 3D model
Figure 8. Grouped building elements and information about their geometrical properties
was activated within the Vico Office module and the developed 3D model determined groups of shelter building
R4. The activation process employed appeared in the Vico Office R4 as it is elements and information about their
the selected element properties (e.g. shown on the right side of Figure 7. geometrical properties.
Element Type, Layer, ID, etc.) to create In order to define the construction In the module Cost Planner, the con-
Takeoff Items, see left side of Figure 7. project activities correctly, the shelter struction costs were estimated for each
Afterwards, the shelter building ele- building elements were rearranged into building element by adding the appro-
ments were listed in the Takeoff Manager several different groups. Figure 8 shows priate components or subcomponents
according to the work that should be geometrical properties of building geometrical properties. The source
done to complete the building with allo- elements were used as source quanti- quantities were then calculated in
cated resources (i.e. workers, materi- ties. The source quantities were deter- accordance with consumptions for the
als, machinery etc.). It was significant mined using the function with a link aim of correct cost estimation. The total
for this step that the appropriate to the Takeoff Item and its appropriate project cost was defined by adding the
Figure 12. Activities on building elements in module Task Manager and integrated components and
subcomponents for the building element Ground slab
units of measurements and unit costs components and subcomponents of project scheduling method of the Vico
into the model. For example, Figure 9 building element Ground slab. Office R4 application is based on the
shows estimated costs with integrated As described in section 2, the main flowline theory. Thus, it was important
Figure 14. Allocated workers for construction work Reinforcement on element Roof Slab
to include the building locations in the information about geometrical prop- project activities. Figure 12 shows
project scheduling process. In the 3D erties incorporated into the location activities on building elements in the
model of shelter building, the three Middle part. module Task Manager and integrated
different locations were defined in the Thereupon, the project activities components and subcomponents for
module LBS Management, i.e. Upper were determined in the module Task the building element Ground slab.
part, Middle part and Lower part, see Manager in accordance with the con- The Schedule Planner, a module in
Figure 10. struction works that should be executed. Vico Office R4, was activated to define
As an example, Figure 11 presents The calculated cost data from the Cost the precedence relationships between
the building element Columns with Planner was linked to the construction activities for the purpose of project
Figure 18. Target bill of quantities for shelter building construction project
scheduling. Figure 13 demonstrates After that, the resources and the construction work Reinforcement on
the construction work Paneling on the work crew sizes were allocated to the building element Roof Slab with
building element Columns with defined the construction project activities. allocated eight reinforce man.
Successor and Predecessor. For example, Figure 14 shows the After the work crew productivity
Figure 20. Construction process animation for shelter building in 4D Simulation module
rates have been defined, the durations colours used to label the construction The final step was to upgrade the
of activities and the project duration were works and assigned workers in output 3D model of shelter building, which
calculated. Figures 15–19 demonstrates graphical reports were defined as follows: was incorporated within the Vico
the developed project network plan, flow- • paneling (yellow) Office R4, with the scheduling data
line diagram, gantt chart, target bill of • reinforcement (red) from the Schedule Planner and the
quantities and resource graph, respec- • concreting (green) cost data from the Cost Planner as
tively. The considered activities of this • isolation (blue) well as to develop the 5D model. This
particular example project as well as • isolation protection (violet) task was executed automatically due
to dynamical link that was estab- influence on other related parts of the through classical 2D drawings, but the
lished between the Cost Planner, the model data, iv) all of the information 3D model of the construction object must
Schedule Planner and the Vico Office is dynamically linked to the building be created on the basis of geometrical
R4. In the 4D Simulation module, a part model, v) the geometrical quantities, the and material properties of building ele-
of Vico Office R4, an animation of the number of items, the required resources, ments. The setup of geometrical char-
construction process for shelter build- the execution times of project activities, acteristics of building elements result
ing was made. A part of the construction the costs and other data are available in basic quantities such as side length,
process animation for shelter building to be used in any time. The advantages object surface area, and object volume.
is presented in Figure 20. of construction time and cost planning Thus, the 3D model of the building can
Different manually selected colours using BIM may significantly improve be modified in a user-friendly manner
were defined within the 4D Simulation the project management, especially in during the design process because the
module and used for animation to cases of large and complex construc- basic quantities will be automatically
achieve better visualization of single tion projects in which the project goals updated. After the architectural design
building elements. Moreover, the actual are usually related to the quality of the is completed, the engineers can upgrade
dates were continuously reported building, short construction time and the 3D model with a wide variety of dif-
during animation in the left upper cost effective realization of the project. ferent information related to structural
corner of the screen. Figure 21 demon- analysis and design, HVAC, energy and
strates an actual phase of shelter build- Conclusion environmental issues, visualization,
ing construction and its finalization. The aim of this paper was to give an facility management, product and tech-
The presented application of Vico insight into the construction project nical information for manufacturers and
Office R4 software indicates possibili- time and cost planning process using distributors, etc.
ties for project participants to contrib- the BIM approach. For this purpose, the As soon as the 3D model of the con-
ute to a better management of con- steps of the time and cost planning of struction object is completed, the con-
struction process by implementing BIM the construction project employing BIM tractors may execute the cost estimates
technique in their practice. However, were introduced. An example based on and the project scheduling. When the
the project participants must be willing the application of Vico Office R4 software building model is upgraded with suitable
to make changes in their current work was presented in the paper to demon- input data, the contractors may obtain in
methods and to adopt new approaches. strate the advantages of the proposed each moment, for each building element,
The main advantages of incorporating approach. all relevant information for the execution
BIM approach into the construction In cases when initial design phases of works. Such model of the construction
project scheduling can be summarized are executed to be incorporated into the object can contain information about the
as follows: i) all of the information is col- BIM application, the architects have to type of building elements, the geometri-
lected in one place and kept up to date, develop the 3D building model and to cal quantities, the number of items, the
ii) the conception risk is minimized, iii) determine required works. However, resources needed for implementation,
all changes in construction automatically the design work should not be executed the execution times of project activities,
costs, etc. The biggest advantage of addict.com/2010/03/list-of-bim-software- Process Modelling 2012, ECPPM 2012,
providers.html [24.10.2013]. Reykjavik, Iceland, pp. 253-258.
BIM is that the information about the
construction object is stored in one place Cheng, J., Wang, H. (2010), Application and Monteiro, A., Poças Martins, J. (2013), A survey
and kept up to date. popularizing of BIM technology in project on modeling guidelines for quantity takeoff-
management, Proceedings of 2010 oriented BIM-based design, Automation in
Hence, the use of modern software
International Conference on E-Product Construction, 35, pp. 238–253.
that allows BIM in construction projects
E-Service and E-Entertainment, Henan, pp. Muhič, S. (2008), Proces brez lukenj, Dimensio,
represents a technological progress with
1–4. 12(13), pp. 33. (in Slovene).
many advantages for all participants.
Cheung, F.K.T., Rihan, J., Tah, J., Duce, D., Peterson, F., Hartmannb, T., Fruchtera, R.,
In this way, this paper intends to pro-
Kurul, E. (2012), Early stage multi-level Fischera, M. (2011), Teaching construction
vide new valuable information for con-
cost estimation for schematic BIM models, project management with BIM support:
struction management experts as well
Automation in Construction, 27, pp. 67–77. experience and lessons learned,
as it will serve as the basis for further
Eastman C., Teicholz P., Sacks R., Liston Automation in Construction, 20(2), pp.
research in the field of BIM based con-
K., BIM Handbook: A Guide to Building 115–125.
struction project management.
Information Modeling for Owners, Proplus d.o.o. (2013), photographic material,
Managers, Designers, Engineers, and 2013.
Acknowledgement Contractors, Second Edition, New Jersey:
Razpet, U., et al., Zaklonišče in podzemni
This research was supported by the Wiley Publishing, 2011.
kolektor med medicinsko fakulteto in UKC
company PROPLUS d.o.o. through Haapio, J. (2012), Future-Based Costing Method Maribor: Tloris zaklonišča, Project No.:
Cooperation Agreement No. 07/2012- for Skeletal Steel Structures based on 901-K/2008, Maribor: PLAN B d.o.o, 2009.
UK “Research and Development Project the Process Approach, Doctoral Thesis, (in Slovene).
for Construction of Medical Faculty in 2012, Tempere University of Technology,
Rundell, R. (2006), BIM and Cost Estimating,
Maribor – Shelter Building". Authors Publication 1027, Tempere, ISBN 978-952-
Cadalyst, available at: http://www.
wish to thank the director Mrs. Bojana 15-2795-1 (PDF)
cadalyst.com/cad/building-design/1-2-3-
Sovič, BSc, Mrs. Mojca Vesenjak, BSc Heinisuo, M., Laasonen, M., Haapio, J. revit-bim-and-cost-estimating-part-1-3350
and Mr. Samo Potrč, BSc from the com- (2010), BIM based manufactoring cost [24.10.2013].
pany PROPLUS d.o.o. for their valuable estimation od building products, eWork
Rundell, R., Stowe, H. K. (2007), 1-2-3 Revit:
support and cooperation. and eBusiness in Architecture, Enginering
BIM and Project Planning, Cadalyst, available
and Construction, ECPPM 2010, CRC Press/
at: http://aec.cadalyst.com/aec/article/
Balkema, London, pp. 53-59.
References articleDetail.jsp?id=408794 [24.10.2013].
Heinisuo, M., Laasonen, M., Ronni, H., Anttila,
Autodesk, Inc. (2007), BIM and Cost Estimating, Sabol, L. (2008), Challenges in Cost Estimating
T. (2010), Integration of joint design f
available at: http://www.consortech.com/ with Building Information Modeling,
steel structures using product model,
bim2/documents/BIM_cost_estimating_ available at: http://www.dcstrategies.
Proceedings of the Computing in Civil and
EN.pdf [24.10.2013]. net/files/2_sabol_cost_estimating.pdf
Building Engineering, 2010, Nottingham
Babič, N.Č., Podbreznik, P., Rebolj, D. (2010), [24.10.2013].
University Press, Nottingham, UK, Paper
Integrating resource production and Shah, J.S. (2011), The fifth dimension of BIM -
162, pp. 323.
construction using BIM, Automation in Cost estimating, 55th Annual Meeting of the
Jung, Y., Joo, M. (2011), Building information
Construction, 19(5), pp. 539–543. Association for the Advancement of Cost
modelling (BIM) framework for practical
Barlish, K., Sullivan, K. (2012), How to Engineering, AACE 2011, Anaheim, CA; United
implementation, Automation in
measure the benefits of BIM – A case study States, Volume 1, 2011, pp. 46-58.
Construction, 20(2), pp. 126–133.
approach, Automation in Construction, 24, Shen, Z., Issa, R. R. A. (2010), Quantitative
Kenley, R., Seppänen, O., Location-Based
pp. 149–159. evaluation of the BIM-assisted construction
Management for Construction: Planning,
Brisk S. (2007), Building Information Modeling detailed cost estimates, Journal of
Scheduling and Control, Abingdon: Spon
in Practice, White Paper, Autodesk, Information Technology in Construction
Press, 2010.
available at: http://revitmep.blogspot. (ITcon), 15, pp. 234–257.
Kim, H., Anderson, K., Lee, S., Hildreth, J.
com/2007/10/building-information- Tulke, J., Hanff, J. (2007), 4D Construction
(2013), Generating construction schedules
modeling-in.html [24.10.2013]. Sequence Planning – New Process and
through automatic data extraction using
Bryde, D., Broquetas, M., Marc Volm, J. (2013), Data Model, available at: http://www.
open BIM (building information modeling)
The project benefits of Building Information inpro-project.eu/media/4d_jantulke.pdf
technology, Automation in Construction,
Modelling (BIM), International Journal of [24.10.2013].
35, pp. 285–295.
Project Management, 31(7), pp. 971–980. Vico Office R4.0 Help File User Guide, Trimble
Mitchell, D. (2012), 5D: Creating cost certainty
CAD Addict (2013), List of BIM Software & Navigation, Ltd., 2012.
and better buildings, Proceedings of the