Professional Documents
Culture Documents
Off Grid Professional Design
Off Grid Professional Design
Off Grid Professional Design
Lamp 460 36 8
Air condition 10 1150 4
Computer 10 210 5
Ceiling fan 1 75 4
Printer 1 550 2
Extra 1 500 4
31.285
192380
192.38
System Detail
Total energy demand(Wh) 192380
System DC voltage (V) 120
PSH 5.73
Module
Pmax 310
Vmp 36
Imp 8.33
Voc 45.1
Isc 8.95
Price ($) 106
Array sizing
AC sub system efficiency 0.82935
DC daily load demand (Ah) 2512.9519
Module derating factor 0.9025
Module output (Ah) 43.077137
NO of parallel module 58.336094 59
No of series module 3.3333333 4
Total module 236
System detial Battery sizing
Total energy demand (Wh) 192380 Battery capacity (Ah)
System Dc voltage 120 NO of battery in parallel
Backup (Day) 3 NO of battery in series
DOD 0.7 Total NO of Battery
Derating factor 0.85
Rate factor 1.8
Battery
Voltage 12
Capacity (Ah) 1200
Price ($) 120
ttery sizing
4490.6629
3.7422191 4
10 10
40
IN
Sub array 1
NO of parallel module 30
Between Inverter& Load
No of series module 4
Total module 120
Sub array 1
NO of parallel module 29 Location
No of series module 4
String
Total module 116
Between array& Inverter
sub array 1-2
Name Itrip
Fuse (P) 20 A
Between Inverter& Load
Isolator DC 500 A
IsolatorAC 500 A
Sub array 1
Protection & Disconnection Description Protection & Disconnection Device Guidelines
Fult Fuse 1.5*Isc<Itrip<2.4*ISC
Sub array 1
Protection & Disconnection Description Protection & Disconnection Device Guidelines
Fult Fuse 1.5*Isc<Itrip<2.4*ISC
402.75
644.4
Itripe
13.425
21.48
389.325
622.92
389.325
622.92
Module Location
Pmax 310 String cable
Vmp 36 Array cable
Imp 8.33 AC cable
Voc 45.1
Isc 8.95
NO of parallel module 30
No of series module 4 Cable mark
Total module 120 N
Y
Y
NYY
مسی
عایقPVC
Cover PVC
Protection size
Rated trip current of the fault current prodection
Rated trip current of the fault current prodection
Rated trip current of the fault current prodection
Name Quanity Price( $/Panel)
PV panel 236 217
Battery 100 235
Inverter 2 1000
Cabling&Wh meter&SOS prodection 5% total cost
Maintenance 1% total cost
Replacement Period Total cost for firest period($)
1 51212 Interest rate (%)
5 23500 inflation rate (%)
2 2000 life time of PV panel (year)
5% total cost 3835.6
1% total cost 805.476
Name
X ($) for inverter after 12 year
21384.32
19459.11
17707.23
16113.07