Project Crashing Problem
Project Crashing Problem
A -- 3
B A 4
C B 2
D A 5
E -- 6
F E 5
G C, D, F 4
24
25
1
5/5/2020
26
A -- 3 0 3 2 5 2
B A 4 3 7 5 9 2
C B 2 7 9 9 11 2
D A 5 3 8 6 11 3
E -- 6 0 6 0 6 0
F E 5 6 11 6 11 0
G C, D, F 4 11 15 11 15 0
27
2
5/5/2020
C, D, F 4 300 3 450
G
28
29
3
5/5/2020
30
31
4
5/5/2020
A -- 3 0 3 2 5 2 200 2
B A 4 3 7 5 9 2 80 3
C B 2 7 9 9 11 2 -- 2
D A 5 3 8 6 11 3 100 3
E -- 6 0 6 0 6 0 130 4
F E 5 6 11 6 11 0 70 3
G C, D, F 4 11 15 11 15 0 150 3
32
A -- 3 0 3 2 5 2 200 2
B A 4 3 7 5 9 2 80 3
C B 2 7 9 9 11 2 -- 2
D A 5 3 8 6 11 3 100 3
E -- 6 0 6 0 6 0 130 4
F E 5 36 11 6 11 0 70 3
G C, D, F 4 11 15 11 15 0 150 3
33
5
5/5/2020
Path E, F, G is critical
Minimum Non Zero Slack is 2
34
A -- 3 0 3 2 5 2 200 2
B A 4 3 7 5 9 2 80 3
C B 2 7 9 9 11 2 -- 2
D A 5 3 8 6 11 3 100 3
E -- 6 0 6 0 6 0 130 4
F E 5 36 11 6 11 0 70 3
G C, D, F 4 11 15 11 15 0 150 3
35
6
5/5/2020
Paths E, F, G and
© 2014 Pearson Education, Inc. A, B, C, G are critical
3 - 36
36
37
7
5/5/2020
38
39
8
5/5/2020
40
41