Professional Documents
Culture Documents
Method Statement For Concrete Works (Rev.01)
Method Statement For Concrete Works (Rev.01)
E mail :brauns@braunsegypt.com
Method Statement
For
Concrete Works Rev (01)
July 2020
Page 1 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
INDEX
1. INTRODUCTION 4
1.1 SCOPE OF WORK 4
2. CREW & EQUIPMENT 4
2.1 PERSONNEL 4
2.2 EQUIPMENTS 4
SAFETY REGULATION 4
2.3.1 Personal Protective Equipments (PPE) 4
2.3.2 House Keeping 4
2.3.3 Equipment Control 4
2.3.4 Fire Control 4
2.3.5 Traffic Control 4
2.3.6 Falling From Heights Control 5
3. DEFINITION OF PROCESS 5
3.1 Generals 5
3.2 Materials 5
3.3 Batching and Mixing 5
3.4 Form Works 6
3.4.1 Generals 6
3.4.2 Form Tiles 6
3.4.3 Cleaning and Oiling Forms 6
3.4.4 Removal of Forms 6
3.4.5 Form Finishes 7
3.5 Steel Reinforcement 7
3.5.1 General 7
3.5.2 Materials 7
3.5.3 Delivery and Storage 8
3.5.4 Fabrication 8
3.5.5 Installation 8
Page 2 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
Page 3 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
1. INTRODUCTION
1.1 Scope of Work
• The method statement is prepared for concrete work for "Construction of Lekela
2.1 Personnel
• See Attached organization chart. (Appendix A)
2.2 Equipments
• Truck Mixers
• Concrete Pump
• Concrete Vibrators
• Steel Reinforcement Cutting Machine.
• Steel Reinforcement Bending Machine.
• Survey Equipment
• Concrete Finishing Helicopter
• Wooden forms, Reinforced steel and all equipment should be arranged into groups
at appropriate place to gain safe and clean work place.
2.3.3 Equipment Control
• Access to be considered for truck and crane I equipments entry, Maximum speed for
vehicles is 20km/hr.
Page 4 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
3. DEFINITION O F PROCESS
3.1 General
This method statement covers the performance of all concrete work for the permanent structures in
accordance with the drawings and contract specification including but not limited to the supply of
concrete materials, the supply erection and removal of formwork, the supply fabrication and erection
of steel reinforcement, mix design, sampling and testing, batching, placing and compaction of plastic
concrete and curing and protection of the in-situ concrete.
3.2 Materials
• All materials will be selected as per the contract and it will be tested according to the test
plan approved by the owner.
• The contractor will design the mix for the used class of concrete through the independent
laboratory approved by the owner.
• The contractor could start using the design mix after getting the owner approval.
• All the tests for concrete will be performed as per the test plan approved by the owner.
Page 5 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
• Form work will be securely fastened to prevent loss of mortar and surfaces in contact
with concrete will be uniformly smooth and true with no local defects.
• Provision will be made for all required openings, offsets, recesses and embedded parts
and all exposed concrete edges or corners will have 25mmx25mm chamfers.
3.4.2 Form Tiles
• Form ties will not leave irregular holes or lead to repair marks that would
detract from the specified finishes.
• After removal of the forms embedded form ties will be cut not less than 3cm below
the formed face of the concrete except where finish class F1 is permitted in which
case form ties may be cut at the formed face.
• When the concrete is placed in the forms the inside surfaces of the forms will be free
from incrustations of mortar or other foreign materials.
• Before placing the formwork surfaces will be oiled with a formwork oil of a proprietary
brand approved by the owner
• Oiling of forms will not produce chemical deterioration or stains on the concrete
surfaces.
• Marking of excavation borders with adequate offset, excavate the whole area to the
levels mentioned in the approved drawings.
3.4.4 REMOVAL OF FORMS
• Formwork will not be disturbed until the concrete has hardened adequately.
• The minimum time prior to removal of formwork will be as specified in ACl347
or as directed by the owner on the basis of site records and test results.
• The contractor will give advance notice of intention to remove formwork and obtain
the approval of the owner before proceeding.
Page 6 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
• Finish F1 is a basic rough finish will be used for hidden buried surfaces or plastered
surfaces and will apply to formed surfaces for which no other finish is specified.
• Finish F2 shall be used for surfaces stated in the contract as fair face will
impart a dense even surface to the concrete with a regular pattern of horizontal and
vertical joints not less than 600mm a part unless otherwise specified or directed.
3.5.1 General
• This specifies requirements for the supply fabrication and installation of steel bar
reinforcement for cast in place concrete including all materials and measures
necessary to complete the reinforcement as shown on the drawings and specified
herein.
3.5.2 Material
• Bar reinforcement will conform to the relevant ASTM A615, Grade 60 or equivalent
• Wire fabric reinforcement will be in accordance with the requirement of ASTM A 185
or equivalent
• Bar supports, chairs and spacers will be selected by the contractor to maintain
specified concrete cover and avoid corrosion, subject to the owner’s approval.
Page 7 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
• Reinforcement bars will be delivered to the site properly colour coded or tagged
according to size and length. When tagged, means will be provided to maintain
identification after bundles are broken.
• Reinforcement bars will be stored clear of the ground and segregated by size, length
and type.
3.5.4 Fabrication
Sheared Length ± 25 𝑚𝑚
Depth of Truss bars − 12 𝑚𝑚
Stirrups, Ties and spirals ± 12 𝑚𝑚
Location of all other bends ± 12 𝑚𝑚
3.5.5 Installation
• Prior to installation all mild steel should be straight, therefore: -
1. Cast Footing or pedestal dimension (0.6m x 0.6m) with fixed angel in the
centre (profile 70 x 70 x 7mm)
2. Straightness the mild steel on the ground in lines.
3. Fix the mild steel in the angle that fixed in the pedestal.
4. Fix the other end of the line in the loader and start pulling until the line be
straight.
• Prior to installation all loose mill scale, rust, oil, paint and any other coating which
would destroy or reduce bond between steel and concrete will be removed.
• All steel reinforcement will be installed positively secured and supported in strict
accordance with the approval drawings and bending schedules. Placing tolerances
for reinforcement shall be in accordance with ACI 377.
Page 8 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
• All water, wood scraps and other debris will be removed from areas where
concrete is to be placed and the areas thoroughly cleaned to ensure proper
placement and bonding of the concrete.
• Forms will be oiled and sub-grades damp but not wet, when concrete is placed.
Page 9 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
• Pneumatic placing and pumping of concrete may only be used with the approval of
the owner. In such a case discharge lines will be horizontal or inclined upwards. The
discharge end will not be more than 3m from the point of placement and shall supply
a continuous stream of concrete without air pockets. Aluminium piping will not be
used.
• During hot weather special precautions as directed or approved by the owner will be
taken to ensure that the temperature of concrete when it is placed does not exceed
30 degrees centigrade.
3.6.3 COMPACTION
• Concrete will be compacted by mechanical vibrators electrically or pneumatically
driven.
• Immersion vibrators will operate when fully immersed at speeds of not less than 7000
impulses per minute for vibrating heads of less than 1 cm diameter and 6000impulses
per minute for heads 10cm or greater in diameter. They will be slowly immersed and
withdrawn vertically at spacing of 30cm to 50cm with vibration periods of 10 to 15
seconds for each penetration and will penetrate into the layer below.
• Vibrators will not come into contact with reinforcement or embedded parts.
3.6.4 CURING
• Concrete surfaces shall be kept continuously moist for at least 14 days after placing
and until the concrete temperature produced by heat of hydration of the cement
has peaked and fallen at least 1 Centigrade.
• Initial curing of exposed surfaces shall be performed by atomized water spray
positioned so that all surfaces to be cured are constantly moist or by a continuous
layer of burlap kept constantly wet.
• Hand sprinkling shall not be used except in conjunction with the burlap alternative.
• Forms capable of moisture loss such as plywood forms will be regularly sprinkled with
water to avoid loss of moisture from formed surfaces of the concrete.
• A curing compound complying with ASTM C309 may be used after getting the owner
approval and will be applied in strict accordance with the manufacturer's
recommendations.
Page 10 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
3.6.5 JOINTS
• Where shown on the drawings or directed by the owner, construction joints shall be
provided and preparation for these shall be in accordance with the section 5.2.3.5.12
of the contract.
• Where the contractor proposes additional construction joints he will first submit
drawings and obtain the approval of the owner.
• Expansion joints will be constructed only at the locations and in accordance with the
details shown on the drawings and approved by the owner.
• Expansion joints in slabs and beams shall be fitted with metal angles at all corners.
3.6.6 FINISHES
• Finishes for formed surfaces shall be class F1 or F2 as specified in the item
3.4.5 where abrupt irregularities mean offsets or fins caused by displaced forms and
gradual irregularities shall be deviations from a plane surface measured with a
template 1.5m long.
• Finishes for unformed surfaces will be class U1 or U3 for which irregularities shall be
defined as above except that gradual irregularities shall be measured with a template
3.0m long.
• Finish U1 will be achieved by screeding concrete surfaces to the required slopes and
grades and removing gradual irregularities exceeding ±1 mm
• Finish U3 will be achieved by screeding, mechanical, floating and trowelling concrete
surfaces to the required slopes and grades removing gradual irregularities exceeding
±6mm and finishing edges and joints with edging tools.
• Where shown on the drawings or directed by the owner special architectural concrete
finishes shall be provided as specified in Architectural Work, Technical Specifications of
this document.
Page 11 of 12
BRAUNS EGYPT
In front of 34 saint gieni St. Roushdy
E mail :brauns@braunsegypt.com
3.6.7 TOLERANCES
• The lines and levels for concrete structures will be achieved to within the following
tolerances:
• Any concrete structure which does not comply with the above tolerances will
be repaired as specified or removed and reconstructed if so directed by the owner.
3.6.8 REPAIR OF DEFECTS
• The contractor will submit proposals for the repair of defects the extent of which will
be clearly marked on the concrete surface, in accordance with the USSR Concrete
Manual.
• All materials and procedures will be subject to approval by the owner on a step by step
basis.
• Honeycombed areas will be cut back to sound concrete and where necessary the depth
of cutting will be increased but will not result in partial exposure of reinforcement.
• Edges of repaired areas will be undercut and all friable materials removed using a sharp
chipping tool.
• Wherever possible repairs will be carried out while the concrete is still green and curing
will be interrupted for the shortest time and smallest area practicable. Materials and
procedures specified or directed for repairs may include use of proprietary non shrink
grout; epoxy or latex based bonding agents, epoxy compounds and cementious grout,
mortar and concrete.
Page 12 of 12