ID Task Task Name Duration Start Finish Predecessors July August September October November

Mode 6/28 7/5 7/12 7/19 7/26 8/2 8/9 8/16 8/23 8/30 9/6 9/13 9/20 9/27 10/4 10/11 10/18 10/25 11/1 11/8 11/15
1 Food Management and Trading 86 days Fri 7/10/20 Fri 11/6/20
Building at Birtamod
2 Phase 1 5 days Sat 7/11/20 Fri 7/17/20
3 Preliminary Preparedness 2 days Sat 7/11/20 Mon 7/13/20
4 Literature Review 5 days Mon 7/13/20Fri 7/17/20 3SS
5 Inception Report Submission 3 days Thu 7/16/20 Mon 7/20/203FS+2 days
6 Data Collection 7 days Tue 7/21/20 Wed 7/29/20
7 Primary Data Collection 7 days Tue 7/21/20 Wed 7/29/205
8 Secondary Data Collection 7 days Tue 7/21/20 Wed 7/29/207SS
9 Phase 2 27 days Thu 7/23/20 Fri 8/28/20
10 Field Survey and Study 10 days Thu 7/23/20 Wed 8/5/20 8SS+2 days
11 Geotechnical Team Site Visit 5 days Mon 7/27/20Fri 7/31/20 10SS+2 days
12 Land Survey 5 days Thu 7/30/20 Wed 8/5/20 11SS+3 days
13 Soil sample collection for Soil 8 days Thu 7/30/20 Mon 12SS
investigation 8/10/20
14 Submission of Soil Test Report 14 days Tue 8/11/20 Fri 8/28/20 13
15 Phase 3 52 days Thu 8/6/20 Fri 10/16/20
16 Preparation of Architectural 20 days Thu 8/6/20 Wed 9/2/20 12
Planning of building
17 Structural Analysis of Building 16 days Tue 8/25/20 Tue 9/15/20 16SS+13 days
18 Preparation of Architectural 5 days Thu 8/20/20 Wed 16SS+10 days
Drawings 8/26/20
19 Preparation of Structural Drawings
7 days Wed 9/16/20Thu 9/24/20 17
20 Preparation of Electrical Drawings
7 days Thu 8/27/20 Fri 9/4/20 16SS+15 days
21 Preparation of Sanitary Drawings7 days Thu 8/27/20 Fri 9/4/20 20SS
22 Preparation of Structural Report6 days Fri 9/18/20 Fri 9/25/20 17FS+2 days
23 Preparation of Detailed 12 days Thu 10/1/20 Fri 10/16/20 22FS+3 days
Estimate of Project
24 Preparation of B.O.Q of the 7 days Mon Tue 22FS+5 days
Project 10/5/20 10/13/20
25 Draft Report Preparation 10 days Fri 10/9/20 Thu 10/22/2023SS+6 days
26 Draft Report Submission 2 days Fri 10/23/20 Mon 10/26/20 25
27 Comments on Draft Report 3 days Tue Thu 26
Collection 10/27/20 10/29/20
28 Preparation of Final Report 10 days Fri 10/30/20 Thu 11/12/2027
29 Final Report Submission 1 day Fri 11/13/20 Fri 11/13/20 28

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 7/5/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone