Professional Documents
Culture Documents
National Cranberry Cooperative Case Answer 1
National Cranberry Cooperative Case Answer 1
National Cranberry Cooperative Case Answer 1
ANSWER 1:
Overtime costs were after control even after spending $200,000 for a fifth
Kiwanee dumper
The waiting time for the unloading the process fruit into the receiving plant is
too long which is upsetting for the growers as the trucks and the drivers leased
spent most of the time standing idle, waiting to unload
Inaccuracy of the colour grading process by the chief berry receiver. In 1995,
$1.50 per bbl premium paid for No. 3 (best) berries on about 450,000 bbls, but
later when they were used it was found that only half of them were No. 3,
others were mistakenly graded 2B
There are not enough holding bins for wet berries
ANSWER 2:
Dumping
3000
Holding
4500 3000
[BOTTLENECK]
1500 600
Separator
1200
Capacity Calculation
Dumping
No. of Kiwanee 5
dumpers
Avg. weight of berries 75 bbls
Avg. time taken for (7+8)/2=7.5
dumping
Total capacity 5*75*7.5=3000
Holding
Capacity for bins 1- 16*250=4000
16(dry)
Capacity for bins 17-24 8*250=2000
(wet or dry)
Capacity for bins 24- 3*400=1200
27(wet)
Destoning
No. of units 3
Capacity per unit 1500bbls/hr
Total destoning capacity 1500*3=4500 bbls/hr
De-chaffing
No of units (wet) 2
No. of units (dry) 1
capacity per unit 1500 bbls/hr
Total destoning capacity 1500*(2+1) = 4500
bbls/hr
Drying
No. of units 3
Capacity per unit 200 bbls/hr
Total drying capacity 200*3=600 bbls/hr (Bottle
Neck)
Separator
No. of units 3
capacity per unit 400 bbls/hr
Total separator capacity 400*3=1200 bbls/hr
ANSWER 4:
The trucks will be waiting after 7pm till 10.40pm to unload the berries.
ANSWER 5:
1. Addition of a dryer: From the capacity calculated at each step of the process,
drying wet berries is the bottleneck with the lowest capacity. If one extra dryer
is added:
As holding capacity of the bins is 3200 bbls, the additional inventory will be
accommodated and the waiting time will be reduced.
3. Add a light meter system for colour grading: In 1995, a loss of $337500 due to
shortcomings in the grading process as it couldn’t differentiate the berries of
grade 2B and 3. A new light meter system will cost $40000, will reduce losses
in long term while an additional maintenance resource will be required at
minimal costs to operate the equipment.
ANSWER 6:
8*75=600 barrels.
There won’t be any wait time for the trucks as the berries are unloaded as soon as the
trucks arrive at the plant.