Civil Datas

S Rate Amount
Description of Item Quantity Per Unit
No (Rs.) (Rs.)
1 Labour charges for Bailing out of water for earth work
excavation / Concrete for foundations below water level in
Sandy soils from 0.0m to 1.0m, etc complete for finished
item of work.
Labour Charges as per SSR 2017-18
1.00 Cum 349.00 1 Cum 349.00
S No 780, BMM-V.04
Add for MA @ 20% 0.20 349.00 69.80
418.80
Overheads&Contractors Profit @13.615% 0.13615 418.80 57.02
Rate per 1 Cum 475.82
Say 475.80

2 Labour charges for Bailing out of water for earth work


excavation / Concrete for foundations below water level in
Sandy soils from 1.0m to 2.0m, etc complete for finished
item of work.
Labour Charges as per SSR 2017-18
1.00 Cum 542.00 1 Cum 542.00
S No 781, BMM-V.05
Add for MA @ 20% 0.20 542.00 108.40
650.40
Overheads&Contractors Profit @13.615% 0.13615 650.40 88.55
Rate per 1 Cum 738.95
Say 739.00

3 Labour charges for Bailing out of water for earth work


excavation / Concrete for foundations below water level in
other than Sandy soils from 0.0m to 1.0m, etc complete for
finished item of work.
Labour Charges as per SSR 2017-18
1.00 Cum 220.00 1 Cum 220.00
S No 777, BMM-V.01
Add for MA @ 20% 0.20 220.00 44.00
264.00
Overheads&Contractors Profit @13.615% 0.13615 264.00 35.94
Rate per 1 Cum 299.94
Say 299.90

4 Labour charges for Bailing out of water for earth work


excavation / Concrete for foundations below water level in
other than Sandy soils from 1.0m to 2.0m, etc complete for
finished item of work.
Labour Charges as per SSR 2017-18
1.00 Cum 260.00 1 Cum 260.00
S No 778, BMM-V.02
Add for MA @ 20% 0.20 260.00 52.00
312.00
Overheads&Contractors Profit @13.615% 0.13615 312.00 42.48
Rate per 1 Cum 354.48
Say 354.50