Professional Documents
Culture Documents
Automatic Coordination of Protection Devices in Distribution System
Automatic Coordination of Protection Devices in Distribution System
com
Abstract
Among the several components of distribution systems, protection devices present a fundamental importance, since they aim at keeping the
physical integrity not only of the system equipment, but also of the electricians’ team and the population in general.
The existing tools today in the market that carry out the making of protection studies basically draw curves, and need direct user’s interference
for the protection devices adjustment and coordination analyses of selectivity, being susceptible to the user’s mistakes and not always considering
the best technical and economical application.
In Brazil, the correct application of the protection devices demand a high amount of time, being extremely laborious due to the great number of
devices (around 200 devices), besides the very dynamic behaviour of distribution networks and the need for constant system expansion.
This article presents a computational tool developed with the objective of automatically determining the adjustments of all protection devices in
the distribution networks to obtain the best technical application, optimizing its performance and making easier protection studies.
© 2007 Elsevier B.V. All rights reserved.
Keywords: Optimization; Protection and switching equipments; Protection coordination and distribution networks
0378-7796/$ – see front matter © 2007 Elsevier B.V. All rights reserved.
doi:10.1016/j.epsr.2007.10.004
L. Comassetto et al. / Electric Power Systems Research 78 (2008) 1210–1216 1211
Table 2
Selectivity between fuse elements
Table 3
First adjustment
Initial node Final node Type ϕr βr Load [A] Fuse
0 1 Dj 1 – 16.94 –
1 2 FU 2 1 11.29 10K
2 3 L 3 2 9.41 –
3 4 FU 4 3 3.76 6K
4 5 L 5 4 1.88 –
3 6 FU 6 3 3.76 6K
6 7 FU 7 6 1.88 6K
1 8 FU 8 1 3.76 6K
8 9 FU 9 8 1.88 6K
of protection devices with the purpose of reducing the number of 2nd Stage: Eq. (2) refers to the annual estimate for branches
devices in series in the critical area allowing the use of elements protected by protection devices.
with slower fusion times and making selectivity viable with the n
protection of the substation and/or distribution reclosers. This S2 = (ωo · EPf )SEPf · (τdes + τloc + τman ) (2)
algorithm takes into account the minimization of the relation f =1
between the expected value of interrupted power by protec-
tion device or interrupted consumers, according to the algorithm ωo is the rate of faults per network kilometer, EP the accumulate
requested by the user. branch of the protection device, SEP the power interruption by
The software considers the historical database of the hap- the protection device, τ des the average time of dispatch, τ loc
pened interruptions of the system in study. The considered data the average time of traveling and τ mar is the average time of
is: maintenance.
3rd Stage: Eq. (3) refers to the annual estimate for branches
after switching equipment protected by protection equipment
The Fault Rate [ωo ], is defined as being the number of defects (cutouts and reclosers).
happened by the total number of network kilometers.
n
The average time of dispatch [τ des ] defined as the interval
S3 = (ωo · EMf )SEPf (τdes + τloc )
between the records of the complaint of lack of power by the
f =1
client to the Call Center, until the start time to dispatch the
n
electricians’ crew.
The average time of traveling [τ loc ] defined as the interval + (ωo · EMf )SEMf (τman ) (3)
between the start of traveling until the time the electricians f =1
crew locates the fault. ωo is the rate of faults per network kilometer, EM the accumulate
The average time of maintenance [τ man ] is defined as the branch of the switching equipment, SEP the interrupted power
interval between the fault location and power supply reestab- by the protection device the back of the switching equipment,
lishment. SEM the interrupted power by the switching equipment, τ des the
average time of dispatch, τ loc the average time of traveling and
The algorithm proposed presents three parts of calculation. τ man is the average time of maintenance.
1st Part: Through the topology algorithm, one obtains the With the sum of all three stages, it is possible to determine
accumulated power or the accumulated number of consumers in the initial interrupted power estimate of the system [WT ].
each breach, defined as [SSE ], [SEP ] and [SEM ]. WT = S1 + S2 + S3 (4)
2nd Part: At this part the switching branches are definite
as switching and protection equipments. The interpretation The ASD determines the impact on the interrupted power
of the network path by the topology algorithm determines estimate, inserting and rearranging or removing the switching
the switching and protection equipments in series, the length and/or protection equipments in the system verify the variation
of the network accumulated from each equipment and the the initial interrupted power.
branch of the network protected by protection devices, as Through this algorithm it is possible to determine the impor-
they are responsible for interrupting faults happening includ- tance of each protection and switching devices to the system.
ing from the switching equipments, defined as [SE ], [EP ] and The interaction among the methodologies described in Sec-
[EM ]. tions 2–4 can be visualized through the flowchart in Fig. 7.
3rd Part: At this third part a local optimization evaluation The optimization algorithm is demonstrated in a constituted
is done for each device tested in three parts of calculation: the system of seven branches and seven transformers with the power
first part corresponding to faults in the branch protected by the defined in 150 kW for transformer, 1 km branch length, 13.8 kV
feeder breaker, plus the second part corresponding to faults in voltage of operation and Fault Rate equal to 1 fault a year.
the branches protected by each protection device, plus the third Re-establishment time: τ des = 10 min; τ loc = 15 min and
stage for faults in the switching device branches interrupted by τ man = 30 min.
protection devices being isolated by that switching device after If we observe Fig. 8 it is easy to verify which protection
that. devices should act in case of defects in each one of the branches.
1st Stage: Eq. (1) refers to the annual estimate for branches It is simple to visualize the isolate areas as well (Table 4).
protected by the over-current relays (breaker feeders). The representation of the load flow can be visualized in
Table 5.
S1 = [(ωo · SE ) · SSE · (τdes + τloc + τman )] (1) After that, initial estimated interrupted energy calculations
are carried out on the original system:
1st Stage: Estimate of interrupted energy for defects in the
ωo is the rate of faults per network kilometer, SE the accumulate branches protected by the substation breaker (Eq. (1)).
branch of the substation breaker, SSE the power supplied by the
feeder, τ des the average time of dispatch, τ loc the average time [(1 · 1) · 1051.8 · (10 + 15 + 30)]
Wo = = 964.15 kVA/h
of traveling and τ man is the average time of maintenance. 60
1214 L. Comassetto et al. / Electric Power Systems Research 78 (2008) 1210–1216
Table 5
Load flow
Initial node Final node Type ϕr βr S [kV A] Load [A] Voltage [kV]
Fig. 9. Example.
WT = 2672.9 V Ah
Based on the initial estimate of interrupted energy, it is possi-
Fig. 8. System example.
ble to test the effect of the site removal for protection equipment,
analyzing its impacts on the reliability of the system.
The removal test of the device is demonstrated in the branch
2nd Stage: Estimate of interrupted energy for defects in the 6–7 (Fig. 9).
branches protected by the protection devices (fused cutouts and With the removal of the cutout in the branch 6–7, there is an
reclosers) (Eq. (2)). increase of the area protected by the cutout of the branch 1–6
(Table 6).
[(1 · 2) · 601.9 · (10 + 15 + 30)]
WFU(1−2) = = 1103.48 V A/h The calculations impact of the cutout removal; of the branch
60 6–7 are shown here:
Table 4 Table 6
Accumulate branch for equipment Accumulate branch for equipment
Initial node Final node Type km ϕr βr Accumulated Initial node Final node Type km ϕr βr Accumulated
branches for device branches for device
0 1 Dj 1 1 – (0–1) = 1 0 1 Dj 1 1 - (0–1) = 1
1 2 FU 1 2 1 (1–2) + (2–3) = 2 1 2 FU 1 2 1 (1–2) + (2–3) = 2
2 3 L 1 3 2 – 2 3 L 1 3 2 (2–3) = 1
3 4 FU 1 4 3 (3–4) = 1 3 4 FU 1 4 3 (3–4) = 1
3 5 FU 1 5 3 (3–5) = 1 3 5 FU 1 5 3 (3–5) = 1
1 6 FU 1 6 1 (1–6) = 1 1 6 FU 1 6 1 (1–6) + (6–7) = 2
6 7 FU 1 7 6 (6–7) = 1 6 7 L 1 7 6 –
L. Comassetto et al. / Electric Power Systems Research 78 (2008) 1210–1216 1215
1st Stage: Estimate of energy interrupted for defects in the 5. Practical results
branch protected by the over-current relays (Eq. (1)).
The initial version of this software was used by two electrical
Wo = 964.15 kV A/h distribution companies, located in the southern of Brazil, for
2nd Stage: Estimate of energy interrupted for defects in the optimization and revision of adjustments—approximately
branches protected by the protection devices (fused cutouts and 22,183 protection devices in 462 feeders around
reclosers) (Eq. (2)) 12 months.
It is important to point that before the ASP software, the
WFU(1−2) = 1103.48 V A/h selectivity studies were carried out manually, taking on average
5 work days for conclusion. Nowadays with this tool, the average
WFU(3−4) = 96.25 V A/h time is only 30 min (Fig. 10).
Besides, it is stood out that ASD presents advantage in rela-
WFU(3−5) = 96.25 V A/h tion to the existent similar software in the market, because it was
prepared for the Companies reality.
WFU(1−6) = 550.55 V A/h The objective for the development of this software was to
create methodologies and algorithm for the optimization and
use of switching and protection devices in distribution systems
WT = 2810.68 V Ah that will result in useful and reliable tools of easy application
Table 7 is obtained after accomplishing similar analysis in for electrical energy company.
other devices. It is important to remark that the program developed was
It is possible for the software ASP, based on every importance prepared to meet the needs of the dealerships, according to
of the fused cutout, to remove the switches of less importance, their predefined criteria of protection and reliability. It benefited
making possible the coordination between the over-current pro- the areas of operation, planning and maintenance with special
tection of feeder and the distribution reclosers with the fused emphasis on the reliability of electrical energy supply associated
cutout. to the operational safety of the system.
Table 7
Summary References
Initial node Final node Type W [kV A/h] Priority of removal [1] J.A. Cipoli, Engenharia de Distribuição, Qualitymark, Rio de Janeiro, 1993.
0 1 Dj – – [2] E.J. Robba, Introdução a sistemas elétricos de potência: componentes
1 2 FU 3497.72 4 simétricas, Forense, São Paulo, 1972, 344 pp.
2 3 L – – [3] N. Kagan, R.N. Adams, Computational decision support system for electrical
3 4 FU 3128.39 2 distribution system planning, in: Proceedings of Computer System and Soft
3 5 FU 3128.39 2 Engineering Conference, 1992, pp. 133–138.
1 6 FU 3361.78 3 [4] A.L. König, D.P. Bernardon, L.N. Canha, V.A. Popov, Modelagem das Cur-
6 7 FU 2810.67 1 vas de Carga dos Consumidores de um Sistema de Distribuição, in: CPFL
Evolução—1◦ Seminário Técnico, Campinas, SP, 2002.
1216 L. Comassetto et al. / Electric Power Systems Research 78 (2008) 1210–1216
[5] V.A. Popov, P. Ekel, S. Ansuj, Node load modelling and distribution system Luciane Neves Canha was born in Santa Maria, Brazil on the 16th of March
state estimation using the heuristic approach, in: Proceedings of the Inter- 1971. She received her Dr. Eng. degree from Federal University of Santa Maria,
national Symposium on Electrical Power Engineering, Stockholm Power in 2004, and has been a professor of electrical engineering at Federal University
Technology, June 1995, pp. 294–299. of Santa Maria, since 1997. Her research interests include distribution system
analysis, planning and operation, distributed generation and renewable energy.
Lorenzo Comassetto was born in Porto-Alegre, Brazil, on the 4th of October
1974, and currently is a doctorate student in electrical engineering of the Federal Alzenira da Rosa Abaide was born in Santa Maria, Brazil. She received Bach-
University of Santa Maria, Brazil, after working for 9 years in Operation of elor degree, M.S. and Dra . in electrical engineering from Federal University of
Electric Systems, and has been a member of IEEE since 2004. Santa Maria. She worked as engineer from 1986 to 1988 in State Company of
Electric Energy. Since 1989 she has been working in Technology Center, Cen-
Daniel Pinheiro Bernardon was born in Santa Maria, Brazil on the 15th of ter of Studies in Energy and Environment, Power System Department of this
September 1977, and currently is a doctorate student in electrical engineering university. Her field and interested includes planning and operation in power
of the Federal University of Santa Maria, Brazil, after working for 6 years in system distribution. She is registered professional engineer in the state of Rio
Operation of Electric Systems, and has been a member of IEEE since 2004. Grande do Sul.