Professional Documents
Culture Documents
Road-Rate-Analysis-076-77 BUDANILKANTHA
Road-Rate-Analysis-076-77 BUDANILKANTHA
Road-Rate-Analysis-076-77 BUDANILKANTHA
2076/077 )
Item No 1
1.1)Description : Site clearance- Clearing and grubbing including the cutting of trees ( only if necessary ) having girth of less than 30 cm when measured at 1 m above the ground.
Unit : 1 sq m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Rate (Nrs) Amount (Nrs) Type Unit Qty. (Nrs) Remarks
s1-1.5(a) 1
1-1.5(b) Unskilled person-day 0.04 750.00 30.00
1-1.6
Total Labour Component ( A ) 30.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 30.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 4.50
Total Cost: Nrs. 34.50
Rate : Nrs. 34.50 Per Sq.m.
Item No 1.2
Description : Surface dressing work including filling pot hole and cutting topsoil with levelling work for service road etc
Unit : 1 sq m
Respective Dor Norms n. Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount
Specification Category Unit Qty. (Nrs) Type Unit Qty. Rate (Nrs) Amount (Nrs) Type Unit Qty. (Nrs) Remarks
s 1.7
Unskilled person-day 0.01 750.00 7.50
Total Labour Component ( A ) 7.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 7.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1.13
Total Cost: Nrs. 8.63
Rate : Nrs. 8.63 Per Sq.m.
Item n. 1.3 Description : Stripping of top soil work for minimum depth of 150 mm including storing or reapplication within a lead up to 100 m along the lead route
Unit : 1 cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Rate (Nrs) Amount (Nrs) Type Unit Qty. (Nrs) Remarks
s 4
Unskilled person-day 0.80 750.00 600.00
Total Labour Component ( A ) 600.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 600.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 90.00
Total Cost: Nrs. 690.00
Rate : Nrs. 690.00 Per Cu M
1
Item No 2
Description : Exacavation in roadways and drain including removal and satisfactory disposal of all materials of 50 m along the lead route. This includes
handling and stacking or hauling ( to sites of embankment construction) suitable cut materials and also the disposal of unsuitable cut materials in specified manner . This further
covers trimming and finishing of roadway .
(2. A) Ordinary Soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2 5.a
2-1.8 Unskilled person-day 0.50 750.00 375.00
2-1.9
T and P @ 3% of Labour Cost 11.25
Total Labour Component ( A ) 386.25 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 386.25
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 57.94
Total Cost: Nrs. 444.19
Rate : Nrs. 444.19 Per Cu M
Unit : 1 Cu m
(2.C) Ordinary Rock
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2
2-1.8 5.c Unskilled person-day 2.00 750.00 1500.00
2-1.9
T and P @ 3% of Labour Cost 45.00
Total Labour Component ( A ) 1545.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 1545.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 231.75
Total Cost: Nrs. 1776.75
Rate : Nrs. 1776.75 Per Cu M
2
(2.D) Marshy soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2 5.f
2-1.8 Unskilled person-day 1.00 750.00 750.00
2-1.9
T and P @ 3% of Labour Cost 22.50
Total Labour Component ( A ) 772.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 772.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 115.88
Total Cost: Nrs. 888.38
Rate : Nrs. 888.38 Per Cu M
Description : Exacavation in roadways and drain including removal and satisfactory disposal of all materials of 50 m along the lead route. This includes
handling and stacking or hauling ( to sites of embankment construction) suitable cut materials and also the disposal of unsuitable cut materials in specified manner . This further
covers trimming and finishing of roadway .
Unit : 1 Cu m
(2.E) Hard Rock ( chiselling,wedging,tempering )
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2 5.f
2-1.8 Unskilled person-day 17.00 750.00 12750.00
2-1.9
T and P @ 3% of Labour Cost 382.50
Total Labour Component ( A ) 13132.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 13132.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1969.88
Total Cost: Nrs. 15102.38
Rate : Nrs. 15102.38 Per Cu M
Unit : 1 Cu m
(2.F)Marshy Soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2
2-1.8 5.g Unskilled person-day 1.00 750.00 750.00
2-1.9
T and P @ 3% of Labour Cost 22.50
Total Labour Component ( A ) 772.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 772.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 115.88
Total Cost: Nrs. 888.38
Rate : Nrs. 888.38 Per Cu M
Item No 3
Description : Transporting material from roadway and drain excavation including all incidentals for every additional haulage of 50 m beyond the specified initial lead distance .
Unit : 1 Cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
sG-13.2 7
2-1.3.10 Unskilled person-day 0.50 750.00 375.00
2-1.9.6
and 2-5.7.2 T and P @ 3% of Labour Cost 11.25
Total Labour Component ( A ) 386.25 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 386.25
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 57.94
3
Total Cost: Nrs. 444.19
Rate : Nrs. 444.19 Per Cu M
4
Item No 4
Description : Exavation for structure including cutting of slopes , shoring ,shuttering, planking, ordinary sealing and disposal of materials up to a lead of 50 m along the lead route
Unit : 1 Cu m
(4. A) Ordinary Soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 2.4 9.a
Unskilled person-day 1.00 750.00 750.00
Unit : 1 Cu m
( 4.B ) Hard Soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 2.4 9.b
Unskilled person-day 2.00 750.00 1500.00
Unit : 1 Cu m
( 4.D ) Hard Rock ( Blasting Prohibited )
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 2.4 9.e
Unskilled person-day 30.00 750.00 22500.00
6
Item No 5.2
Description : Construction of roadway in embankment and miscellaneous backfilling areas with approved materials ( Hard soil cutting for filling material )obtained either from
excavation for road construction
borrowpits or other sources
excluding the excavation ( which shall be covered separately under S n No 5 ) and transporation ( which shall be covered under S N No 6 or 11 ) components
In this case, initial lead is 50 m
Unit : 1 Cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 5&10
Unskilled person-day 0.25 750.00 187.50 filling
Unskilled person-day 0.60 750.00 450.00 cutting
T and P @ 3% of Labour Cost 19.13
Total Labour Component ( A ) 656.63 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 656.63
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 98.49
Total Cost: Nrs. 755.12
Rate : Nrs. 755.12 Per Cu M
Item No 5.3
Compaction of filling material by 8-10 tonne roller by layer to layer .( for 100 cu m )
Respective Dor Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification norms(old) Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s Roller(8-10 t)
2.ka.35 Skilled person-day hrs 1.67 1201.37 2006.29
Unskilled person-day 0.00
Total Labour Component ( A ) 0.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 2006.29
Sub Total (A+B+C ) : Nrs. 2006.29
Rate per Cu m 20.06
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 3.01
Total Cost: Nrs. 23.07
Rate : Nrs. 23.07 per cu m
Item no 7
Description: Scarifying existing granular/bituminuous road surface for carrying out the required operation necessary to complete the work . This include handling, salvaging, stack
ing and disposing of scarified material upto a lead of 100 m along the lead route .
Unit : 1 sq m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 15
2-5.7.6 Unskilled person-day 0.20 750.00 150.00
2-5.4.3
T and P @ 3% of Labour Cost 4.50
Total Labour Component ( A ) 154.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 154.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 23.18
Total Cost: Nrs. 177.68
Rate : Nrs. 177.68 Per Cu M
Rate : Nrs. 30.90 Per Sq M
7
Item No 8.1
According to Norms of (DOR new norms no-10.04, clause-1004)
Description : Subgrade construction with treated materials formation of as per specification.
Unit : 1 cu m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Amount(Nrs Amount
Specification Category Unit Qty. Rate (Nrs) Type Unit Qty. Rate (Nrs) Amount (Nrs) Type Unit Qty. Rate (Nrs)
) (Nrs) Remarks
s
Suitable
Skilled person-day 0.01 1030.00 10.30 materail soil m3 1.100 240.00 264.00 Grader hrs 0.020 1558.67 31.17
1004 Unskilled person-day 0.10 750.00 75.00 Roller(8-10t) hrs 0.017 1201.37 20.42
Water lit 100.00 0.25 25.00
Total Labour Component ( A ) 85.30 Total Material Component ( B ) 289.00 Total Equipment Component ( C) ) 51.60
Sub Total (A+B+C ) : Nrs. 425.90
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 63.88
Total Cost: Nrs. 489.78
Rate : Nrs. 489.78 Per Cu M
Item No 8.2
According to Norms of ((DOR new norms no-10.04, clause-1004)
Description : Subgrade construction without treated materials formation of as per specification.
Unit : 1 cu m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount(Nrs Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification
Category Unit Qty. ) Type Unit Qty. Type Unit Qty. s) Remarks
s
Skilled person-day 0.01 1030.00 10.30 0.00 Grader hrs 0.020 1558.67 31.17
1004 Unskilled person-day 0.10 750.00 75.00 Roller(8-10t) hrs 0.017 1201.37 20.42
Water lit 100.00 0.25 25.00
Total Labour Component ( A ) 85.30 Total Material Component ( B ) 25.00 Total Equipment Component ( C) ) 51.60
Sub Total (A+B+C ) : Nrs. 161.90
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 24.28
Total Cost: Nrs. 186.18
Rate : Nrs. 186.18 Per Cu M
Item No 8.3
According to Norms of ((DOR new norms no-10.05, clause-1003)
Description : Preparation of Subgrade for rehabilitaion or other similar works ( filing or cutting depth 10cm to 20cm thick) Common soil
Unit : 1 sq m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount(Nrs Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nr
Specification
Category Unit Qty. ) Type Unit Qty. Type Unit Qty. s) Remarks
s
1004 Unskilled person-day 0.10 750.00 75.00 diesel lit 0.120 75.00 9.00 grader hrs 0.010 1558.67 15.59
skilled 0.01 910.00 9.10 Roller(8-10t) hrs 0.020 1201.37 24.03
Tools & plants 3 2.52
Total Labour Component ( A ) 86.62 Total Material Component ( B ) 9.00 Total Equipment Component ( C) ) 39.61
Sub Total (A+B+C ) : Nrs. 135.24
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 20.29
Total Cost: Nrs. 155.52
Rate : Nrs. 155.52 Per cu M
Rate : Nrs. 27.05 Per Sq M
8
Description : Preparation of Subgrade for rehabilitaion or other similar works ( filing or cutting depth 10cm to 20cm thick) gravel & boulder mixed soil
Unit : 1 sq m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount(Nrs Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nr
Specification
Category Unit Qty. ) Type Unit Qty. Type Unit Qty. s) Remarks
s
1004 Unskilled person-day 0.10 750.00 75.00 0.00
Skilled 0.01 1030.00 10.30
Tools & plants 3 2.56
Total Labour Component ( A ) 87.86 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 87.86
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 13.18
Total Cost: Nrs. 101.04
Rate : Nrs. 101.04 Per sq M
Item No 9
Description : Carrying out the construction operation of granular sub- base including full compensations for
making arrangements for traffic in accordance with clause G -12 of the Specification except for initial treatment to shoulders and construction of diversions
fumishing all materials to be incorporated in the work including all royalties, fees, rents wherever necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
and carrying out the work in part widths of roadway where directed.
A. With naturally found deposits of sand/gravel aggregates conforming to the specification for
(a) Class II Grading ( When CBR = 25 % )
Procuring sieved river gravel aggregates having sizes of 63-80 mm, 4.75-63 mm, 75 micron- m4.75 mm
Preparation of sub- grade that was finished earlier
9.1.1)Local gravel For laying of aggregates including compaction and the incidentals
Unit : 1 cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s3,1 Skilled person-day 0.005 1030.00 5.15 local gravel Cu M 1.10 2019.43 2221.37 8-10 t roller hrs 0.09 1201.37 108.12
Item No 9
Unit : 1 cu m
9.1.2)Gravel from Tikabhairav, Bhakunde Equv.Quarry site
Tikabhairav, Bhakunde
Equv.Quarry site
3,1 Skilled person-day 0.005 1030.00 5.15 gravel Cu M 1.10 2681.28 2949.41 8-10 t roller hrs 0.09 1201.37 108.12
9
(9.2.3) Class II Grading ( When CBR = 25 % ) without compaction .
Procuring sieved river gravel aggregates having sizes of 63-80 mm, 4.75-63 mm, 75 micron- m4.75 mm
Preparation of sub- grade that was finished earlier
a)Local gravel For laying of aggregates including compaction and the incidentals
Unit : 1 cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s3,1 Skilled person-day 0.005 1030.00 5.15 gravel Cu M 1.00 2019.43 2019.43
26.A Unskilled person-day 0.04 750.00 30.00 Transportation 0.00
Total Labour Component ( A ) 35.15 Total Material Component ( B ) 2019.43 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 2054.58
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 308.19
Total Cost: Nrs. 2362.76
Item No 10
Description : carrying out the construction operation of water bound macadam ( WBM ), sub- base/base course including full compensation for
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
fumishing all materials to be incorporated in the work including all royalties, fees, rents wherever necessary and all leads along the lead route 130.00
all labour and incindentals to complete the work to the specification and
and carrying out the work in part widths of roadway where directed Collection of rubble for aggregates
10.a) Grading No I ( Restricted to use for sub-base only ) Laying of sub-base For sub -base
Breaking stones for aggregates sizes -10-20, 20-40mm, 40-63mm,80-100mm Incidentals
Unit : 1 Cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 27 Skilled person-day 0.005 1030.00 5.15 Mix soling Cu M 1.27 2963.52 3763.67 8-10 t roller hrs 0.09 1201.37 108.12
dor 12.13
3,2 Unskilled person-day 0.020 750.00 15.00 Transportation 0.00
Total Labour Component ( A ) 20.15 Total Material Component ( B ) 3763.67 Total Equipment Component ( C) ) 108.12
Sub Total (A+B+C ) : Nrs. 3891.94
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 583.79
Total Cost: Nrs. 4475.74
Rate : Nrs. 4475.74 Per Cu M
10
Item No 11
Description : Preparation base for bituminuous macadam by carrying out the preparatory work of scarifying and relaying the aggregate base course including full compensation for
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
Preparation of base including filling of potholes except for levelling course
providing all materials to be incorporated in the work including all royalties fees, rents where necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
This item is same as S No 8 but with due deduction for the procurement of quantity received from the scarifying of receiving surface
Item No 11
Description Cleaning top surface by brush and broom before pitching
of Item
Unit : 10 sq m
11.a) On water Bound Macadam
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 15.16.1 Skilled person-day 1030.00 brush, kuchho L.s 45.00 45.00
Unskilled person-day 0.25 750.00 187.50
Total Labour Component ( A ) 187.50 Total Material Component ( B ) 45.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 232.50
Nrs. 23.25 Per sqm
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 3.49
Total Cost: Nrs. 26.74
Rate : Nrs. 26.74 Persqm
11
Item No 12
Description
of Item Semi-grouting works including compaction ( Ref norms of Dor Item no 15-21(a) in Open oven
( 5 cm thickness )
Unit 10 sq M
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 15.21 Skilled person-day Bitumen kg 35.00 78.10 2733.50
Unskilled person-day 1.20 750.00 900.00 kerosine lit 0.25 85.40 21.35 Roller machine hrs 0.07 1401.37 98.10
Fire wood ( in open
oven) kg 48.00 18.00 864.00 Sprayer hrs 0.07 1726.99 120.89
Aggregate 38-40mm
Cu M 0.60 3351.60 2010.96
Aggregate 12mm
Cu M 0.15 3316.32 497.45 dor
13.06/01
Total Labour Component ( A ) 900.00 Sub Total 6127.26 Total Equipment Component ( C) ) 218.99
Transportation 0.00
Total Material Component ( B ) 6127.26
Sub Total (A+B+C ) : Nrs. 7246.24
Nrs. 724.62 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1086.94
Total Cost: Nrs. 8333.18
Rate : Nrs. 833.32 per sq m
Description : Carrying out the required operation for the application of tack coat including full compensation for
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
providing all materials to be incorporated in the work including all royalties fees, rents where necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
Carrying out the work in part widths of roadway where directed
Unit : 10 10 sq m
a) When the application is upon existing bituminuous treated surface
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s4,2 30.a Skilled person-day Bitumen kg 5.00 78.10 390.50
Unskilled person-day 0.15 750.00 112.50 Fire wood kg 8.00 18.00 144.00 Sprayer hrs 0.04 1726.99 69.08
kerosine lit 0.50 85.40 42.70
Sub Total 577.20
Transportation
Total Labour Component ( A ) 112.50 Total Material Component ( B ) 577.20 Total Equipment Component ( C) ) 69.08
Sub Total (A+B+C ) : Nrs. 758.78
Rate : Nrs. 75.88 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 11.38
Total Cost: Nrs. 87.26
Rate : Nrs. 87.26 per sq m
12
Tack Coat
b) When the application is upon existing WBM
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit. Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s4,2 30.b Skilled person-day Bitumen kg 10.00 78.10 781.00
Unskilled person-day 0.20 750.00 150.00 Fire wood kg 16.00 18.00 288.00 Sprayer hrs 0.04 1726.99 69.08
kerosine lit 0.50 85.40 42.70
Sub Total 1111.70
Transportation 0.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 1111.70 Total Equipment Component ( C) ) 69.08
Sub Total (A+B+C ) : Nrs. 1330.78
Rate : Nrs. 133.08 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 19.96
Total Cost: Nrs. 153.04 per sq m
Item No 14
According to Norms of DoR 18 (A)
Description : Carrying out the required operation for the application of prime coat supplying of all necessary material.
Unit : 10 10 sq m
a) When the application is upon existing bituminuous treated surface
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s4,2 15.18.1 Skilled person-day Bitumen kg 4.90 78.10 382.69
Fire wood in open Sprayer
Unskilled person-day 0.20 750.00 150.00 oven kg 8.00 18.00 144.00 hrs 0.04 1726.99 69.08
Kerosine lit 0.50 85.40 42.70
Sub Total 569.39
Transportation 0.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 569.39 Total Equipment Component ( C) ) 69.08
Sub Total (A+B+C ) : Nrs. 788.47
Rate : Nrs. 78.85 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 11.83
Total Cost: Nrs. 90.67
Rate : Nrs. 90.67 per sq m
13
Item No 14
According to Norms of DoR 18 (B)
Description :
Unit : 10
Description : Carrying out the required operation for the application of prime coat supplying of all necessary material.
b)When the application is upon base course.
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s4,2 15.18.2 Skilled person-day Bitumen kg 9.75 78.10 761.48
Fire wood in open Sprayer
Unskilled person-day 0.20 750.00 150.00 oven kg 16.00 18.00 288.00 hrs 0.04 1726.99 69.08
Kerosine lit 0.50 85.40 42.70
Sub total 1092.17
Transportation 0.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 1092.17 Total Equipment Component ( C) ) 69.08
Sub Total (A+B+C ) : Nrs. 1311.25
Rate : Nrs. 131.13 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 19.67
Total Cost: Nrs. 150.79
Rate : Nrs. 150.79 per sq m
Item No 15
Description : 13.09DOR Providing,mixing,laying and compaction of bituminous premix carpet Spec no:1307/1308
Unit : 1 cu m
Respective
Clause of
Specification Dor norms
Remarks
s (old) Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s)
4,2 15.24.kha Skilled person-day 0.45 1030.00 463.50 Bitumen lit 77.00 78.10 6013.70 Smooth wheel roller hrs 0.50 1201.37 600.69
Unskilled person-day 4.50 750.00 3375.00 Kerosene lit 7.70 85.40 657.57 Sprayer hrs 0.50 1726.99 863.50
Aggregate cu m 1.20 3245.76 3894.91
Per m3
Total Labour Component ( A ) 3838.50 Total Material Component ( B ) 10566.18 Total Equipment Component ( C) 1464.18
Sub Total (A+B+C ) : Nrs. 15868.86
Rate : Nrs. 15868.86 per cu m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2380.33
Total Cost: Nrs. 18249.19
Rate : Nrs. 18249.19 per cu m
Item No 16
Description : Sand seal including compaction .
Unit : 10 10 sq m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 15.23 Skilled person-day 0.10 1030.00 103.00 Bitumen kg 6.60 78.10 515.46 8-10 t roller hrs 0.04 1401.37 56.05
Unskilled person-day 0.14 750.00 105.00 Fire wood kg 16.00 18.00 288.00 Sprayer hrs 0.04 1726.99 69.08
( in open oven )
coarse sand cu m 0.07 3210.48 224.73
Sub Total 1028.19
Transportation 0.00
Total Labour Component ( A ) 208.00 Total Material Component ( B ) 1028.19 Total Equipment Component ( C) ) 125.13
Sub Total (A+B+C ) : Nrs. 1361.33
Rate : Nrs. 136.13 per sq m
14
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 20.42
Total Cost: Nrs. 156.55
Rate : Nrs. 156.55 per sq m
15
Item No
Description : 13.1DOR Bituminous Concrete/Asphalt concrete.Providing and laying Bituminous concrete/Asphalt concrete 5cm using crushed aggregate of specified grading,premixed with bituminous binder and filler as per drawing
and technical specification Spec 1307/1308
Unit : Cum
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 15.23 Skilled person-day 0.03 1030.00 30.90 Bitumen lit 117.00 78.10 9137.70 Asphalt Mixing Plant hr 0.04 1000.00 44.00
Unskilled person-day 0.13 750.00 97.50 Cement Tonne 0.02 16714.00 367.71 wheel Loader hr 0.66 2053.98 1355.63
Foreman person-day 0.01 750.00 7.50 Diesel Lit 10.45 85.40 892.41 Asphalt Paver hr 0.22 1201.37 264.30
Aggregate Cum 1.20 3316.32 3979.58 Steel tyred Roller hr 0.55 1201.37 660.75
Pneumatic Roller hr 0.55 1401.37 770.75
Tipper, Trucks hr 0.32 1612.39 515.96
Sub Total 14377.40
Total Labour Component ( A ) 135.90 Total Material Component ( B ) 14377.40 Total Equipment Component ( C) ) 3611.40
Sub Total (A+B+C ) : Nrs. 18124.71
Rate : Nrs. 18124.71 Per cum
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2718.71
Total Cost: Nrs. 20843.41
Rate : Nrs. 20843.41 Per cum
Item No 19
Description : Brick masonry with all necessary operations including full compensations for all labour , materials , scaffolding, and other incidentals required to complete the work
as per the specifications and as shown on the drawings. It includes full compensation for using specially moulded bricks on the face of walls with better provision
of weep holes jointed with cement sand mortar.
Unit : 1cu m
19.a) in 1:4 mix ratio
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s Brick
7 37.A.b Skilled person-day 1.50 1030.00 1545.00 (224*108*57mm) No 530.00 14.91 7902.30
Unskilled person-day 4.99 750.00 3742.50 Cement bag 2.00 835.70 1671.40
Sand cu m 0.35 3210.48 1123.67
Sub Total 10697.37
Transportation 0.00
Total Labour Component ( A ) 5287.50 Total Material Component ( B ) 10697.37 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 15984.87
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2397.73
Total Cost: Nrs. 18382.60
Rate : Nrs. 18382.60 per cu m
17
Item no 20
Description 12.5 mm th. Plastering with cement sand mortar on brick walls or concrete surfaces with all necessary operations including full compensation for all labours, materials
scaffolding and other incidentals required to complete the work as per the specifications
Unit 100 sq m
20.a) in 1:4mix ratio
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amoun Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. t(Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s7-9.4 37.B.c Skilled person-day 15.00 1030.00 15450.00 Cement Bag 7.26 835.70 6067.18
,7-12 Unskilled person-day 13.59 750.00 10192.50 Sand cu m 1.46 3210.48 4687.30
Bamboo nos 2.00 210.00 420.00
Rope ls 100.00 15 mutha
7-13.2 Sub Total 11274.48
Transportation 0.00
Total Labour Component ( A ) 25642.50 Total Material Component ( B ) 11274.48 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 36916.98
Rate : Nrs. 369.17 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 55.38
Total Cost: Nrs. 424.55
Rate : Nrs. 424.55 per sq m
Description 12.5 mm th. Plastering with cement sand mortar on brick walls or concrete surfaces with all necessary operations including full compensation for all labours, materials
scaffolding and other incidentals required to complete the work as per the specifications
Unit 100 sq m
20.b) in 1:6mix ratio
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s7-9.4 37.B.d Skilled person-day 15.00 1030.00 15450.00 Cement Bag 5.76 835.70 4813.63
,7-12 Unskilled person-day 13.70 750.00 10275.00 Sand cu m 1.58 3210.48 5072.56
Bamboo nos 2.00 210.00 420.00
Rope 100.00 100.00
7-13.2 Sub Total 10406.19
Transportation 0.00
Total Labour Component ( A ) 25725.00 Total Material Component ( B ) 10406.19 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 36131.19
Rate : Nrs. 361.31 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 54.20
Total Cost: Nrs. 415.51
Rate : Nrs. 415.51 per sq m
18
Item no 22
Description Pointing work with cement sand mortar on brick wall with all required operations including full compensation for all labours, materials and other incidentals necessary
to complete the work as per the specifications
Unit 100 sq m
22.a) in 1:3mix ratio
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s7-9.3 37.C.c Skilled person-day 8.00 1030.00 8240.00 Cement Bag 1.92 835.70 1604.54
7-12 Unskilled person-day 8.88 750.00 6660.00 Sand cu m 0.29 3210.48 931.04
Bamboo nos 2.00 210.00 420.00
Rope Ls 100.00 100.00
and 7-13.3 Sub Total 3055.58
Transportation 0.00
Total Labour Component ( A ) 14900.00 Total Material Component ( B ) 3055.58 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 17955.58
Rate : Nrs. 179.56 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 26.93
Total Cost: Nrs. 206.49
Rate : Nrs. 206.49 per sq m
Item no 23
Description Dry brick laying
Unit 10 sq m
23.1.a) Flat
Respective Dor norms n. Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 11.15.ka Skilled person-day 0.50 1030.00 515.00 Brick Nos 420.00 14.91 6262.20
Unskilled person-day 1.00 750.00 750.00 Sand cu m 0.71 3210.48 2279.44
Sub Total 8541.64
Transportation 0.00
Total Labour Component ( A ) 1265.00 Total Material Component ( B ) 8541.64 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 9806.64
Rate : Nrs. 980.66 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 147.10
Total Cost: Nrs. 1127.76
Rate : Nrs. 1127.76 per sq m
Item no 23
Description Dry brick laying
Unit 10 sq m
23.1.b) edge
Respective Dor norms n. Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 11.15. kha Skilled person-day 1.00 1030.00 1030.00 Brick Nos 750.00 14.91 11182.50
Unskilled person-day 3.25 750.00 2437.50 Sand cu m 0.71 3210.48 2279.44
Sub Total 13461.94
Transportation 0.00
Total Labour Component ( A ) 3467.50 Total Material Component ( B ) 13461.94 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 16929.44
Rate : Nrs. 1692.94 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 253.94
Total Cost: Nrs. 1946.89
Rate : Nrs. 1946.89 per sq m
Item no 23.2
Description Dry Stone laying work
Unit 1 cu.m.
Respective Dor norms n. Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification 19
(old) Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 11.16 Skilled person-day 1.00 1030.00 1030.00 stone m3 1.10 2363.76 2600.14
Unskilled person-day 3.50 750.00 2625.00 Sand cu m 0.71 3210.48 2279.44
S.n. Item
1 Skilled
2 Unskilled
10 Agg3-6
11 Agg 6-12
12 Sand
21 fire wood
22 Stone dust
23 Water
Budhanilkantha Municipality Rate 2075/076
24 GI wire, Medium
24.1 Medium class
8 mm dia
10 mm dia
12 mm dia
23.2 Heavy Duty
G I wire 8mm dia ( H )
G I wire 10mm dia (H)
G I wire 12mm dia ( H)
24 gravel girt
25 Brick(Chimney bhatta)
26 Stone quarry
27 Water proof ply 9mm
28 Boulder Stone from river 100mm
29 Road equipment
7.3
7.5
7.6
10.1
5.2
5.3
5.4
4.1
11.ka
13.2.a+b
13.d
23
14.1.10
14.1.Ta
7.chha
32
20.1b.2b.3b
20.1b
20.2b
20.3b
20c
20c
20c
8.gha
1.3
3.1.1
3.1.2
53.pp
53.nn
53.z
aaa
gg
ft3
95
84
92
91
m3
57.24 2019.43
76 2681.28
76 2681.28
84 2963.52
94
1441.666667
3316.32
3351.6
2963.52
3245.76
3210.48
0
0
50862
41.04 1447.89
67 2363.76
105
0
3704.4
0
Rate
1030.00
750.00
2019.43
2681.28
2681.28
2963.52
78.10
3316.32
3351.60
2963.52
3245.76
3210.48
835.70
16714.00
84.00
84000.00
92.00
97.35
50862.00
18.00
1447.89
0.26
100.00
100.00
100.00
105.00
105.00
105.00
0.00
14.91
2363.76
956.75
3704.40
1201.37
1401.37
1612.39
2653.98
85.40
1280.15
2053.98
Unit
Md
Md
Cu M
Cu M
Cu M
kg
Cu M
Cu M
Cu M
Cu M
Cu M
bag
MT
kg
Mt
kg
kg
Cu M
kg
Cu M
kg
kg
kg
kg
kg
kg
Cu M
No
Cu M
sqm
Cu M
hr.
hr.
hr.
hr.
lt
hr.
hr.
Grader (with fuel )
Air compressor
Bitumen heater/Boiler
Sprayer bitumen
Batch mix HMP
Paver finisher
Generater
Smooth wheeled roller
pneumatic roller
30 water
31 Nails
32 R.C.C. Hume Pipe and Collar
PIPES
a) NP-2
150 mm dia.
200 mm dia.
225 mm dia.
250 mm dia.
300 mm dia.
350 mm dia.
375 mm dia.
400 mm dia.
450 mm dia.
500 mm dia.
600 mm dia.
700 mm dia.
750 mm dia.
800 mm dia.
900 mm dia.
1000 mm dia.
1200 mm dia.
1500 mm dia.
b) NP-3
150 mm dia.
200 mm dia.
225 mm dia.
250 mm dia.
300 mm dia.
350 mm dia.
375 mm dia.
400 mm dia.
450 mm dia.
500 mm dia.
600 mm dia.
700 mm dia.
750 mm dia.
800 mm dia.
900 mm dia.
1000 mm dia.
1200 mm dia.
1500 mm dia
1500 mm dia.
bb
53.ee
53.uu
32
32
26
26.a
26.b
0
0
1558.67
335.40
1897.79
1726.99
1000.00
1201.37
150.00
1201.37
1000.00
0.26
112.00
570.00
740.00
883.00
925.00
1260.00
1325.00
1520.00
1750.00
1852.00
2080.00
2740.00
3575.00
3870.00
4320.00
5835.00
6805.00
8301.00
17450.00
1310.00
1745.00
0.00
2185.00
3140.00
3520.00
3760.00
4010.00
4500.00
5020.00
6200.00
7485.00
8600.00
9384.00
12172.00
13525.00
16100.00
25300.00
25300.00
hr.
hr.
hr.
hr.
hr.
hr.
hr.
hr.
ltr
kg
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.C.C. Hume Pipe
Collar 26…a
a) NP-2
150 mm dia. 145 Nos
200 mm dia. 193 Nos
225 mm dia. 0 Nos
250 mm dia.
239 Nos
300 mm dia.
324 Nos
350 mm dia.
357 Nos
375 mm dia.
392 Nos
400 mm dia. 451 Nos
450 mm dia. 476 Nos
b) NP-3 26…b
150 mm dia. 327 Nos
2264.46
308.21 4325.00
93.97 1441.67 2681.85
Fuel
cosumtion Fuel
charge cosumtion deisel
Hire Rate Amount charge ltr rate/lits 75.57
1656.40
1407.94
1449.00
2530000
400gm Kg
17 42.5
SUMMARY OF ROAD RATE ANALYSIS
Government Of Nepal
Budhanilkantha Municipality Office
Golfutar , Kathmandu
Page 26
SUMMARY OF ROAD RATE ANALYSIS
Page 27
SUMMARY OF ROAD RATE ANALYSIS
6.8 Sand seal laying works Sq M 124.25 142.89 131.16 150.84 136.13 156.55
7.0 Other costruction work
7.1 Dry brick/ stone soling.
Page 28
SUMMARY OF ROAD RATE ANALYSIS
Page 29
SUMMARY OF ROAD RATE ANALYSIS
Page 30
SUMMARY OF ROAD RATE ANALYSIS
Page 31
SUMMARY OF ROAD RATE ANALYSIS
Page 32
SUMMARY OF ROAD RATE ANALYSIS
Page 33
SUMMARY OF ROAD RATE ANALYSIS
Page 34
SUMMARY OF ROAD RATE ANALYSIS
Page 35
RATE ANALYSIS OF CONSTRUCTION WORK ITEMS
Scarifying existing granular/bituminous road surface for carrying out the required operations necessary to complete the work. This
includes handling, salvaging, stacking and disposing of scarified material up to a lead of 100 m along the lead route.
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.20 700.00 140.00
Skilled md 0.00 0.00
Sub Total Labor 140.00
2.00 Tools / Equipment
Axes, Khukuri, Saws, Crowbars, Wheel
Barrows or Bullock Carts 4.20
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 2.80 700.00 1960.00
Skilled md 0.00 0.00
Sub Total Labor 1960.00
2.00 Tools / Equipment
,@ 3% of labour 58.80
Sub Total Tool/Equipment 58.80
Sub Total (Labor+Tool/Equipment) -I 2018.80
Contractor Over head 15% of I 302.82
Total rate per m3 2321.62
II EARTHWORK
b. Hard soil
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.60 700.00 420.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 420.00
2.00 Tools / Equipment
Picks, Shovels, Kodalo,
Doko/Baskets/Wheel Barrows,
Crowbars 12.60
Sub Total Tool/Equipment 12.60
Sub Total (Labor+Tool/Equipment) -I 432.60
Contractor Over head 15% of I 64.89
Total rate per m3 497.49
c. Ordinary rock
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 2.00 700.00 1400.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 1400.00
2.00 Tools / Equipment
Picks, Shovels, Kodalo,
Doko/Baskets/Wheel Barrows, 42.00
Crowbars
Sub Total Tool/Equipment 42.00
Sub Total (Labor+Tool/Equipment) -I 1442.00
Contractor Over head 15% of I 216.30
Total rate per m3 1658.30
d. Medium rock
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 4.00 700.00 2800.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 2800.00
2.00 Tools / Equipment
Picks, Shovels, Kodalo,
Doko/Baskets/Wheel Barrows, 84.00
Crowbars
Sub Total Tool/Equipment 84.00
Sub Total (Labor+Tool/Equipment) -I 2884.00
Contractor Over head 15% of I 432.60
Total rate per m3 3316.60
Excavation in Roadway , drain and foundation of structure including removal and satisfactory disposal of all materials
up to a lead of 50m along the lead route using excavator or breaker and finishing manually wherever and to what extent
necessary
Manual Equipment
Manual Equipment
Excavation Excavation
S.No Description Excavation Excavation
(5%) (95%)
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.25 700.00 175.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 175.00
2.00 Tools / Equipment
Picks, Shovels, Doko/Baskets,
5.25
Wheel barrows
Sub Total Tool/Equipment 5.25
Sub Total (Labor+Tool/Equipment) -I 180.25
Contractor Over head 15% of I 27.04
Total rate per m3 207.29
VIII CONCRETING
Norms Serial No: 40
Clause No.: 10
drawing and as directed by engineer. It also includes all devices for keeping reinforcement in approved position and jointing as
per approved method with due allowance for wastage overlaps spacers brand annealed steel bar for binding.
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 7.00 700.00 4900.00
Skilled md 7.00 960.00 6720.00
Sub Total Labor 11620.00
2.00 Material
Reinforcement bars MT 1.05 84000.00 88200.00
Binding wires MT 0.01 92.00 0.92
Sub Total Material 88200.92
3.00 Tools and equipment 2994.63
Sub Total Tool/Equipment 2994.63
Sub Total (Labor+Material+Tool/Equipment) -I 102815.55
Contractor Over head 15% of I 15422.33
Total rate per MT 118237.88
IX DRAINAGE WORKS:
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 1.00 700.00 700.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 700.00
2.00 Material
Granular material m3 1.10 2019.43 2221.37
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 1.25 700.00 875.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 875.00
2.00 Material
Stone m3 1.10 2363.76 2600.14
Gravel/Spalls m3 0.25 2019.43 504.86
Sub Total Material 3104.99
Total of RBG Works 3979.99
3.00 Tools and equipment 119.40
Sub Total Tool/Equipment 119.40
Sub Total (Labor+Material+Tool/Equipment) -I 4099.39
Contractor Over head 15% of I 614.91
Total rate per m3 4714.30
1.00 Labour
Unskilled md 0.10 750.00 75.00
Skilled md 0.01 1030.00 10.30
Sub Total Labor 85.30
2.00 Material
Diesel Lit 0.12 85.40 10.42
Sub Total Material 10.42
3.00 Tools and equipment
Grader Hr 0.01 1,600.00 16.00
Roller Hr 0.02 500.00 8.50
Sub Total Tool/Equipment 24.50
Sub Total (Labor+Material+Tool/Equipment) -I 120.22
Contractor Over head 15% of I 18.03
Total rate per m3 138.25
Total rate per sqm 27.65
1.00 Labour
Unskilled md 0.04 750.00 30.00
Skilled md 0.0050 1,030.00 5.15
Sub Total Labor 35.15
2.00 Material
Diesel Lit 0.79 71.06 56.28
Sub base aggregate m3 1.28 1,870.00 2393.60
Sub Total Material 2449.88
3.00 Tools and equipment
Grader Hr 0.0220 85.00 1.87
Vibrating roller Hr 0.0220 800.00 17.60
Water browser Hr 0.0380 550.00 20.90
Loader Hr 0.0110 1,200.00 13.20
Providing, laying, spreading, watering, leveling and compaction of crusher run materials for base course lead up to
10m.
1.00 Labour
Unskilled md 0.0200 750.00 15.00
Skilled md 0.0050 1,030.00 5.15
Sub Total Labor 20.15
2.00 Material
Diesel Lit 0.99 71.06 70.35
Base aggregate m3 1.20 2,963.52 3556.22
Sub Total Material 3626.57
3.00 Tools and equipment
Grader Hr 0.03 85.00 2.81
Vibrating roller Hr 0.03 1,600.00 52.80
Water browser Hr 0.03 1,200.00 39.60
Loader Hr 0.0110 550.00 6.05
1.00 Labour
Unskilled md 0.0460 750.00 34.50
Skilled md 0.0030 1,030.00 3.09
Sub Total Labor 37.59
2.00 Material
Bitumen Lit 1.05 68.40 71.82
Kerosene Lit 0.10 85.40 8.54
Diesel Lit 0.275 85.40 23.48
Sub Total Material 103.84
3.00 Tools and equipment
Boiler Hr 0.0025 180.00 0.45
Sprayer Hr 0.0025 260.00 0.65
Air compressor Hr 0.0030 260.00 0.78
Sub Total Tool/Equipment 1.88
Sub Total (Labor+Material+Tool/Equipment) -I 143.31
Contractor Over head 15% of I 21.50
Total rate per litre 164.81
1.00 Labour
Unskilled md 0.0460 750.00 34.50
Skilled md 0.0030 1,030.00 3.09
Sub Total Labor 37.59
2.00 Material
Bitumen Lit 1.05 68.40 71.82
Kerosene Lit 0.10 75.00 7.50
Diesel Lit 0.275 85.40 23.48
Sub Total Material 102.80
3.00 Tools and equipment
Boiler Hr 0.0025 180.00 0.45
Sprayer Hr 0.0025 260.00 0.65
Air compressor Hr 0.0030 250.00 0.75
Sub Total Tool/Equipment 1.85
Sub Total (Labor+Material+Tool/Equipment) -I 142.24
Contractor Over head 15% of I 21.34
Total rate per litre 163.58
1.00 Labour
Unskilled md 4.50 750.00 3375.00
Skilled md 0.45 1,030.00 463.50
Sub Total Labor 3838.50
2.00 Material
Bitumen Lit 77.00 68.40 5266.80
Kerosene Lit 7.70 85.40 657.57
Aggregates cum 1.20 3,245.76 3894.91
Sub Total Material 9819.28
3.00 Tools and equipment
Sprayer Hr 0.50 260.00 130.00
Roller Hr 0.50 500.00 250.00
1.00 Labour
Unskilled md 0.14 635.00 88.90
Skilled md 0.10 865.00 86.50
Sub Total Labor 175.40
2.00 Material
Bitumen Lit 6.60 68.40 451.44
Kerosene Lit 0.10 85.40 8.54
Diesel Lit 0.81 85.40 69.17
Fine Aggregates cum 0.12 3,210.48 385.26
Sub Total Material 914.41
3.00 Tools and equipment
Boiler Hr 0.04 250.00 10.00
Roller Hr 0.04 1,600.00 64.00
Sprayer Hr 0.01 1,200.00 12.00
1.00 Labour
Unskilled md 0.13 750.00 97.50
Skilled md 0.03 1,030.00 30.90
foreman md 0.01 750.00 7.50
Sub Total Labor 135.90
2.00 Material
Bitumen Lit 117.00 68.40 8002.80
cement t 0.022 1,600.00 35.20
Diesel Lit 10.45 85.40 892.41
Aggregates cum 1.20 2,998.80 3598.56
Sub Total Material 12528.97
3.00 Tools and equipment
Asphalt mixing plant Hr 0.044 2,500.00 110.00
Wheel Loader Hr 0.66 550.00 363.00
asphalt paver Hr 0.22 85.00 18.70
Tipper Trucks Hr 0.32 75.00 24.00
Steel tyred Roller Hr 0.55 1,600.00 880.00
Pneumatic Rollers Hr 0.55 500.00 275.00
Sub Total Tool/Equipment 1670.70
Sub Total (Labor+Material+Tool/Equipment) -I 14335.57
Contractor Over head 15% of I 2150.34
Total rate per m3 16485.91
TEMS
FY: 2075/76
Remarks
Unit : 1 no.
Remarks
Unit :1 no.
Remarks
Unit : 1 no.
Remarks
Unit : 1 no.
Remarks
Unit : 1 no.
Remarks
ary to complete the work. This
g the lead route.
Unit : 1 sqm
Remarks
33.17
astes to 10m
Unit : 1 cum
Remarks
Unit : 1 cum
Remarks
Unit : 1 cum
Remarks
Unit : 1 cum
Remarks
Unit : 1 cum
Remarks
Unit : 1 cum
Remarks
Average Rate
NRs
109.22
113.37
171.41
695.69
1502.30
Unit : cum
Remarks
ecially dressed stones on
Unit : cum
Remarks
Unit : cum
Remarks
Unit : cum
Remarks
Unit : 1 Box
Remarks
Unit : 1 Box
Remarks
Unit : 1 Box
Remarks
Unit : 1 Box
Remarks
Unit : 1 Box
Remarks
Unit : m3
Remarks
Remarks
s. The rate includes the works
Unit : cum
Remarks
Unit : cum
Remarks
Unit : cum
Remarks
Remarks
Unit : m3
Remarks
Remarks
red to complete the works
ent sand mortar.
Unit : 7.5 RM
Remarks
10 to 20 cm) in:
Unit : m3
Remarks
Remarks
ace using wire, brushes,
Unit : lit
Remarks
Unit : lit
Remarks
Unit : m3
Remarks
Unit : m3
Remarks
135.22
Unit : m3
Remarks