Professional Documents
Culture Documents
Saudi Aramco Inspection Checklist
Saudi Aramco Inspection Checklist
00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review Procedure - Hot Tap & Stopple Connection Installation
SAIC-L-2090 30-Apr-17 MECH-
(Per SAEP-311, 13 September 2009)
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIM
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA
No.
A General Requirements (See Notes 1, 2, 3)
Each Hot Tap & Stopple Connection Installation is Controlled from the design
phase through Completion utilizing the following requirements:
A) Latest Edition of SAEP-311 (Install. of Hot Tapped & Stopple Conns)
SAEP-311
A1 B) Materials are per latest approved edition of 02-SAMSS-006.
(Procedure)
Procedure details design package content
per SAEP-311. Procedure shall be approved prior to the
start of work by SA.
Procedure follows the sequence of operations outlined in SAEP-311 for HOT TAP
SAEP-311
A2 INSTALLATION for welded connections to pipe, pressure vessels and tanks while
(Procedure)
in service. See Attachment 1.
Procedure States: Personnel responsible for work are fully trained in use of
SAEP-311,
A5 procedure & shall be carefully supervised by experienced Engineers &
Section 1
Construction Supervisors during execution of HOT Work
Procedure references & has Attached the following Forms:
SAEP-311,
A6 See Attachment 1 for a complete list of Latest
Appendix A
Forms Req'd
NTRACTOR
PLANT NO.
TRAVEL TIME
MCO USE ONLY
WORK PERMIT REQUIRED?
RE-INSP DATE
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA
No.
Procedure ensures Documentation of Design Pkgs & Work Activities includes docs SAEP-311,
B2
& drawings listed in Section 12. Section 12
Procedure ensures Pressure Testing & Inspection Section includes all the checks SAEP-311,
B3
and requirements listed in Section 14. Section 14
SAEP-311,
C1
Para. 15.1.1
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA
No.
SAEP-311,
C2
Para. 15.1.2
SAEP-311,
C3
Para. 15.1.3
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA
No.
SAEP-311,
C4
Para. 15.1.4
SAEP-311,
C5
Para. 15.1.5
D MATERIAL RECEIVING & MATERIAL REQMTS (PROCEDURE SPECIFIC) ... Utilize Checklist SAIC-L-2092 with this Section
E DESIGN PACKAGE & DESIGN SPECIFICS (From Item A1) ... Note: Design Package "Content" is listed in Procedure.
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA
No.
Design Package: The initiating organization* shall prepare a design package for
each hot tap that will include fully dimensioned drawings, a materials list, Direct
SAEP-311,
E1 Charge Requisitions and welding procedures.
Para. 5.1
The design package shall be approved by Hot Tap Group.
SAPMT is the initiating Organization
Hot tap connections shall be designed for the Maximum Allowable Operating SAEP-311,
E2
Pressure for tapped equipment per applicable ASME code. Para. 9.1
The dimensions of the connection, the hot tap valve, and clearances shall be within
the limits specified for the hot tapping equipment to be used. Hot-Tap and Stopple SAEP-311,
E3
Unit should be contacted to provide this data prior to purchase of any fitting with an Para. 9.2
extended branch nipple.
The minimum valve bore shall be large enough to pass the cutter. The valve seat SAEP-311,
E4
lugs shall not restrict the opening. Para. 9.3
A tap equal to the nominal size of the header (such as required for stoppling of a
SAEP-311,
E5 pipeline) shall be made only when accurate positioning of the cutter can be
Para. 9.4
guaranteed.
In hot tap cases other than those for stoppling purposes, the cutter should be at SAEP-311,
E6
least one pipe size smaller than the pipe to be tapped. Para. 9.5
If the hot tap is to be used for stoppling the pipe, the hot tap crew shall take
measurements and mark the tapping location prior to welding of split tee to ensure
that the pipe out of roundness meets the tolerances in the following table:
SAEP-311,
E7
Para. 9.6
Storage Tanks: For atmospheric or low pressure hydrocarbon storage tanks, hot
tap connections shall be located at least 1 m (39 inches) below the liquid level
while welding or hot tapping is in progress.
SAEP-311,
E9 A) If the tank or vessel is in service during the welding or hot tapping
Para. 9.8
process, the operating organization must ensure that the liquid level
above the level of the weld or cut shall not be less than 1 meter.
B) Connections on tanks shall meet the requirements SAES-D-108.
F INSTALLATION & WELDING (HOT TAP & STOPPLE SAFEGUARDS & LIMITATIONS, ADDITIONAL DESIGN CHECKS)
Procedure ensures Restrictions are listed & steps are taken to assure that Work is SAEP-311,
F1
strictly controlled. Section 6
Procedure ensures Installation & Welding Section includes all the checks and SAEP-311,
F2
requirements per Section 13. Section 13
G Safety Requirements
SAEP-311,
G1 Procedure ensures Safety Requirements are identified and met.
Section 7
REMARKS: UPON AGREEMENT, THIS CHECKLIST & SAEP-311 in entirety may be used in lieu of a Procedure.
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DA
No.
NOTES: 1. Copy and paste as much of checklist into finished procedure as possible. SAEP-311 = Procedure = This Checklist
2. June 3 2008 Version of SAEP-311 has been utilized & referenced here (Pipeline Safety). Utilize latest edition regardless of date (Safety).
3. Quality Managers shall ensure the correct and thorough development of procedures & Design Packages using this checklist.
4. SAES-L-052 is no longer utilized for Hot Taps. SAEP-311 is MANDATORY. SAEP-310 requirements may also be mandatory in the event
that damage assessment & Pressure Piping Considerations come into the picture due to Inspection Findings (HIC Damage, etc).
5. Utilize SATR-NDE-2007 for HOT TAP UT REPORT (Appendix A4). UT Results shall be *current. *Utilize 30-day rule in Procedure.
REFERENCE DOCUMENTS:
1- SAEP-311 -- Installation of Hot Tapped & Stopple Connections, (01March 2013)
2- SAEP-310 -- Pipeline Repair and Maintenance (10 March 2012)
3- SAES-A-004 -- General requirements for Pressure Testing (30 Jan 2011)
4- SAES-D-008 -- Repairs, Alterations, and Re-rating of Pressured Equipment 30 June 2014.
5-SAES-W-010 -- Welding Requirements for Pressure Vessels 08 September 2012.
6-SAES-W-011 -- Welding Requirements for On-Plot Piping (16 December 2013)
7-SAES-W-012 -- Welding Requirements for Pipelines 08 September 2012.
8. SASD AB-036719- Sht-001-Rev-11--Reinforcement of Welded Branch Connections
9- 02-SAMSS-006 -- Hot Tap and Stopple Fittings, (6 September 2011)
NTRACTOR
RE-INSP DATE
NTRACTOR
RE-INSP DATE
NTRACTOR
RE-INSP DATE
tion
NTRACTOR
RE-INSP DATE
NTRACTOR
RE-INSP DATE
ty).
vent
Work Verified
Work Verified
Work Verified
Y = YES N = NO F = FAILED