Road-Rate-Analysis-076-77 BUDANILKANTHA

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 69

Analysis of Rates for Road Works ( F.Y.

2076/077 )
Item No 1
1.1)Description : Site clearance- Clearing and grubbing including the cutting of trees ( only if necessary ) having girth of less than 30 cm when measured at 1 m above the ground.
Unit : 1 sq m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Rate (Nrs) Amount (Nrs) Type Unit Qty. (Nrs) Remarks
s1-1.5(a) 1
1-1.5(b) Unskilled person-day 0.04 750.00 30.00
1-1.6

Total Labour Component ( A ) 30.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 30.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 4.50
Total Cost: Nrs. 34.50
Rate : Nrs. 34.50 Per Sq.m.
Item No 1.2
Description : Surface dressing work including filling pot hole and cutting topsoil with levelling work for service road etc
Unit : 1 sq m
Respective Dor Norms n. Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount
Specification Category Unit Qty. (Nrs) Type Unit Qty. Rate (Nrs) Amount (Nrs) Type Unit Qty. (Nrs) Remarks
s 1.7
Unskilled person-day 0.01 750.00 7.50

Total Labour Component ( A ) 7.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 7.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1.13
Total Cost: Nrs. 8.63
Rate : Nrs. 8.63 Per Sq.m.

Item n. 1.3 Description : Stripping of top soil work for minimum depth of 150 mm including storing or reapplication within a lead up to 100 m along the lead route
Unit : 1 cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Rate (Nrs) Amount (Nrs) Type Unit Qty. (Nrs) Remarks
s 4
Unskilled person-day 0.80 750.00 600.00

Total Labour Component ( A ) 600.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 600.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 90.00
Total Cost: Nrs. 690.00
Rate : Nrs. 690.00 Per Cu M

1
Item No 2
Description : Exacavation in roadways and drain including removal and satisfactory disposal of all materials of 50 m along the lead route. This includes
handling and stacking or hauling ( to sites of embankment construction) suitable cut materials and also the disposal of unsuitable cut materials in specified manner . This further
covers trimming and finishing of roadway .
(2. A) Ordinary Soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2 5.a
2-1.8 Unskilled person-day 0.50 750.00 375.00
2-1.9
T and P @ 3% of Labour Cost 11.25
Total Labour Component ( A ) 386.25 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 386.25
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 57.94
Total Cost: Nrs. 444.19
Rate : Nrs. 444.19 Per Cu M

(2. B) Hard Soil


Unit : 1 Cu m
(B) Hard Soil
Respective Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
sRespective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount(Nrs Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. ) Type Unit Qty. Type Unit Qty. s) Remarks
s2-1.2.2 5.b
2-1.8 Unskilled person-day 0.60 750.00 450.00
2-1.9
T and P @ 3% of Labour Cost 13.50
Total Labour Component ( A ) 463.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 463.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 69.53
Total Cost: Nrs. 533.03
Rate : Nrs. 533.03 Per Cu M

Unit : 1 Cu m
(2.C) Ordinary Rock
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2
2-1.8 5.c Unskilled person-day 2.00 750.00 1500.00
2-1.9
T and P @ 3% of Labour Cost 45.00
Total Labour Component ( A ) 1545.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 1545.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 231.75
Total Cost: Nrs. 1776.75
Rate : Nrs. 1776.75 Per Cu M

2
(2.D) Marshy soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2 5.f
2-1.8 Unskilled person-day 1.00 750.00 750.00
2-1.9
T and P @ 3% of Labour Cost 22.50
Total Labour Component ( A ) 772.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 772.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 115.88
Total Cost: Nrs. 888.38
Rate : Nrs. 888.38 Per Cu M

Description : Exacavation in roadways and drain including removal and satisfactory disposal of all materials of 50 m along the lead route. This includes
handling and stacking or hauling ( to sites of embankment construction) suitable cut materials and also the disposal of unsuitable cut materials in specified manner . This further
covers trimming and finishing of roadway .
Unit : 1 Cu m
(2.E) Hard Rock ( chiselling,wedging,tempering )
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2 5.f
2-1.8 Unskilled person-day 17.00 750.00 12750.00
2-1.9
T and P @ 3% of Labour Cost 382.50
Total Labour Component ( A ) 13132.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 13132.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1969.88
Total Cost: Nrs. 15102.38
Rate : Nrs. 15102.38 Per Cu M

Unit : 1 Cu m
(2.F)Marshy Soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s2-1.2.2
2-1.8 5.g Unskilled person-day 1.00 750.00 750.00
2-1.9
T and P @ 3% of Labour Cost 22.50
Total Labour Component ( A ) 772.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 772.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 115.88
Total Cost: Nrs. 888.38
Rate : Nrs. 888.38 Per Cu M
Item No 3
Description : Transporting material from roadway and drain excavation including all incidentals for every additional haulage of 50 m beyond the specified initial lead distance .
Unit : 1 Cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
sG-13.2 7
2-1.3.10 Unskilled person-day 0.50 750.00 375.00
2-1.9.6
and 2-5.7.2 T and P @ 3% of Labour Cost 11.25
Total Labour Component ( A ) 386.25 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 386.25
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 57.94

3
Total Cost: Nrs. 444.19
Rate : Nrs. 444.19 Per Cu M

4
Item No 4
Description : Exavation for structure including cutting of slopes , shoring ,shuttering, planking, ordinary sealing and disposal of materials up to a lead of 50 m along the lead route
Unit : 1 Cu m
(4. A) Ordinary Soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 2.4 9.a
Unskilled person-day 1.00 750.00 750.00

T and P @ 3% of Labour Cost 22.50


Total Labour Component ( A ) 772.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 772.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 115.88
Total Cost: Nrs. 888.38
Rate : Nrs. 888.38 Per Cu M

Unit : 1 Cu m
( 4.B ) Hard Soil
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 2.4 9.b
Unskilled person-day 2.00 750.00 1500.00

T and P @ 3% of Labour Cost 45.00


Total Labour Component ( A ) 1545.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 1545.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 231.75
Total Cost: Nrs. 1776.75
Rate : Nrs. 1776.75 Per Cu M

( 4.C ) Ordinary Rock


Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 2.4 9.c
Unskilled person-day 4.00 750.00 3000.00

T and P @ 3% of Labour Cost 90.00


Total Labour Component ( A ) 3090.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 3090.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 463.50
Total Cost: Nrs. 3553.50
Rate : Nrs. 3553.50 Per Cu M

Unit : 1 Cu m
( 4.D ) Hard Rock ( Blasting Prohibited )
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 2.4 9.e
Unskilled person-day 30.00 750.00 22500.00

T and P @ 3% of Labour Cost 675.00


Total Labour Component ( A ) 23175.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 23175.00
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 3476.25
Total Cost: Nrs. 26651.25
Rate : Nrs. 26651.25 Per Cu M
5
4.E) Special provision for preparation of rock foundation
Unit : 1 Cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 2.4 9.f
Unskilled person-day 0.50 750.00 375.00

T and P @ 3% of Labour Cost 11.25


Total Labour Component ( A ) 386.25 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 386.25
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 57.94
Total Cost: Nrs. 444.19
Rate : Nrs. 444.19 Per Cu. M
( 4.F ) Marshy Soil
Unit : 1 Cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 2.4 9.g
Unskilled person-day 3.00 750.00 2250.00

T and P @ 3% of Labour Cost 67.50


Total Labour Component ( A ) 2317.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 2317.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 347.63
Total Cost: Nrs. 2665.13
Rate : Nrs. 2665.13 Per Cu M
Item No 5.1
Description : Construction of roadway in embankment and miscellaneous backfilling areas with approved materials obtained either from
excavation for road construction or borrowpits or other sources
excluding the excavation ( which shall be covered separately under S n No 5 ) and transporation ( which shall be covered under S N No 6 or 11 ) components
In this case, initial lead is 50 m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 10
Unskilled person-day 0.25 750.00 187.50
2.5
T and P @ 3% of Labour Cost 5.63
Total Labour Component ( A ) 193.13 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 193.13
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 28.97
Total Cost: Nrs. 222.09
Rate : Nrs. 222.09 Per Cu M

6
Item No 5.2
Description : Construction of roadway in embankment and miscellaneous backfilling areas with approved materials ( Hard soil cutting for filling material )obtained either from
excavation for road construction
borrowpits or other sources
excluding the excavation ( which shall be covered separately under S n No 5 ) and transporation ( which shall be covered under S N No 6 or 11 ) components
In this case, initial lead is 50 m
Unit : 1 Cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 5&10
Unskilled person-day 0.25 750.00 187.50 filling
Unskilled person-day 0.60 750.00 450.00 cutting
T and P @ 3% of Labour Cost 19.13
Total Labour Component ( A ) 656.63 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 656.63
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 98.49
Total Cost: Nrs. 755.12
Rate : Nrs. 755.12 Per Cu M
Item No 5.3
Compaction of filling material by 8-10 tonne roller by layer to layer .( for 100 cu m )
Respective Dor Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification norms(old) Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s Roller(8-10 t)
2.ka.35 Skilled person-day hrs 1.67 1201.37 2006.29
Unskilled person-day 0.00
Total Labour Component ( A ) 0.00 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 2006.29
Sub Total (A+B+C ) : Nrs. 2006.29
Rate per Cu m 20.06
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 3.01
Total Cost: Nrs. 23.07
Rate : Nrs. 23.07 per cu m

Item no 7
Description: Scarifying existing granular/bituminuous road surface for carrying out the required operation necessary to complete the work . This include handling, salvaging, stack
ing and disposing of scarified material upto a lead of 100 m along the lead route .
Unit : 1 sq m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. (Nrs) Remarks
s 15
2-5.7.6 Unskilled person-day 0.20 750.00 150.00
2-5.4.3
T and P @ 3% of Labour Cost 4.50
Total Labour Component ( A ) 154.50 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 154.50
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 23.18
Total Cost: Nrs. 177.68
Rate : Nrs. 177.68 Per Cu M
Rate : Nrs. 30.90 Per Sq M

7
Item No 8.1
According to Norms of (DOR new norms no-10.04, clause-1004)
Description : Subgrade construction with treated materials formation of as per specification.
Unit : 1 cu m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Amount(Nrs Amount
Specification Category Unit Qty. Rate (Nrs) Type Unit Qty. Rate (Nrs) Amount (Nrs) Type Unit Qty. Rate (Nrs)
) (Nrs) Remarks
s
Suitable
Skilled person-day 0.01 1030.00 10.30 materail soil m3 1.100 240.00 264.00 Grader hrs 0.020 1558.67 31.17
1004 Unskilled person-day 0.10 750.00 75.00 Roller(8-10t) hrs 0.017 1201.37 20.42
Water lit 100.00 0.25 25.00
Total Labour Component ( A ) 85.30 Total Material Component ( B ) 289.00 Total Equipment Component ( C) ) 51.60
Sub Total (A+B+C ) : Nrs. 425.90
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 63.88
Total Cost: Nrs. 489.78
Rate : Nrs. 489.78 Per Cu M

Item No 8.2
According to Norms of ((DOR new norms no-10.04, clause-1004)
Description : Subgrade construction without treated materials formation of as per specification.
Unit : 1 cu m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount(Nrs Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification
Category Unit Qty. ) Type Unit Qty. Type Unit Qty. s) Remarks
s
Skilled person-day 0.01 1030.00 10.30 0.00 Grader hrs 0.020 1558.67 31.17
1004 Unskilled person-day 0.10 750.00 75.00 Roller(8-10t) hrs 0.017 1201.37 20.42
Water lit 100.00 0.25 25.00
Total Labour Component ( A ) 85.30 Total Material Component ( B ) 25.00 Total Equipment Component ( C) ) 51.60
Sub Total (A+B+C ) : Nrs. 161.90
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 24.28
Total Cost: Nrs. 186.18
Rate : Nrs. 186.18 Per Cu M
Item No 8.3
According to Norms of ((DOR new norms no-10.05, clause-1003)
Description : Preparation of Subgrade for rehabilitaion or other similar works ( filing or cutting depth 10cm to 20cm thick) Common soil
Unit : 1 sq m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount(Nrs Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nr
Specification
Category Unit Qty. ) Type Unit Qty. Type Unit Qty. s) Remarks
s
1004 Unskilled person-day 0.10 750.00 75.00 diesel lit 0.120 75.00 9.00 grader hrs 0.010 1558.67 15.59
skilled 0.01 910.00 9.10 Roller(8-10t) hrs 0.020 1201.37 24.03
Tools & plants 3 2.52
Total Labour Component ( A ) 86.62 Total Material Component ( B ) 9.00 Total Equipment Component ( C) ) 39.61
Sub Total (A+B+C ) : Nrs. 135.24
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 20.29
Total Cost: Nrs. 155.52
Rate : Nrs. 155.52 Per cu M
Rate : Nrs. 27.05 Per Sq M

8
Description : Preparation of Subgrade for rehabilitaion or other similar works ( filing or cutting depth 10cm to 20cm thick) gravel & boulder mixed soil
Unit : 1 sq m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount(Nrs Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nr
Specification
Category Unit Qty. ) Type Unit Qty. Type Unit Qty. s) Remarks
s
1004 Unskilled person-day 0.10 750.00 75.00 0.00
Skilled 0.01 1030.00 10.30
Tools & plants 3 2.56
Total Labour Component ( A ) 87.86 Total Material Component ( B ) 0.00 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 87.86
Contractor 's Miscellaneous Overhead Expenses ( 15 % ): Nrs. 13.18
Total Cost: Nrs. 101.04
Rate : Nrs. 101.04 Per sq M

Item No 9
Description : Carrying out the construction operation of granular sub- base including full compensations for
making arrangements for traffic in accordance with clause G -12 of the Specification except for initial treatment to shoulders and construction of diversions
fumishing all materials to be incorporated in the work including all royalties, fees, rents wherever necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
and carrying out the work in part widths of roadway where directed.
A. With naturally found deposits of sand/gravel aggregates conforming to the specification for
(a) Class II Grading ( When CBR = 25 % )
Procuring sieved river gravel aggregates having sizes of 63-80 mm, 4.75-63 mm, 75 micron- m4.75 mm
Preparation of sub- grade that was finished earlier
9.1.1)Local gravel For laying of aggregates including compaction and the incidentals
Unit : 1 cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s3,1 Skilled person-day 0.005 1030.00 5.15 local gravel Cu M 1.10 2019.43 2221.37 8-10 t roller hrs 0.09 1201.37 108.12

26.A Unskilled person-day 0.04 750.00 30.00 Transportation DOR 12.02


Total Labour Component ( A ) 35.15 Total Material Component ( B ) 2221.37 Total Equipment Component ( C) ) 108.12
Sub Total (A+B+C ) : Nrs. 2364.64
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 354.70
Total Cost: Nrs. 2719.34
Rate : Nrs. 2719.34 Per Cu M

Item No 9
Unit : 1 cu m
9.1.2)Gravel from Tikabhairav, Bhakunde Equv.Quarry site

Respective Dolidar Labour (A) Material(B) Equipment ( c )


Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s

Tikabhairav, Bhakunde
Equv.Quarry site
3,1 Skilled person-day 0.005 1030.00 5.15 gravel Cu M 1.10 2681.28 2949.41 8-10 t roller hrs 0.09 1201.37 108.12

26.A Unskilled person-day 0.04 750.00 30.00 Transportation


Total Labour Component ( A ) 35.15 Total Material Component ( B ) 2949.41 Total Equipment Component ( C) ) 108.12
Sub Total (A+B+C ) : Nrs. 3092.68
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 463.90
Total Cost: Nrs. 3556.58
Rate : Nrs. 3556.58 Per Cu M

9
(9.2.3) Class II Grading ( When CBR = 25 % ) without compaction .
Procuring sieved river gravel aggregates having sizes of 63-80 mm, 4.75-63 mm, 75 micron- m4.75 mm
Preparation of sub- grade that was finished earlier
a)Local gravel For laying of aggregates including compaction and the incidentals
Unit : 1 cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s3,1 Skilled person-day 0.005 1030.00 5.15 gravel Cu M 1.00 2019.43 2019.43
26.A Unskilled person-day 0.04 750.00 30.00 Transportation 0.00
Total Labour Component ( A ) 35.15 Total Material Component ( B ) 2019.43 Total Equipment Component ( C) ) 0.00
Sub Total (A+B+C ) : Nrs. 2054.58
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 308.19
Total Cost: Nrs. 2362.76

Item No 10
Description : carrying out the construction operation of water bound macadam ( WBM ), sub- base/base course including full compensation for
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
fumishing all materials to be incorporated in the work including all royalties, fees, rents wherever necessary and all leads along the lead route 130.00
all labour and incindentals to complete the work to the specification and
and carrying out the work in part widths of roadway where directed Collection of rubble for aggregates
10.a) Grading No I ( Restricted to use for sub-base only ) Laying of sub-base For sub -base
Breaking stones for aggregates sizes -10-20, 20-40mm, 40-63mm,80-100mm Incidentals
Unit : 1 Cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 27 Skilled person-day 0.005 1030.00 5.15 Mix soling Cu M 1.27 2963.52 3763.67 8-10 t roller hrs 0.09 1201.37 108.12
dor 12.13
3,2 Unskilled person-day 0.020 750.00 15.00 Transportation 0.00
Total Labour Component ( A ) 20.15 Total Material Component ( B ) 3763.67 Total Equipment Component ( C) ) 108.12
Sub Total (A+B+C ) : Nrs. 3891.94
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 583.79
Total Cost: Nrs. 4475.74
Rate : Nrs. 4475.74 Per Cu M

Item No 10.b Grading No I I For base


Breaking stones for aggregates sizes -10-20, 20-40mm, 40-50mm,50-63mm,63-80mm
For screening - 150microm down,150 microm, 4.75 mm ,4.75mm-10mm, 10-12.5mm
Collection of rubble for aggregates
Laying of base
Incidentals
Unit : 1 Cu m
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 27 Skilled person-day 0.005 1030.00 5.15 Mix soling Cu M 1.3 2963.52 3852.58 8-10 t roller hrs 0.09 1201.37 108.12

3,2 Unskilled person-day 0.020 750.00 15.00 Transportation 0.00


Total Labour Component ( A ) 20.15 Total Material Component ( B ) 3852.58 Total Equipment Component ( C) ) 108.12
Sub Total (A+B+C ) : Nrs. 3980.85
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 597.13
Total Cost: Nrs. 4577.98
Rate : Nrs. 4577.98 Per Cu M

10
Item No 11
Description : Preparation base for bituminuous macadam by carrying out the preparatory work of scarifying and relaying the aggregate base course including full compensation for
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
Preparation of base including filling of potholes except for levelling course
providing all materials to be incorporated in the work including all royalties fees, rents where necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
This item is same as S No 8 but with due deduction for the procurement of quantity received from the scarifying of receiving surface
Item No 11
Description Cleaning top surface by brush and broom before pitching
of Item
Unit : 10 sq m
11.a) On water Bound Macadam
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 15.16.1 Skilled person-day 1030.00 brush, kuchho L.s 45.00 45.00
Unskilled person-day 0.25 750.00 187.50
Total Labour Component ( A ) 187.50 Total Material Component ( B ) 45.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 232.50
Nrs. 23.25 Per sqm
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 3.49
Total Cost: Nrs. 26.74
Rate : Nrs. 26.74 Persqm

11.b) On Other Surface


Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 15.16.2 Skilled person-day brush, kuchho L.s 45.00 45.00
Unskilled person-day 0.20 750.00 150.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 45.00 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 195.00
Nrs. 19.50 Per sqm
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2.93
Total Cost: Nrs. 22.43
Rate : Nrs. 22.43 Per10sqm

11
Item No 12
Description
of Item Semi-grouting works including compaction ( Ref norms of Dor Item no 15-21(a) in Open oven
( 5 cm thickness )
Unit 10 sq M
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 15.21 Skilled person-day Bitumen kg 35.00 78.10 2733.50
Unskilled person-day 1.20 750.00 900.00 kerosine lit 0.25 85.40 21.35 Roller machine hrs 0.07 1401.37 98.10
Fire wood ( in open
oven) kg 48.00 18.00 864.00 Sprayer hrs 0.07 1726.99 120.89
Aggregate 38-40mm
Cu M 0.60 3351.60 2010.96
Aggregate 12mm
Cu M 0.15 3316.32 497.45 dor
13.06/01
Total Labour Component ( A ) 900.00 Sub Total 6127.26 Total Equipment Component ( C) ) 218.99
Transportation 0.00
Total Material Component ( B ) 6127.26
Sub Total (A+B+C ) : Nrs. 7246.24
Nrs. 724.62 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 1086.94
Total Cost: Nrs. 8333.18
Rate : Nrs. 833.32 per sq m
Description : Carrying out the required operation for the application of tack coat including full compensation for
making arrangements for traffic in accordance with clause G 12 of the specification except for initial treatment to shoulders and construction of diversions
providing all materials to be incorporated in the work including all royalties fees, rents where necessary and all leads along the lead route
all labour and incindentals to complete the work to the specification and
Carrying out the work in part widths of roadway where directed
Unit : 10 10 sq m
a) When the application is upon existing bituminuous treated surface
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s4,2 30.a Skilled person-day Bitumen kg 5.00 78.10 390.50
Unskilled person-day 0.15 750.00 112.50 Fire wood kg 8.00 18.00 144.00 Sprayer hrs 0.04 1726.99 69.08
kerosine lit 0.50 85.40 42.70
Sub Total 577.20
Transportation
Total Labour Component ( A ) 112.50 Total Material Component ( B ) 577.20 Total Equipment Component ( C) ) 69.08
Sub Total (A+B+C ) : Nrs. 758.78
Rate : Nrs. 75.88 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 11.38
Total Cost: Nrs. 87.26
Rate : Nrs. 87.26 per sq m

12
Tack Coat
b) When the application is upon existing WBM
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit. Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s4,2 30.b Skilled person-day Bitumen kg 10.00 78.10 781.00
Unskilled person-day 0.20 750.00 150.00 Fire wood kg 16.00 18.00 288.00 Sprayer hrs 0.04 1726.99 69.08
kerosine lit 0.50 85.40 42.70
Sub Total 1111.70
Transportation 0.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 1111.70 Total Equipment Component ( C) ) 69.08
Sub Total (A+B+C ) : Nrs. 1330.78
Rate : Nrs. 133.08 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 19.96
Total Cost: Nrs. 153.04 per sq m

Item No 14
According to Norms of DoR 18 (A)
Description : Carrying out the required operation for the application of prime coat supplying of all necessary material.
Unit : 10 10 sq m
a) When the application is upon existing bituminuous treated surface
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s4,2 15.18.1 Skilled person-day Bitumen kg 4.90 78.10 382.69
Fire wood in open Sprayer
Unskilled person-day 0.20 750.00 150.00 oven kg 8.00 18.00 144.00 hrs 0.04 1726.99 69.08
Kerosine lit 0.50 85.40 42.70
Sub Total 569.39
Transportation 0.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 569.39 Total Equipment Component ( C) ) 69.08
Sub Total (A+B+C ) : Nrs. 788.47
Rate : Nrs. 78.85 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 11.83
Total Cost: Nrs. 90.67
Rate : Nrs. 90.67 per sq m

13
Item No 14
According to Norms of DoR 18 (B)
Description :
Unit : 10
Description : Carrying out the required operation for the application of prime coat supplying of all necessary material.
b)When the application is upon base course.
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount(Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s4,2 15.18.2 Skilled person-day Bitumen kg 9.75 78.10 761.48
Fire wood in open Sprayer
Unskilled person-day 0.20 750.00 150.00 oven kg 16.00 18.00 288.00 hrs 0.04 1726.99 69.08
Kerosine lit 0.50 85.40 42.70
Sub total 1092.17
Transportation 0.00
Total Labour Component ( A ) 150.00 Total Material Component ( B ) 1092.17 Total Equipment Component ( C) ) 69.08
Sub Total (A+B+C ) : Nrs. 1311.25
Rate : Nrs. 131.13 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 19.67
Total Cost: Nrs. 150.79
Rate : Nrs. 150.79 per sq m

Item No 15
Description : 13.09DOR Providing,mixing,laying and compaction of bituminous premix carpet Spec no:1307/1308
Unit : 1 cu m
Respective
Clause of
Specification Dor norms
Remarks
s (old) Labour (A) Material(B) Equipment ( c )
Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s)
4,2 15.24.kha Skilled person-day 0.45 1030.00 463.50 Bitumen lit 77.00 78.10 6013.70 Smooth wheel roller hrs 0.50 1201.37 600.69
Unskilled person-day 4.50 750.00 3375.00 Kerosene lit 7.70 85.40 657.57 Sprayer hrs 0.50 1726.99 863.50
Aggregate cu m 1.20 3245.76 3894.91
Per m3

Sub Total 10566.18

Total Labour Component ( A ) 3838.50 Total Material Component ( B ) 10566.18 Total Equipment Component ( C) 1464.18
Sub Total (A+B+C ) : Nrs. 15868.86
Rate : Nrs. 15868.86 per cu m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2380.33
Total Cost: Nrs. 18249.19
Rate : Nrs. 18249.19 per cu m
Item No 16
Description : Sand seal including compaction .
Unit : 10 10 sq m
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 15.23 Skilled person-day 0.10 1030.00 103.00 Bitumen kg 6.60 78.10 515.46 8-10 t roller hrs 0.04 1401.37 56.05
Unskilled person-day 0.14 750.00 105.00 Fire wood kg 16.00 18.00 288.00 Sprayer hrs 0.04 1726.99 69.08
( in open oven )
coarse sand cu m 0.07 3210.48 224.73
Sub Total 1028.19
Transportation 0.00
Total Labour Component ( A ) 208.00 Total Material Component ( B ) 1028.19 Total Equipment Component ( C) ) 125.13
Sub Total (A+B+C ) : Nrs. 1361.33
Rate : Nrs. 136.13 per sq m

14
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 20.42
Total Cost: Nrs. 156.55
Rate : Nrs. 156.55 per sq m

15
Item No
Description : 13.1DOR Bituminous Concrete/Asphalt concrete.Providing and laying Bituminous concrete/Asphalt concrete 5cm using crushed aggregate of specified grading,premixed with bituminous binder and filler as per drawing
and technical specification Spec 1307/1308
Unit : Cum
Respective Labour (A) Material(B) Equipment ( c )
Clause of Dor norms Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification (old)
Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 15.23 Skilled person-day 0.03 1030.00 30.90 Bitumen lit 117.00 78.10 9137.70 Asphalt Mixing Plant hr 0.04 1000.00 44.00
Unskilled person-day 0.13 750.00 97.50 Cement Tonne 0.02 16714.00 367.71 wheel Loader hr 0.66 2053.98 1355.63
Foreman person-day 0.01 750.00 7.50 Diesel Lit 10.45 85.40 892.41 Asphalt Paver hr 0.22 1201.37 264.30
Aggregate Cum 1.20 3316.32 3979.58 Steel tyred Roller hr 0.55 1201.37 660.75
Pneumatic Roller hr 0.55 1401.37 770.75
Tipper, Trucks hr 0.32 1612.39 515.96
Sub Total 14377.40

Total Labour Component ( A ) 135.90 Total Material Component ( B ) 14377.40 Total Equipment Component ( C) ) 3611.40
Sub Total (A+B+C ) : Nrs. 18124.71
Rate : Nrs. 18124.71 Per cum
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2718.71
Total Cost: Nrs. 20843.41
Rate : Nrs. 20843.41 Per cum

Item No 19
Description : Brick masonry with all necessary operations including full compensations for all labour , materials , scaffolding, and other incidentals required to complete the work
as per the specifications and as shown on the drawings. It includes full compensation for using specially moulded bricks on the face of walls with better provision
of weep holes jointed with cement sand mortar.
Unit : 1cu m
19.a) in 1:4 mix ratio
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s Brick
7 37.A.b Skilled person-day 1.50 1030.00 1545.00 (224*108*57mm) No 530.00 14.91 7902.30
Unskilled person-day 4.99 750.00 3742.50 Cement bag 2.00 835.70 1671.40
Sand cu m 0.35 3210.48 1123.67
Sub Total 10697.37
Transportation 0.00
Total Labour Component ( A ) 5287.50 Total Material Component ( B ) 10697.37 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 15984.87
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2397.73
Total Cost: Nrs. 18382.60
Rate : Nrs. 18382.60 per cu m

19.b) in 1:6mix ratio


Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s Brick
7 37.A.c Skilled person-day 1.50 1030.00 1545.00 (224*108*57mm) No 530.00 14.91 7902.30
Unskilled person-day 5.02 750.00 3765.00 Cement bag 1.40 835.70 1169.98
Sand cu m 0.38 3210.48 1219.98
Sub Total 10292.26
Transportation 0.00
Total Labour Component ( A ) 5310.00 Total Material Component ( B ) 10292.26 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 15602.26
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 2340.34
Total Cost: Nrs. 17942.60
16
Rate : Nrs. 17942.60 per cu m

17
Item no 20
Description 12.5 mm th. Plastering with cement sand mortar on brick walls or concrete surfaces with all necessary operations including full compensation for all labours, materials
scaffolding and other incidentals required to complete the work as per the specifications
Unit 100 sq m
20.a) in 1:4mix ratio
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amoun Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. t(Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s7-9.4 37.B.c Skilled person-day 15.00 1030.00 15450.00 Cement Bag 7.26 835.70 6067.18
,7-12 Unskilled person-day 13.59 750.00 10192.50 Sand cu m 1.46 3210.48 4687.30
Bamboo nos 2.00 210.00 420.00
Rope ls 100.00 15 mutha
7-13.2 Sub Total 11274.48
Transportation 0.00
Total Labour Component ( A ) 25642.50 Total Material Component ( B ) 11274.48 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 36916.98
Rate : Nrs. 369.17 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 55.38
Total Cost: Nrs. 424.55
Rate : Nrs. 424.55 per sq m

Description 12.5 mm th. Plastering with cement sand mortar on brick walls or concrete surfaces with all necessary operations including full compensation for all labours, materials
scaffolding and other incidentals required to complete the work as per the specifications
Unit 100 sq m
20.b) in 1:6mix ratio
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s7-9.4 37.B.d Skilled person-day 15.00 1030.00 15450.00 Cement Bag 5.76 835.70 4813.63
,7-12 Unskilled person-day 13.70 750.00 10275.00 Sand cu m 1.58 3210.48 5072.56
Bamboo nos 2.00 210.00 420.00
Rope 100.00 100.00
7-13.2 Sub Total 10406.19
Transportation 0.00
Total Labour Component ( A ) 25725.00 Total Material Component ( B ) 10406.19 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 36131.19
Rate : Nrs. 361.31 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 54.20
Total Cost: Nrs. 415.51
Rate : Nrs. 415.51 per sq m

18
Item no 22
Description Pointing work with cement sand mortar on brick wall with all required operations including full compensation for all labours, materials and other incidentals necessary
to complete the work as per the specifications
Unit 100 sq m
22.a) in 1:3mix ratio
Respective Dolidar Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Norms n. Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s7-9.3 37.C.c Skilled person-day 8.00 1030.00 8240.00 Cement Bag 1.92 835.70 1604.54
7-12 Unskilled person-day 8.88 750.00 6660.00 Sand cu m 0.29 3210.48 931.04
Bamboo nos 2.00 210.00 420.00
Rope Ls 100.00 100.00
and 7-13.3 Sub Total 3055.58
Transportation 0.00
Total Labour Component ( A ) 14900.00 Total Material Component ( B ) 3055.58 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 17955.58
Rate : Nrs. 179.56 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 26.93
Total Cost: Nrs. 206.49
Rate : Nrs. 206.49 per sq m
Item no 23
Description Dry brick laying
Unit 10 sq m
23.1.a) Flat
Respective Dor norms n. Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 11.15.ka Skilled person-day 0.50 1030.00 515.00 Brick Nos 420.00 14.91 6262.20
Unskilled person-day 1.00 750.00 750.00 Sand cu m 0.71 3210.48 2279.44
Sub Total 8541.64
Transportation 0.00
Total Labour Component ( A ) 1265.00 Total Material Component ( B ) 8541.64 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 9806.64
Rate : Nrs. 980.66 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 147.10
Total Cost: Nrs. 1127.76
Rate : Nrs. 1127.76 per sq m

Item no 23
Description Dry brick laying
Unit 10 sq m
23.1.b) edge
Respective Dor norms n. Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 11.15. kha Skilled person-day 1.00 1030.00 1030.00 Brick Nos 750.00 14.91 11182.50
Unskilled person-day 3.25 750.00 2437.50 Sand cu m 0.71 3210.48 2279.44
Sub Total 13461.94
Transportation 0.00
Total Labour Component ( A ) 3467.50 Total Material Component ( B ) 13461.94 Total Equipment Component ( C) )
Sub Total (A+B+C ) : Nrs. 16929.44
Rate : Nrs. 1692.94 per sq m
Contractor 's Miscellaneous Overhead Expensed ( 15 % ): Nrs. 253.94
Total Cost: Nrs. 1946.89
Rate : Nrs. 1946.89 per sq m
Item no 23.2
Description Dry Stone laying work
Unit 1 cu.m.
Respective Dor norms n. Labour (A) Material(B) Equipment ( c )
Clause of Rate (Nrs) Amount Rate (Nrs) Amount (Nrs) Rate (Nrs) Amount(Nr
Specification 19
(old) Category Unit Qty. (Nrs) Type Unit Qty. Type Unit Qty. s) Remarks
s 11.16 Skilled person-day 1.00 1030.00 1030.00 stone m3 1.10 2363.76 2600.14
Unskilled person-day 3.50 750.00 2625.00 Sand cu m 0.71 3210.48 2279.44

S.n. Item

1 Skilled
2 Unskilled

10 Agg3-6
11 Agg 6-12
12 Sand

21 fire wood
22 Stone dust
23 Water
Budhanilkantha Municipality Rate 2075/076

3 Gravel Local Quarry


Gravel(Tikabhairav, Bhakunde
4 equiv Quarry site)
Gravel (cross run material size 63
5 mm down )
6 40mm down crushed base
7 Bitumen 80/100
8 Agg 10-20
9 Agg 20-40

14 Cement( OPC) with load/unload


15 Cement (OPC) with load/ unload
16 Steel (TMT )
17 Steel
18 Binding wire
19 Barbed wire
Mix wooden Jamun,salla , Utis
20 wood

24 GI wire, Medium
24.1 Medium class
8 mm dia
10 mm dia
12 mm dia
23.2 Heavy Duty
G I wire 8mm dia ( H )
G I wire 10mm dia (H)
G I wire 12mm dia ( H)
24 gravel girt
25 Brick(Chimney bhatta)
26 Stone quarry
27 Water proof ply 9mm
28 Boulder Stone from river 100mm

29 Road equipment

Roller vib. 6.3 ton per hour.(with


fuel )
Roller Pneumatic per hour.(with
fuel )
Truck Tripper nissan CPC 14E
Dozer D50
Diesel 071.4.29
water browser (with fuel )
loader (with fuel )
Source from Approved DTO Rate
sn
2
6
7.4

7.3

7.5
7.6
10.1
5.2
5.3
5.4

4.1
11.ka

13.2.a+b

13.d
23

14.1.10
14.1.Ta
7.chha
32
20.1b.2b.3b

20.1b
20.2b
20.3b

20c
20c
20c
8.gha
1.3
3.1.1

3.1.2

53.pp

53.nn

53.z

aaa
gg
ft3

95
84
92
91
m3

57.24 2019.43

76 2681.28

76 2681.28
84 2963.52

94

1441.666667
3316.32
3351.6
2963.52
3245.76
3210.48

0
0

50862

41.04 1447.89

67 2363.76

105
0

3704.4

0
Rate

1030.00
750.00
2019.43

2681.28

2681.28
2963.52
78.10
3316.32
3351.60
2963.52
3245.76
3210.48
835.70
16714.00
84.00
84000.00
92.00
97.35

50862.00
18.00
1447.89
0.26

100.00
100.00
100.00

105.00
105.00
105.00
0.00
14.91
2363.76
956.75
3704.40

1201.37

1401.37
1612.39
2653.98
85.40
1280.15
2053.98
Unit

Md
Md
Cu M

Cu M

Cu M
kg
Cu M
Cu M
Cu M
Cu M
Cu M
bag
MT
kg
Mt
kg
kg

Cu M
kg
Cu M

kg
kg
kg

kg
kg
kg
Cu M
No
Cu M
sqm
Cu M

hr.

hr.
hr.
hr.
lt
hr.
hr.

Grader (with fuel )
Air compressor

Bitumen heater/Boiler
Sprayer bitumen
Batch mix HMP
Paver finisher
Generater
Smooth wheeled roller
pneumatic roller

30 water
31 Nails
32 R.C.C. Hume Pipe and Collar


PIPES
a) NP-2
150 mm dia.
200 mm dia.
225 mm dia.
250 mm dia.
300 mm dia.
350 mm dia.
375 mm dia.
400 mm dia.
450 mm dia.
500 mm dia.
600 mm dia.
700 mm dia.
750 mm dia.
800 mm dia.
900 mm dia.
1000 mm dia.
1200 mm dia.
1500 mm dia.
b) NP-3
150 mm dia.
200 mm dia.
225 mm dia.
250 mm dia.
300 mm dia.
350 mm dia.
375 mm dia.
400 mm dia.
450 mm dia.
500 mm dia.
600 mm dia.
700 mm dia.
750 mm dia.
800 mm dia.
900 mm dia.
1000 mm dia.
1200 mm dia.
1500 mm dia
1500 mm dia.
bb

53.ee
53.uu

32
32
26

26.a

26.b
0
0
1558.67
335.40

1897.79
1726.99
1000.00
1201.37
150.00
1201.37
1000.00

0.26
112.00

570.00
740.00
883.00
925.00
1260.00
1325.00
1520.00
1750.00
1852.00
2080.00
2740.00
3575.00
3870.00
4320.00
5835.00
6805.00
8301.00
17450.00

1310.00
1745.00
0.00
2185.00
3140.00
3520.00
3760.00
4010.00
4500.00
5020.00
6200.00
7485.00
8600.00
9384.00
12172.00
13525.00
16100.00
25300.00
25300.00
hr.

hr.
hr.
hr.
hr.
hr.
hr.
hr.

ltr
kg

R.m
R.m
R.m
R.m
R.m

R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m

R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.m
R.C.C. Hume Pipe
Collar 26…a
a) NP-2
150 mm dia. 145 Nos
200 mm dia. 193 Nos
225 mm dia. 0 Nos
250 mm dia.

239 Nos
300 mm dia.

324 Nos
350 mm dia.

357 Nos
375 mm dia.

392 Nos
400 mm dia. 451 Nos
450 mm dia. 476 Nos

500 mm dia. 435 Nos


600 mm dia. 706 Nos
700 mm dia. 920 Nos

750 mm dia. 995 Nos


800 mm dia. 1110 Nos

900 mm dia. 1500 Nos


1000 mm dia. 1752 Nos


1200 mm dia. 2137 Nos
1500 mm dia. 4492 Nos

b) NP-3 26…b
150 mm dia. 327 Nos

200 mm dia. 436 Nos


250 mm dia. 544 Nos


300 mm dia. 783 Nos


350 mm dia. 879 Nos
375 mm dia. 940 Nos

400 mm dia. 1000 Nos


450 mm dia. 1125 Nos


500 mm dia. 1255 Nos


600 mm dia. 1550 Nos

700 mm dia. 1871 Nos


750 mm dia. 2150 Nos


800 mm dia. 2344 Nos


900 mm dia. 3042 Nos


1000 mm dia. 3382 Nos


1200 mm dia. 4024 Nos


1500 mm dia. 6324 Nos


33 Jute 31 100 Kg
34 Soil (mud without transportation) 31 318.6 m3
35 Kerosine 85 ltr
36 Rope 100
37 Bamboo(18-20 foot length) 210 Nos
38 19 mm thick water proof ply 1495.64 Sq. m.
2019.86

2264.46
308.21 4325.00
93.97 1441.67 2681.85

Fuel
cosumtion Fuel
charge cosumtion deisel
Hire Rate Amount charge ltr rate/lits 75.57

800.00 401.37 4.70 85.40

1000.00 401.37 4.70 85.40


1100 512.39 6 85.40
1800 853.98 10 85.40
93.00
550 730.15 8.55 85.40
1200 853.98 10 85.40
1200 358.67 4.2 85.40
250 85.40 1 85.40

1300.00 597.79 7.00 85.40


1300.00 426.99 5.00 85.40

1656.40
1407.94
1449.00

2530000
400gm Kg

17 42.5
SUMMARY OF ROAD RATE ANALYSIS

Government Of Nepal
Budhanilkantha Municipality Office
Golfutar , Kathmandu

SUMMARY OF RATE ANALYSIS


(Fiscal Year - 2076/077)

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)

1.0 Site Clearance


1.1 Site Clearance - Clearing and grubbing etc all complete
work 26.80 30.82 28.00 32.20 30.00 34.50
Sq M
1.2 Surface dressing work Sq M 6.70 7.71 7.00 8.05 7.50 8.63
1.3 Stripping of top soil work Cu M 536.00 616.40 560.00 644.00 600.00 690.00
2.0 Excavation work
2.1 Excavation in roadway and drain
a) Ordinary Soil Cu M 345.05 396.81 360.50 414.58 386.25 444.19
b) Hard Soil Cu M 414.06 476.17 432.60 497.49 463.50 533.03
c) Ordinary Rock Cu M 1380.20 1587.23 1442.00 1658.30 1545.00 1776.75
2.2 Exavation for structures
a) Ordinary Soil Cu M 690.10 793.62 721.00 829.15 772.50 888.38
b) Hard Soil Cu M 1380.20 1587.23 1442.00 1658.30 1545.00 1776.75
c) Ordinary Rock Cu M 2760.40 3174.46 2884.00 3316.60 3090.00 3553.50
2.3 Filling work with or with out compaction
2.3.1 Construction of roadway in embankments Cu M 172.53 198.40 180.25 207.29 193.13 222.09
2.3.2 Construction of roadway in embankments with hard soil
586.59 674.57 612.85 704.78 656.63 755.12
cuttings Cu M
2.3.3 Compaction of filling material with Rolling Cu M 20.84 23.96 18.50 21.28 20.06 23.07

Page 26
SUMMARY OF ROAD RATE ANALYSIS

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)
2.4 Transporting materials from roadway and drain
excavation Cu M

3.0 Sub grade work


3.1 Scarifying existing granular/bituminuous road surface Sq M 27.60 31.74 28.84 33.17 30.90 35.54
3.2 Subgrade construction with treated materials Cu M 416.53 479.01 416.93 479.47 425.90 489.78
3.3 Subgrade construction without treated materials Cu M 152.53 175.41 152.93 175.87 161.90 186.18
3.4 Prepration of Subgrade for rehabilitaion works ( filing or
cutting depth 10cm to 20cm thick)
3.4.1 22.68 26.08 25.48 29.30 27.05 31.10
In Common soil Sq M
3.4.2 78.38 90.14 81.99 94.29 87.86 101.04
In Gravel & boulder mixed soil Sq M
4.0 Sub Base (Gravelling work)
Carrying out the construction operation of gravel
material for sub-base work
4.1 Local Gravel with compaction . Cu M 2200.48 2530.55 2353.87 2706.95 2364.64 2719.34
4.2 Gravel quarry from (Tikabhairav, Bhakunde site) Cu M 2860.21 3289.24 3081.91 3544.20 3092.68 3556.58
4.3 Local Gravel without compaction . Cu M 1901.19 2186.37 2052.23 2360.06 2054.58 2362.76
5.0 Base course work ( WBM )
Carrying out the construction operation of Water
bound macadam ( WBM ) , sub-base / base course
5.1 Grading No I For sub base Cu M 3625.09 4168.85 3882.17 4464.50 3891.94 4475.74
5.2 Grading No II -For base Cu M 3707.64 4263.79 3971.08 4566.74 3980.85 4577.98

6.0 Black Topped work


6.1 Cleaning top surface by brush and broom before
pitching
6.1.1 On Water Bound Macadam Sq M 21.25 24.44 22.00 25.30 23.25 26.74

Page 27
SUMMARY OF ROAD RATE ANALYSIS

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)
6.1.2 On Other Surfaces Sq M 17.90 20.59 18.50 21.28 19.50 22.43
6.2 Semi-grouting works
6.2.1 5 cm thick Semi-grouting works including compaction
663.11 762.57 705.28 811.07 724.62 833.32
Sq M
6.3 Tack coat
Carrying out the required operation for the application
of tack coat
6.3.1 Bituminuous treated surface Sq M 69.08 79.44 73.37 84.38 75.88 87.26
6.3.2 Water Bound Macadam Sq M 114.65 131.85 128.58 147.87 133.08 153.04
6.4 Prime coat
Carrying out the required operation for the application of
prime coat
6.4.1 Bituminuous treated surface Sq M 71.75 82.51 76.12 87.54 78.85 90.67
6.4.2 Water Bound Macadam Sq M 119.32 137.22 126.71 145.72 131.13 150.79
6.5 Premix carpeting work
Carrying out the required operation of premix carpeting
16536.26 19016.70 17566.38 20201.34 15868.86 18249.19
work including compaction Cu M

6.6 For Patch work only


6.6.1 Semi-grouting works including compaction Sq M 742.22 853.55 742.22 853.55 742.22 853.55
6.6.2 premix carpeting work including compaction Cu M 16536.26 19016.70 17566.38 20201.34 15868.86 18249.19

6.7 Asphalt concrete/Bituminous concrete(50mm) CuM - - - - 18124.71 20843.41

6.8 Sand seal laying works Sq M 124.25 142.89 131.16 150.84 136.13 156.55
7.0 Other costruction work
7.1 Dry brick/ stone soling.

Page 28
SUMMARY OF ROAD RATE ANALYSIS

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)
7.1.1 Flat Brick Sq M 858.89 987.72 972.16 1117.99 980.66 1127.76
7.1.2 On edge Brick Sq M 1484.14 1706.76 1669.69 1920.15 1692.94 1946.89
7.1.3 Stone soling work (15cm thick ) Sq M 770.38 885.94 828.96 953.30 853.46 981.48
Stone filling in the foundations and levelling including
3672.17 4222.99 3886.51 4469.49 3961.51 4555.74
7.1.4 haulage distance up to 30 m. Cu M
7.2 Cement Concrete Work.
7.2.1 A) In foundation
a) M 10 Grade ( 1:3:6 ) mix by volume. Cu M 10676.16 12277.58 11445.25 13162.04 11605.43 13346.24
b) M 15 Grade ( 1:2:4 ) mix by volume. Cu M 12121.80 13940.07 12973.17 14919.15 13105.75 15071.61
7.2.2 In superstructural components ( beam,slab, abutment, caps
etc.)
a) M 15 Grade ( 1:2:4 ) mix by volume. Cu M 12851.78 14779.54 13643.18 15689.66 13825.76 15899.63
b) M 20 Grade ( 1:1.5:3 ) mix by volume. Cu M 14156.38 16279.84 15024.84 17278.56 15185.94 17463.83
7.3 Brick Masonry work with all necessary operations .
7.3.1 In 1:4 c/s mix ratio Cu M 14186.14 16314.06 15660.97 18010.11 15984.87 18382.60
7.3.2 In 1:6 c/s mix ratio Cu M 13810.91 15882.55 15267.68 17557.83 15602.26 17942.60
7.4 Formwork with timber /ply wood as material .
Providing preparing and instaling form work and
removing after completion work
7.4.1 Foundation & footing work Sq M 625.02 718.77 638.52 734.30 659.02 757.87
7.4.2 wall work Sq M 569.23 654.61 569.23 654.61 569.23 654.61
7.4.3 Lintel , Beam & slab structure work Sq M 372.76 428.67 389.26 447.65 414.36 476.51
7.5 Reinforcement for Rcc work ( Tor Steel )
7.5.1 Type ( A ) for Crank type along bar ( tor steel ) Kg 89.64 103.09 108.71 125.02 101.58 116.82
7.5.2 Type ( B ) for Plain straight bar ( tor steel ) for common
84.11 96.73 102.90 118.34 95.35 109.65
use Kg
7.5.3 Type ( C) for C type hook bar ( tor steel ) Kg 86.88 99.91 105.81 121.68 98.47 113.23
7.5.4 Type ( D) for stirups ( tor steel ) Kg 100.70 115.81 120.33 138.38 114.04 131.15

Page 29
SUMMARY OF ROAD RATE ANALYSIS

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)
7.6 Plastering work
7.6.1 12.5 mm th. plastering with cement sand mortar on
brick walls of concrete surfaces.
a) In 1:4 c/s mix ratio Sq M 332.04 381.85 352.99 405.93 369.17 424.55
b) In 1:6 c/s mix ratio Sq M 324.16 372.79 344.84 396.57 361.31 415.51
7.7 Pointing work in cement sand mortar on brick & stone
161.04 185.20 169.81 195.28 179.56 206.49
wall with all necessary operations in 1:3 c/s mix ratio Sq M
Structural work in Road way
8.0 Retaining / protection wall work
Stone Masonry Work Un-coursed Rubble Masonry
8.1 In Dry wall Cu M 3904.90 4490.64 4130.14 4749.66 4240.14 4876.16
8.2 In Stone wall 1:4 c/s mix ratio Cu M 9163.23 10537.72 9791.38 11260.09 9919.89 11407.87
8.3 In Stone wall 1:6 c/s mix ratio Cu M 8897.40 10232.01 9514.22 10941.35 9652.56 11100.45
9.0 A Gabion Wall work
Fabrication of gabion boxes including rolling, cutting
and weaving. Mesh wire-10swg selvedge wire 7 swg ,
Hexagonal mesh size -100*120 mm with partition
9.1 Using Heavy class wire
a) Box sizes 2m*1m*1m Box 2969.93 3415.42 3329.57 3829.01 3314.25 3811.39
b) Box sizes 3m*1m*1m Box 4300.07 4945.08 4820.97 5544.12 4798.65 5518.45
c) Box sizes 2m*1m*0.5m Box 2069.81 2380.28 2321.14 2669.31 2309.70 2656.16
d) Box sizes 3m*1m*0.5m Box 3024.63 3478.32 3391.63 3900.37 3375.15 3881.42
e) Box sizes 2m*1m*0.3m Box 1714.80 1972.02 1923.16 2211.63 1913.50 2200.53
f) Box sizes 3m*1m*0.3m Box 2510.72 2887.33 2816.00 3238.40 2801.60 3221.84

Using Medium class wire


9.2

Page 30
SUMMARY OF ROAD RATE ANALYSIS

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)
a) Box sizes 2m*1m*1m Box 2868.32 3298.57 3198.02 3677.72 3182.70 3660.11
b) Box sizes 3m*1m*1m Box 4152.32 4775.17 4630.42 5324.98 4608.10 5299.32
c) Box sizes 2m*1m*0.5m Box 2000.40 2300.46 2229.04 2563.40 2217.60 2550.24
d) Box sizes 3m*1m*0.5m Box 2922.84 3361.27 3257.18 3745.76 3240.70 3726.81
e) Box sizes 2m*1m*0.3m Box 1658.22 1906.95 1846.76 2123.77 1837.10 2112.67
f) Box sizes 3m*1m*0.3m Box 2427.32 2791.42 2704.00 3109.60 2689.60 3093.04
9.3 Packing and filling of gabion crates with rubbles stones.
3220.40 3703.46 3413.14 3925.11 3471.64 3992.38
Cu M
9.4 Assembling of wire crates/gabion/revetment and
placing them in position.
9.4.1 Using Light class wire
Binding wire 12 swg.
a) Box sizes 2m*1m*1m Box 146.75 168.76 160.85 184.98 162.50 186.88
b) Box sizes 3m*1m*1m Box 205.40 236.21 224.90 258.64 227.50 261.63
c) Box sizes 2m*1m*0.5m Box 113.79 130.85 124.71 143.41 126.00 144.90
d) Box sizes 3m*1m*0.5m Box 146.75 168.76 160.85 184.98 162.50 186.88
e) Box sizes 2m*1m*0.3m Box 99.35 114.25 108.95 125.29 110.00 126.50
f) Box sizes 3m*1m*0..3m Box 142.20 163.53 155.70 179.06 157.50 181.13

9.4.2 Using Medium class wire


Binding wire 12 swg.
a) Box sizes 2m*1m*1m Box 146.75 168.76 160.85 184.98 162.50 186.88
b) Box sizes 3m*1m*1m Box 211.32 243.01 231.60 266.33 234.00 269.10
c) Box sizes 2m*1m*0.5m Box 110.60 127.19 121.10 139.27 122.50 140.88
d) Box sizes 3m*1m*0.5m Box 146.75 168.76 160.85 184.98 162.50 186.88
e) Box sizes 2m*1m*0.3m Box 99.35 114.25 108.95 125.29 110.00 126.50
f) Box sizes 3m*1m*0..3m Box 142.20 163.53 155.70 179.06 157.50 181.13

Page 31
SUMMARY OF ROAD RATE ANALYSIS

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)
9.5 Gabion wall all complete work ( including fabrication ,
packing stone & assembling of wire crates with using Heavy
class wire as above specification)
9.5.1 Unit per Box
a) Box sizes 2m*1m*1m ( 2 m3 ) Box 10313.27 11860.26 10313.27 11860.26 10313.27 11860.26
b) Box sizes 3m*1m*1m ( 3 m3 ) Box 14172.60 16298.49 15291.97 17585.77 15447.56 17764.69
c) Box sizes 2m*1m*0.5m ( 1 m3 ) Box 5400.81 6210.93 5855.38 6733.68 5903.84 6789.41
d) Box sizes 3m*1m*0.5m ( 1.5 m3 )
8001.98 9202.28 8672.18 9973.01 8745.10 10056.87
Box
9.5.2 Unit per Cu. m.
a) Box sizes 2m*1m*1m Cu M 5156.64 5930.13 5156.64 5930.13 5156.64 5930.13
b) Box sizes 3m*1m*1m Cu M 4724.20 5432.83 5097.32 5861.92 5149.19 5921.56
c) Box sizes 2m*1m*0.5m Cu M 5400.81 6210.93 5855.38 6733.68 5903.84 6789.41
d) Box sizes 3m*1m*0.5m Cu M 5334.66 6134.85 5781.46 6648.67 5830.07 6704.58
9.0 Gabion Wall work ( Machine made maccaferi
B
Box )
Fabricated Gabion boxes by Meachine weaving
Mechanically Selvedged double twist wire mesh all
complete work. Hexogonal mesh size 100*120 Maccaferi
box Gabion (MBG) 2.7/3.7/2.2 Heavy galvanized(ZN)
9.6 Using Heavy class wire
a) Box sizes 2m*1m*1m Box 3045.00 3501.75 3045.00 3501.75 3045.00 3501.75
b) Box sizes 3m*1m*1m Box 4299.00 4943.85 4299.00 4943.85 4299.00 4943.85
c) Box sizes 1.5m*1m*1m Box 2269.00 2609.35 2269.00 2609.35 2269.00 2609.35
d) Box sizes 2m*1m*0.5m Box 2150.00 2472.50 2150.00 2472.50 2150.00 2472.50
e) Box sizes 3m*1m*0.5m Box 3045.00 3501.75 3045.00 3501.75 3045.00 3501.75

Page 32
SUMMARY OF ROAD RATE ANALYSIS

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)
9.7 Gabion wall all complete work ( including fabrication ,
packing stone & assembling of wire crates with using Heavy
class wire as above specification)
9.7.1 Unit per Box
a) Box sizes 2m*1m*1m ( 2 m3 ) Box 9485.81 10908.68 9871.27 11351.96 9988.27 11486.51
b) Box sizes 3m*1m*1m ( 3 m3 ) Box 13960.21 16054.24 14538.41 16719.17 14713.91 16920.99
c) Box sizes 1.5m*1m*1m ( 1.5 m3 )
7099.61 8164.55 7388.70 8497.01 7476.45 8597.92
Box
d) Box sizes 2m*1m*0.5m ( 1 m3 ) Box 5370.40 6175.96 5563.14 6397.61 5621.64 6464.88
e) Box sizes 3m*1m*0.5m ( 1.5 m3 )
7875.61 9056.95 8164.70 9389.41 8252.45 9490.32
Box
9.7.2 Unit per Cu. m.
a) Box sizes 2m*1m*1m ( 2 m3 ) Cu M 4742.90 5454.34 4935.64 5675.98 4994.14 5743.26
b) Box sizes 3m*1m*1m ( 3 m3 ) Cu M 4653.40 5351.41 4846.14 5573.06 4904.64 5640.33
c) Box sizes 1.5m*1m*1m ( 1.5 m3 )
4733.07 5443.03 4925.80 5664.67 4984.30 5731.95
Cu M
d) Box sizes 2m*1m*0.5m ( 1 m3 ) Cu M 5370.40 6175.96 5563.14 6397.61 5621.64 6464.88
e) Box sizes 3m*1m*0.5m ( 1.5 m3 )
5250.40 6037.96 5443.14 6259.61 5501.64 6326.88
Cu M
10 Hume pipe work
Laying fitting and fixing of hume pipe having a length
of 1 m of more.
Rcc Hume pipe - NP2
10.1 For one or first pipe.
a) Pipe having 150 mm diameter. R.m 553.25 636.24 595.50 684.83 664.49 764.16
b) Pipe having 300 mm diameter. R.m 1209.50 1390.93 1428.00 1642.20 1410.74 1622.35
c) Pipe having 450 mm diameter. R.m 1733.50 1993.53 1869.00 2149.35 2002.74 2303.15
d) Pipe having 600 mm diameter. R.m 2584.50 2972.18 2785.00 3202.75 2984.86 3432.59
e) Pipe having 750 mm diameter.

Page 33
SUMMARY OF ROAD RATE ANALYSIS

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)
f) Pipe having 900 mm diameter. R.m 5378.50 6185.28 5801.00 6671.15 6193.10 7122.07
10.2 For every subsequent pipe having a length of minimum
1m
a) Pipe having 150 mm diameter. R.m 585.79 673.66 627.77 721.94 707.29 813.39
b) Pipe having 300 mm diameter. R.m 1319.88 1517.86 1539.89 1770.87 1526.92 1755.96
c) Pipe having 450 mm diameter. R.m 1843.88 2120.46 1980.89 2278.02 2121.49 2439.71
d) Pipe having 600 mm diameter. R.m 2956.92 3400.46 3168.47 3643.75 3324.69 3823.39
e) Pipe having 750 mm diameter.
f) Pipe having 900 mm diameter. R.m 6208.12 7139.34 6658.84 7657.67 7069.30 8129.70
Rcc Hume pipe-Np3
Laying fitting and fixing of hume pipe having a length
of 1 m of more.
10.3 For one or first pipe.
a) Pipe having 150 mm diameter. R.m 1264.05 1453.66 1362.90 1567.34 1404.49 1615.16
b) Pipe having 300 mm diameter. R.m 2867.50 3297.63 3093.00 3556.95 3290.74 3784.35
c) Pipe having 450 mm diameter. R.m 4069.50 4679.93 4392.00 5050.80 4650.74 5348.35
d) Pipe having 600 mm diameter. R.m 5635.50 6480.83 6080.00 6992.00 6444.86 7411.59
e) Pipe having 750 mm diameter.
f) Pipe having 900 mm diameter. R.m 10968.50 12613.78 11838.00 13613.70 12530.10 14409.62
10.4 For every subsequent pipe having a length of minimum
1m
a) Pipe having 150 mm diameter. R.m 1238.79 1424.61 1332.77 1532.69 1447.29 1664.39
b) Pipe having 300 mm diameter. R.m 2977.88 3424.56 3204.89 3685.62 3406.92 3917.96
c) Pipe having 450 mm diameter. R.m 4179.88 4806.86 4503.89 5179.47 4746.94 5458.98
d) Pipe having 600 mm diameter. R.m 6007.92 6909.11 6463.47 7433.00 6791.11 7809.77
e) Pipe having 750 mm diameter.
f) Pipe having 900 mm diameter. R.m 11798.12 13567.84 12695.84 14600.22 13329.49 15328.91

Page 34
SUMMARY OF ROAD RATE ANALYSIS

F.Y. 2074/075 F.Y. 2075/076 F.Y. 2076/077

S No. Item no. Description of Work Unit Remarks


Contractor Contractor Contractor
Users Rate Users Rate Users Rate
Rate Rate Rate
(Excluding (Excluding (Excluding
(Including (Including (Including
Overhead) Overhead) Overhead)
Overhead) Overhead) Overhead)

11 HDPE Double Wall Corrugated Pipe(For sewerage and drainage application)

a) Pipe having 150 mm diameter. R.m - - - - 561.11 645.28


b) Pipe having 200 mm diameter. R.m - - - - 1586.86 1824.89
c) Pipe having 250 mm diameter. R.m - - - - 2012.61 2314.51
d) Pipe having 300 mm diameter. R.m - - - - 3298.36 3793.12
e) Pipe having 400 mm diameter. R.m - - - - 4259.86 4898.84
f) Pipe having 500 mm diameter. R.m - - - - 5110.98 5877.62
g) Pipe having 600 mm diameter. R.m - - - - 8652.10 9949.92
h) Pipe having 800 mm diameter. R.m - - - - 14271.90 16412.69
i) Pipe having 1000 mm diameter. R.m - - - - 21323.15 24521.62

Page 35
RATE ANALYSIS OF CONSTRUCTION WORK ITEMS

District: Kathmandu FY: 2075/76


I SITE CLEARANCE:
Norms Serial No: 1
Clause No.: 1-1.5(a), 1-1.5(b) & 1-1.6
Site Clearance : It includes Clearing and Grubbing including the cutting of trees (only if necessary) having girth of
less than 30 cm when measured at 1m above the ground.
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.04 700.00 28.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 28.00
2.00 Tools /Tools / Equipment
Picks, Shovels, Kodalo, Doko/Baskets 0.84
Sub Total Tool/Equipment 0.84
Sub Total (Labor+Tool/Equipment) -I 28.84
Contractor Over head 15% of I 4.33
Total rate per Sqm 33.17

Norms Serial No: 2


Clause no.:
Cutting of 1-1.5(c)
trees having& girth
1-1.6of above 30 cm when measured at 1 m above the ground including the removal of trunk,
branches and stumps up to a lead of 100 m along the lead route for trees of size:
a. Above 30cm to 60cm girth
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.30 700.00 210.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 210.00
2.00 Tools / Equipment
Axes, Khukuri, Saws, Crowbars,
Wheel Barrows or Bullock Carts 6.30

Sub Total Tool/Equipment 6.30


Sub Total (Labor+Tool/Equipment) -I 216.30
Contractor Over head 15% of I 32.45
Total rate per no 248.75

b. Above 60cm to 90cm girth


Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.40 700.00 280.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 280.00
2.00 Tools / Equipment
Axes, Khukuri, Saws, Crowbars,
8.40
Wheel Barrows or Bullock Carts
Sub Total Tool/Equipment 8.40
Sub Total (Labor+Tool/Equipment) -I 288.40
Contractor Over head 15% of I 43.26
Total rate per no 331.66

c. Above 90cm to 180cm girth


Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 1.50 700.00 1050.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 1050.00
2.00 Tools / Equipment
Axes, Khukuri, Saws, Crowbars,
31.50
Wheel Barrows or Bullock Carts
Sub Total Tool/Equipment 31.50
Sub Total (Labor+Tool/Equipment) -I 1081.50
Contractor Over head 15% of I 162.23
Total rate per no 1243.73

c. Above 180cm to 270 cm girth


Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 3.00 700.00 2100.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 2100.00
2.00 Tools / Equipment
Axes, Khukuri, Saws, Crowbars,
63.00
Wheel Barrows or Bullock Carts
Sub Total Tool/Equipment 63.00
Sub Total (Labor+Tool/Equipment) -I 2163.00
Contractor Over head 15% of I 324.45
Total rate per no 2487.45

c. Above 270cm to 450 cm girth


Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 10.00 700.00 7000.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 7000.00
2.00 Tools / Equipment
Axes, Khukuri, Saws, Crowbars,
210.00
Wheel Barrows or Bullock Carts
Sub Total Tool/Equipment 210.00
Sub Total (Labor+Tool/Equipment) -I 7210.00
Contractor Over head 15% of I 1081.50
Total rate per no 8291.50
Norms Serial No:15
and 2-5.4.3

Scarifying existing granular/bituminous road surface for carrying out the required operations necessary to complete the work. This
includes handling, salvaging, stacking and disposing of scarified material up to a lead of 100 m along the lead route.

Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.20 700.00 140.00
Skilled md 0.00 0.00
Sub Total Labor 140.00
2.00 Tools / Equipment
Axes, Khukuri, Saws, Crowbars, Wheel
Barrows or Bullock Carts 4.20

Sub Total Tool/Equipment 4.20


Sub Total (Labor+Tool/Equipment) -I 144.20
Contractor Over head 15% of I 21.63
Total rate per no 165.83

Norms Serial No:DoR


Clause No:201
Felling and uprooting of bamboo,clearing the area, stacking of bamboo and disposing of wastes to 10m

Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 2.80 700.00 1960.00
Skilled md 0.00 0.00
Sub Total Labor 1960.00
2.00 Tools / Equipment
,@ 3% of labour 58.80
Sub Total Tool/Equipment 58.80
Sub Total (Labor+Tool/Equipment) -I 2018.80
Contractor Over head 15% of I 302.82
Total rate per m3 2321.62

II EARTHWORK

Norms Serial No: 5


Clause no.: 2.1,2.2,2-1.8 and 2-1.9
Excavation in Roadway , drain and foundation of structure including removal and satisfactory disposal of all materials
up to a lead of 50m along the lead route.
a. Ordinary soil
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.50 700.00 350.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 350.00
2.00 Tools / Equipment
Picks, Shovels, Kodalo,
Doko/Baskets/Wheel Barrows,
Crowbars 10.50
Sub Total Tool/Equipment 10.50
Sub Total (Labor+Tool/Equipment) -I 360.50
Contractor Over head 15% of I 54.08
Total rate per m3 414.58

b. Hard soil
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.60 700.00 420.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 420.00
2.00 Tools / Equipment
Picks, Shovels, Kodalo,
Doko/Baskets/Wheel Barrows,
Crowbars 12.60
Sub Total Tool/Equipment 12.60
Sub Total (Labor+Tool/Equipment) -I 432.60
Contractor Over head 15% of I 64.89
Total rate per m3 497.49

c. Ordinary rock
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 2.00 700.00 1400.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 1400.00
2.00 Tools / Equipment
Picks, Shovels, Kodalo,
Doko/Baskets/Wheel Barrows, 42.00
Crowbars
Sub Total Tool/Equipment 42.00
Sub Total (Labor+Tool/Equipment) -I 1442.00
Contractor Over head 15% of I 216.30
Total rate per m3 1658.30

d. Medium rock
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 4.00 700.00 2800.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 2800.00
2.00 Tools / Equipment
Picks, Shovels, Kodalo,
Doko/Baskets/Wheel Barrows, 84.00
Crowbars
Sub Total Tool/Equipment 84.00
Sub Total (Labor+Tool/Equipment) -I 2884.00
Contractor Over head 15% of I 432.60
Total rate per m3 3316.60

e. Hard rock (chiseling, wedging, tempering, etc)


Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 17.00 700.00 11900.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 11900.00
2.00 Tools / Equipment
Picks, Shovels, Kodalo,
Doko/Baskets/Wheel Barrows, 357.00
Crowbars
Sub Total Tool/Equipment 357.00
Sub Total (Labor+Tool/Equipment) -I 12257.00
Contractor Over head 15% of I 1838.55
Total rate per m3 14095.55

Excavation in Roadway , drain and foundation of structure including removal and satisfactory disposal of all materials
up to a lead of 50m along the lead route using excavator or breaker and finishing manually wherever and to what extent
necessary

Manual Equipment
Manual Equipment
Excavation Excavation
S.No Description Excavation Excavation
(5%) (95%)

NRs NRs NRs NRs


1 Ordinary soil 414.58 93.15 20.73 88.49
2 Hard soil 497.49 93.15 24.87 88.49
3 Ordinary rock 1658.30 93.15 82.92 88.49
4 Medium rock 3316.60 557.75 165.83 529.86
5 Hard rock 14095.55 839.50 704.78 797.53
Note: Contracter Over head of 15% is included in Equipment Excavation Cost

Norms Serial No: 10


Clause No.: 2-5
Construction of roadway in embankments and miscellaneous backfilling areas with approved material excluding the
excavation and transportation with initial lead of 50 m.

Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 0.25 700.00 175.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 175.00
2.00 Tools / Equipment
Picks, Shovels, Doko/Baskets,
5.25
Wheel barrows
Sub Total Tool/Equipment 5.25
Sub Total (Labor+Tool/Equipment) -I 180.25
Contractor Over head 15% of I 27.04
Total rate per m3 207.29

VI RETAINING WALLS & STRUCTURES:

Norms Serial No: 38


Clause
the workNo.: 8 the specifications and drawings. It includes full compensation for using specially dressed stones on
as per
the face of wall with batter and makes provisions for weep hole as necessary

A. Un-coursed Rubble Masonry


a) In dry
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 1.50 700.00 1050.00
Skilled md 0.50 960.00 480.00

Sub Total Labor 1530.00


2.00 Material
Rubble stone m3 1.10 2363.76 2600.14
Sub Total Material 2600.14
3.00 Tools and equipment 123.90
Sub Total Tool/Equipment 123.90
Sub Total (Labor+Material+Tool/Equipment) -I 4254.04
Contractor Over head 15% of I 638.11
Total rate per m3 4892.15

b) In 1:3 cement sand mortar


Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 3.24 0.00 0.00
Skilled md 1.50 670.00 1005.00

Sub Total Labor 1005.00


2.00 Material
Cement(53 grade) kg 148.00 16.00 2368.00
Sand m3 0.44 3210.48 1412.61
Block Stone m3 1.10 2363.76 2600.14
Sub Total material 6380.75
Total for RBG works 7385.75
3.00 Tools and equipment
Sub Total Tool/Equipment 0.00
Sub Total (Labor+Material+Tool/Equipment) -I 7385.75
Contractor Over head 15% of I 1107.86
Total rate per m3 8493.61

c) In 1:4 cement sand mortar


Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 3.24 700.00 2268.00
Skilled md 1.50 960.00 1440.00

Sub Total Labor 3708.00


2.00 Material
Cement(53 grade) kg 116.00 16.00 1856.00
Sand m3 0.47 3210.48 1508.93
Block Stone m3 1.10 2363.76 2600.14
Sub Total material 5965.06
Total for RBG works 9673.06
3.00 Tools and equipment
Sub Total Tool/Equipment 0.00
Sub Total (Labor+Material+Tool/Equipment) -I 9673.06
Contractor Over head 15% of I 1450.96
Total rate per m3 11124.02

VII GABION WORKS


Norms Serial No: 44.1
Clause No.: 17-1.4,17-5 and 17-6
Item : Fabrication of Gabion boxes of Size 3 m x1 mx 1 m having mesh size (100 x 120)mm including rolling, cutting and weaving( Mesh wire
10 SWG, selvedge wire 7 SWG, Binding wire 12 SWG, all heavy coated)
b) Box size 3m*1m*1m
SNo Description of works Unit Quantity Rate Amount
1.00 Labour
Unskilled m-d 0.28 700.00 127.00
Skilled m-d 0.57 960.00 337.35
Sub Total Labor 464.35
2.00 Material
selvedge wire -7 SWG Kg 3.88 105.00 407.40
Mesh wire -10 SWG Kg 33.43 100.00 3343.00
Sub Total Material 3750.40
3.00 Tools and equipment 126.44
Sub Total Tool/Equipment 126.44
Sub Total (Labor+Material+Tool/Equipment) -I 4341.19
Contractor Over head 15% of I 651.18
Total rate per Box 4992.37
b) Box size 2m*1m*1m
SNo Description of works Unit Quantity Rate Amount
1.00 Labour
Unskilled m-d 0.20 700.00 140.00
Skilled m-d 0.39 960.00 374.40
Sub Total Labor 514.40
2.00 Material
selvedge wire -7 SWG Kg 2.88 100.00 288.00
Mesh wire -10 SWG Kg 23.43 90.00 2108.70
Sub Total Material 2396.70
3.00 Tools and equipment 87.33
Sub Total Tool/Equipment 87.33
Sub Total (Labor+Material+Tool/Equipment) -I 2998.43
Contractor Over head 15% of I 449.76
Total rate per Box 3448.20

c) Box size 1.5m*1m*1m


SNo Description of works Unit Quantity Rate Amount
1.00 Labour
Unskilled m-d 0.15 700.00 105.00
Skilled m-d 0.28 960.00 268.80
Sub Total Labor 373.80
2.00 Material
selvedge wire -7 SWG Kg 2.09 100.00 209.00
Mesh wire -10 SWG Kg 17.04 90.00 1533.60
Sub Total Material 1742.60
3.00 Tools and equipment 63.49
Sub Total Tool/Equipment 63.49
Sub Total (Labor+Material+Tool/Equipment) -I 2179.89
Contractor Over head 15% of I 326.98
Total rate per Box 2506.88

Norms Serial No: 44.2


Clause No.: 17-1.4,17-5 and 17-6
Assembling of Gabion box and placing them in position including stretching, binding them together and tying down leads binding wire 12 SWg

Work : Box size 2m*1m*1m


SNo Description of works Unit Quantity Rate Amount
1.00 Labour
Unskilled m-d 0.09 700.00 63.00
Skilled m-d 0.00 960.00 0.00
Sub Total Labor 63.00
2.00 Material
GI wire -12 SWG Kg 0.95 100.00 95.00
Sub Total Material 95.00
3.00 Tools and equipment 4.74
Sub Total Tool/Equipment 4.74
Sub Total (Labor+Material+Tool/Equipment) -I 162.74
Contractor Over head 15% of I 24.41
Total rate per Box 187.15

Work : Box size 1.5m*1m*1m


SNo Description of works Unit Quantity Rate Amount
1.00 Labour
Unskilled m-d 0.07 700.00 49.00
Skilled m-d 0.00 0.00 0.00
Sub Total Labor 49.00
2.00 Material
GI wire -12 SWG Kg 0.70 100.00 70.00
Sub Total Material 70.00
3.00 Tools and equipment 3.57
Sub Total Tool/Equipment 3.57
Sub Total (Labor+Material+Tool/Equipment) -I 122.57
Contractor Over head 15% of I 18.39
Total rate per Box 140.96
Norms Serial No: 45
Clause No.: 17-1.4,17-5 and 17-6
Packing and filling of gabion crates with rubble stones

SNo Description of works Unit Quantity Rate Amount


1.00 Labour
Unskilled m-d 0.75 700.00 525.00
Skilled m-d 0.30 960.00 288.00
Sub Total Labor 813.00
2.00 Material
Stones m3 1.10 2363.76 2600.14
Sub Total Material 2600.14
3.00 Tools and equipment 102.39
Sub Total Tool/Equipment 102.39
Sub Total (Labor+Material+Tool/Equipment) -I 3515.53
Contractor Over head 15% of I 527.33
Total rate per m3 4042.86

VIII CONCRETING
Norms Serial No: 40
Clause No.: 10
drawing and as directed by engineer. It also includes all devices for keeping reinforcement in approved position and jointing as
per approved method with due allowance for wastage overlaps spacers brand annealed steel bar for binding.

Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 7.00 700.00 4900.00
Skilled md 7.00 960.00 6720.00
Sub Total Labor 11620.00
2.00 Material
Reinforcement bars MT 1.05 84000.00 88200.00
Binding wires MT 0.01 92.00 0.92
Sub Total Material 88200.92
3.00 Tools and equipment 2994.63
Sub Total Tool/Equipment 2994.63
Sub Total (Labor+Material+Tool/Equipment) -I 102815.55
Contractor Over head 15% of I 15422.33
Total rate per MT 118237.88

Norms Serial No: 41


Clause No.: 11
curing and all other incidental required to produce concrete of specified strength as per specifications. The rate includes the works
of making fixing and removing all centres and forms required for the works

a) M 10 Grade (1:3:6 mix by volume)


Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 4.00 700.00 2800.00
Skilled md 1.00 960.00 960.00
Sub Total Labor 3760.00
2.00 Material
Sand m3 0.47 3210.48 1508.93
Aggregates
-40mm m3 0.65 3351.60 2178.54
-20mm m 3
0.24 3351.60 804.38
Cement Kg 220.00 16.00 3520.00
Wood for form works m 3
0.33 50862.00 16784.46
Sub Total Material 24796.31
3.00 Tools and equipment 856.69
Sub Total Tool/Equipment 856.69
Sub Total (Labor+Material+Tool/Equipment) -I 29413.00
Contractor Over head 15% of I 4411.95
Total rate per m3 33824.95
b) M 15Grade (1:2:4 mix by volume)
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 4.06 700.00 2842.00
Skilled md 1.00 960.00 960.00
Sub Total Labor 3802.00
2.00 Material
Sand m3 0.44 3210.48 1412.61
Aggregates
40 mm m3 0.52 3351.60 1742.83
20 mm m3 0.22 3351.60 737.35
10 mm Kg 0.11 3104.64 341.51
Cement kg 320.00 16.00 5120.00
Wood for form works m3 0.33 50862.00 16784.46
Sub Total Material 26138.77
3.00 Tools and equipment 898.22
Sub Total Tool/Equipment 898.22
Sub Total (Labor+Material+Tool/Equipment) -I 30838.99
Contractor Over head 15% of I 4625.85
Total rate per m3 35464.84

b) M 20 Grade (1:1.5:3 mix by volume)


Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 5.12 700.00 3584.00
Skilled md 1.00 960.00 960.00
Sub Total Labor 4544.00
2.00 Material
Sand m3 0.42 3210.48 1348.40
Aggregates
20 mm m3 0.57 3351.60 1910.41
10 mm m 3
0.29 3104.64 900.35
Cement Kg 400.00 16.00 6400.00
Wood for form works m 3
0.33 50862.00 16784.46
Sub Total Material 27343.62
3.00 Tools and equipment 956.63
Sub Total Tool/Equipment 956.63
Sub Total (Labor+Material+Tool/Equipment) -I 32844.25
Contractor Over head 15% of I 4926.64
Total rate per m3 37770.88

IX DRAINAGE WORKS:

Norms Serial No: 48


Clause No.: 17-2.2,17-2.3,17-5 and 17-6
Preparation of bedding for stone pitching with granular material. It includes all labor material and incidental required
to complete the work as per the specification

Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 1.00 700.00 700.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 700.00
2.00 Material
Granular material m3 1.10 2019.43 2221.37

Sub Total Material 2221.37


Total for RBG works 2921.37
3.00 Tools and equipment 87.64
Sub Total Tool/Equipment 87.64
Sub Total (Labor+Material+Tool/Equipment) -I 3009.01
Contractor Over head 15% of I 451.35
Total rate per m3 3460.36

Norms Serial No: 49


Clause No.: 17-2.2,17-5 and 17-6
Stone Pitching/Stone soling work on prepared granular bedding.

Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 1.25 700.00 875.00
Skilled md 0.00 960.00 0.00
Sub Total Labor 875.00
2.00 Material
Stone m3 1.10 2363.76 2600.14
Gravel/Spalls m3 0.25 2019.43 504.86
Sub Total Material 3104.99
Total of RBG Works 3979.99
3.00 Tools and equipment 119.40
Sub Total Tool/Equipment 119.40
Sub Total (Labor+Material+Tool/Equipment) -I 4099.39
Contractor Over head 15% of I 614.91
Total rate per m3 4714.30

Norms Serial No: 47


Clause No.: 15-5 and 15-6
Supplying , Laying fitting and fixing of RCC Hume Hume pipe. It include all operation required to complete the works
up to a trench depth of 2.2m below the ground level and the jointing of pipes with 1:2 cement sand mortar.
Diameter of pipe : 600 mm NP3
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 1.63 750.00 1218.75
Skilled md 0.25 1030.00 257.50
Sub Total Labor 1476.25
2.00 Material
Pipe m 7.50 6,200.00 46500.00
Cement Kg 15.00 16.00 240.00
Jute Kg 12.50 100.00 1250.00
Sand m3 0.02 3,210.48 64.21
Bitumen Kg 2.50 68.40 171.00
Sub Total Material 48225.21
3.00 Tools and equipment 1491.04
Sub Total Tool/Equipment 1491.04
Sub Total (Labor+Material+Tool/Equipment) -I 51192.50
Contractor Over head 15% of I 7678.88
Total rate for 7.5 m 58871.38
Total rate per RM 7849.52

Norms Serial No: 47


Clause No.: 15-5 and 15-6
Supplying , Laying fitting and fixing of RCC Hume Hume pipe. It include all operation required to complete the works
up to a trench depth of 2.2m below the ground level and the jointing of pipes with 1:2 cement sand mortar.
Diameter of pipe : 900mm NP-3
Rate in Amount in
S.No. Description Unit Quantity
NRs NRs
1.00 Labour
Unskilled md 3.38 750.00 2531.25
Skilled md 0.75 1,030.00 772.50
Sub Total Labor 3303.75
2.00 Material
Pipe m 7.50 10,734.00 80505.00
Cement Kg 30.00 16.00 480.00
Jute Kg 20.00 100.00 2000.00
Sand m3 0.05 3,210.48 160.52
Bitumen Kg 5.00 68.40 342.00
Sub Total Material 83487.52
3.00 Tools and equipment 2603.74
Sub Total Tool/Equipment 2603.74
Sub Total (Labor+Material+Tool/Equipment) -I 89395.01
Contractor Over head 15% of I 13409.25
Total rate for 7.5 m 102804.26
Total rate per RM 13707.24

Norms Serial No: 10.05 (DOR)


Clause No.: 8
Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in:

SNo Description of works Unit Quantity Rate Amount

1.00 Labour
Unskilled md 0.10 750.00 75.00
Skilled md 0.01 1030.00 10.30
Sub Total Labor 85.30
2.00 Material
Diesel Lit 0.12 85.40 10.42
Sub Total Material 10.42
3.00 Tools and equipment
Grader Hr 0.01 1,600.00 16.00
Roller Hr 0.02 500.00 8.50
Sub Total Tool/Equipment 24.50
Sub Total (Labor+Material+Tool/Equipment) -I 120.22
Contractor Over head 15% of I 18.03
Total rate per m3 138.25
Total rate per sqm 27.65

Norms Serial No: 12.01 (DOR)


Clause No.: 1201
Providing, laying, spreading, watering, leveling and compaction of natural sand gravel sub base grading as per table
12.1 of standard specification
SNo Description of works Unit Quantity Rate Amount

1.00 Labour
Unskilled md 0.04 750.00 30.00
Skilled md 0.0050 1,030.00 5.15
Sub Total Labor 35.15
2.00 Material
Diesel Lit 0.79 71.06 56.28
Sub base aggregate m3 1.28 1,870.00 2393.60
Sub Total Material 2449.88
3.00 Tools and equipment
Grader Hr 0.0220 85.00 1.87
Vibrating roller Hr 0.0220 800.00 17.60
Water browser Hr 0.0380 550.00 20.90
Loader Hr 0.0110 1,200.00 13.20

Sub Total Tool/Equipment 53.57


Sub Total (Labor+Material+Tool/Equipment) -I 2538.60
Contractor Over head 15% of I 380.79
Total rate per m3 2919.39

Norms Serial No: 12.06(DOR)


Clause No.: 1202

Providing, laying, spreading, watering, leveling and compaction of crusher run materials for base course lead up to
10m.

SNo Description of works Unit Quantity Rate Amount

1.00 Labour
Unskilled md 0.0200 750.00 15.00
Skilled md 0.0050 1,030.00 5.15
Sub Total Labor 20.15
2.00 Material
Diesel Lit 0.99 71.06 70.35
Base aggregate m3 1.20 2,963.52 3556.22
Sub Total Material 3626.57
3.00 Tools and equipment
Grader Hr 0.03 85.00 2.81
Vibrating roller Hr 0.03 1,600.00 52.80
Water browser Hr 0.03 1,200.00 39.60
Loader Hr 0.0110 550.00 6.05

Sub Total Tool/Equipment 101.26


Sub Total (Labor+Material+Tool/Equipment) -I 3747.98
Contractor Over head 15% of I 562.20
Total rate per m3 4310.18
Norms Serial No: 13.01 (DOR)
Clause No.:
Providing and1301/ 1302bituminous tack coat MC30/MC70 including cleaning the road surface using wire, brushes,
spraying
broom etc before applying prime coat. (@0.60lit/sqm)

SNo Description of works Unit Quantity Rate Amount

1.00 Labour
Unskilled md 0.0460 750.00 34.50
Skilled md 0.0030 1,030.00 3.09
Sub Total Labor 37.59
2.00 Material
Bitumen Lit 1.05 68.40 71.82
Kerosene Lit 0.10 85.40 8.54
Diesel Lit 0.275 85.40 23.48
Sub Total Material 103.84
3.00 Tools and equipment
Boiler Hr 0.0025 180.00 0.45
Sprayer Hr 0.0025 260.00 0.65
Air compressor Hr 0.0030 260.00 0.78
Sub Total Tool/Equipment 1.88
Sub Total (Labor+Material+Tool/Equipment) -I 143.31
Contractor Over head 15% of I 21.50
Total rate per litre 164.81

Norms Serial No: 13.03 (DOR)

Clause No.: 1301/ 1302


Providing and spraying bituminous prime coat MC30/MC70 including cleaning the road surface using wire, brushes,
broom etc before applying prime coat.

SNo Description of works Unit Quantity Rate Amount

1.00 Labour
Unskilled md 0.0460 750.00 34.50
Skilled md 0.0030 1,030.00 3.09
Sub Total Labor 37.59
2.00 Material
Bitumen Lit 1.05 68.40 71.82
Kerosene Lit 0.10 75.00 7.50
Diesel Lit 0.275 85.40 23.48
Sub Total Material 102.80
3.00 Tools and equipment
Boiler Hr 0.0025 180.00 0.45
Sprayer Hr 0.0025 260.00 0.65
Air compressor Hr 0.0030 250.00 0.75
Sub Total Tool/Equipment 1.85
Sub Total (Labor+Material+Tool/Equipment) -I 142.24
Contractor Over head 15% of I 21.34
Total rate per litre 163.58

Norms Serial No: 13.09 (DOR)


Clause No.: 1307 / 1308
Providing, mixing, laying and compaction of premixed carpet

SNo Description of works Unit Quantity Rate Amount

1.00 Labour
Unskilled md 4.50 750.00 3375.00
Skilled md 0.45 1,030.00 463.50
Sub Total Labor 3838.50
2.00 Material
Bitumen Lit 77.00 68.40 5266.80
Kerosene Lit 7.70 85.40 657.57
Aggregates cum 1.20 3,245.76 3894.91
Sub Total Material 9819.28
3.00 Tools and equipment
Sprayer Hr 0.50 260.00 130.00
Roller Hr 0.50 500.00 250.00

Sub Total Tool/Equipment 380.00


Sub Total (Labor+Material+Tool/Equipment) -I 14037.78
Contractor Over head 15% of I 2105.67
Total rate per m3 16143.45

Norms Serial No: 13.07 (DOR)


Clause No.: 1301 / 1305
Providing and laying sand seal (for 10sqm)

SNo Description of works Unit Quantity Rate Amount

1.00 Labour
Unskilled md 0.14 635.00 88.90
Skilled md 0.10 865.00 86.50
Sub Total Labor 175.40
2.00 Material
Bitumen Lit 6.60 68.40 451.44
Kerosene Lit 0.10 85.40 8.54
Diesel Lit 0.81 85.40 69.17
Fine Aggregates cum 0.12 3,210.48 385.26
Sub Total Material 914.41
3.00 Tools and equipment
Boiler Hr 0.04 250.00 10.00
Roller Hr 0.04 1,600.00 64.00
Sprayer Hr 0.01 1,200.00 12.00

Sub Total Tool/Equipment 86.00


Sub Total (Labor+Material+Tool/Equipment) -I 1175.81
Contractor Over head 15% of I 176.37
Total rate per sqm 1352.18

Norms Serial No: 13.10 (DOR)


Clause No.: 1307 / 1308
Providing, mixing, laying asphalt concrete with compaction

SNo Description of works Unit Quantity Rate Amount

1.00 Labour
Unskilled md 0.13 750.00 97.50
Skilled md 0.03 1,030.00 30.90
foreman md 0.01 750.00 7.50
Sub Total Labor 135.90
2.00 Material
Bitumen Lit 117.00 68.40 8002.80
cement t 0.022 1,600.00 35.20
Diesel Lit 10.45 85.40 892.41
Aggregates cum 1.20 2,998.80 3598.56
Sub Total Material 12528.97
3.00 Tools and equipment
Asphalt mixing plant Hr 0.044 2,500.00 110.00
Wheel Loader Hr 0.66 550.00 363.00
asphalt paver Hr 0.22 85.00 18.70
Tipper Trucks Hr 0.32 75.00 24.00
Steel tyred Roller Hr 0.55 1,600.00 880.00
Pneumatic Rollers Hr 0.55 500.00 275.00
Sub Total Tool/Equipment 1670.70
Sub Total (Labor+Material+Tool/Equipment) -I 14335.57
Contractor Over head 15% of I 2150.34
Total rate per m3 16485.91
TEMS

FY: 2075/76

cessary) having girth of

Remarks

uding the removal of trunk,

Unit : 1 no.

Remarks

Unit :1 no.

Remarks
Unit : 1 no.

Remarks

Unit : 1 no.

Remarks

Unit : 1 no.

Remarks
ary to complete the work. This
g the lead route.
Unit : 1 sqm

Remarks

33.17

astes to 10m
Unit : 1 cum

Remarks

ory disposal of all materials

Unit : 1 cum

Remarks
Unit : 1 cum

Remarks

Unit : 1 cum

Remarks

Unit : 1 cum

Remarks
Unit : 1 cum

Remarks

ry disposal of all materials


herever and to what extent
Unit : 1 cum

Average Rate

NRs
109.22
113.37
171.41
695.69
1502.30

ed material excluding the

Unit : cum

Remarks
ecially dressed stones on

Unit : cum

Remarks

Unit : cum

Remarks
Unit : cum

Remarks

cutting and weaving( Mesh wire

Unit : 1 Box
Remarks

Unit : 1 Box
Remarks
Unit : 1 Box
Remarks

down leads binding wire 12 SWg

Unit : 1 Box
Remarks

Unit : 1 Box
Remarks

Unit : m3
Remarks

ved position and jointing as


binding.
Unit : MT

Remarks
s. The rate includes the works

Unit : cum
Remarks

Unit : cum

Remarks
Unit : cum

Remarks

al and incidental required


Unit : m3

Remarks
Unit : m3

Remarks

red to complete the works


ent sand mortar.
Unit : 7.5 RM

Remarks
red to complete the works
ent sand mortar.
Unit : 7.5 RM

Remarks

10 to 20 cm) in:
Unit : m3

Remarks

base grading as per table


Unit : m3
Remarks

r base course lead up to

Remarks
ace using wire, brushes,

Unit : lit

Remarks

rface using wire, brushes,

Unit : lit

Remarks
Unit : m3

Remarks

Unit : m3

Remarks
135.22

Unit : m3

Remarks

You might also like