S Rate Amount
Description of Item Quantity Per Unit
No (Rs.) (Rs.)
1 Labour charges for Bailing out of water for earth work
excavation / Concrete for foundations below water level in
Sandy soils from 0.0m to 1.0m, etc complete for finished
item of work.
Labour Charges as per SSR 2017-18
1.00 Cum 349.00 1 Cum 349.00
S No 780, BMM-V.04
Add for MA @ 20% 0.20 349.00 69.80
418.80
Overheads&Contractors Profit @13.615% 0.13615 418.80 57.02
Rate per 1 Cum 475.82
Say 475.80