A - Excavation and Earth Work

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 6

BOQ FOR PROPOSED PART OF HOUSE FOR Mr.M.P.R.

SENARATHNA,
No. 469, DAHAM MAWATHA, MEEGODA.
Item Description Qty Unit Rate Amount
Rs cts
A - Excavation and Earth Work
Rate shall include for:
a) Excavation for foundation in any
materials except rook requiring blasting
part return filling and rammed and surplus
disposed of with in site as directed.
b) Filling under floors with ravelor other
approved quality of filling, spread,watered
and well rammed in 3’’ layers with
available earth.
c) Excavate trench for wall and
columns foundation. Payment for
planking and strutting will be made on
actual quantities of work executed.
Planking and strutting shall be carried out
only if specially instructed to do so by
the consultant.

A-1 Allow the provisional sum for necessary item nil


earth work directed by the Engineer.

A-2 Clearing the site of all growth roots and Sqrs nil
cutting top soil and foundation if any up
to 10’ - 0’’ beyond the outer walls of the
proposed building and carrying the waste
materials from the site and forming ground
level,

A-3 Excavation for walls and column 17.00 Cube 1,500.00 25,500.00
foundations not exceeding 5’ - 0’’ deep
commencing at formed level.

A-4 Filling under floors including levelling 10.50 Cube 1,750.00 18,375.00
watering and compacting in 3’’ layers
with available and selected at site.
Total carried to summary. 43,875.00

B - Concrete Work
Rate shall include for:
a) Mixing, depositing, handling & hoisting
in to position.
B) Racking, damping around
reinforcement including vibrating.
C) Curing as specified & stop pour
construction joint, etc.
1 : 3 : 6 ( 1 1/2’’) Cement Concrete in
followings.
B-1 Base of wall & column foundations 3’’ thick. 4.86 Sqrs 3,800.00 18,468.00

B-2 Dining, bed room 3 & 6, living,kitchen,stair case 5.60 Sqrs 3,550.00 19,880.00
& bath room 2 1/2"tk. Screde concrete
1 : 2 : 4 (3/4’’ ) RCC in followings.
including form work & rainforcement
B-3 Slab 4’’ thick at upper floor. 6.19 Sqrs 38,500.00 238,315.00
B-4 9’’ thick column footings in 9’’ x 9’’ in 0.24 Cube 24,500.00 5,880.00
columns.

B-5 Column size 9’’x9’’ in footing upto DPC level 0.34 Cube 35,200.00 11,968.00

B-6 Column size 9’’x9’’ in footing upto slab bottom level to 0.65 Cube 37,880.00 24,622.00

B-7 Beam size 9’’ x 12’’ in upper floor. 0.68 Cube 41,000.00 27,880.00

B-8 Beam size 9’’ x 9’’ in upper floor. 0.40 Cube 39,550.00 15,820.00

B-9 Stair case and associated landings 0.64 Cube 65,000.00 41,600.00
landing beam from ground level to upper floor
level

B - 10 Lintols size 9" x 6’’ 59.00 L.ft. 310.00 18,290.00

COMPOSITE CONSTRUCTION
B - 11 Installation of 2000 liters capacity PLASTISEL 01 item 48,000.00 48,000.00
water tank at top of the RCC concrete column.including
specification providing 50mm dia ball valve
with ball float and fittings and all other necessary
pipe work.

B - 12 Construction of 10'x5'x8' capacity Septic tank 1.00 item 45,000.00 45,000.00


and sockege pit including excavetion.
Total carried to summary. 515,723.00

C - Rubble Work
Rate shall include for :
a) Plumbing angles.
c) Setting and jointing.

C- 1 Random rubble masonary in cement, mortar 10.53 Cube 13,500.00 142,155.00


1 : 5 in walls foundations and curb wall
foundations.
Total carried to summary. 142,155.00

D - Block Work
Rate shall include for :
a) Plumbing angles.
b) Forming rebated reveals.
c) Square cutting and baking of joints for
plastering.

D- 1 6’’ thick clay block work in 1 : 5 cement mortar 17.00 Sqrs 16,300.00 277,100.00

Total carried to summary 277,100.00

E - Carpentry & Joinery


Rate shall include for :
a) All timber shall be specials class unless
other wise specified.
b) All labour in framing, hoisting, fixing in
position drilling for holes complete with all
necessary nails, spikes, screws etc.
c) All ironmongery shall be of oxidized
brass.
E-1 Supply & fix door type D2 size 3’ - 0’’X 8’-6" 25.50 Sqft 950.00 24,225.00
frame & panelled door sash with
4’’ X 3’’ timber frame. Rate shall include for
03 Nos 4’’ X 3’’ brass butt hinges and 01
No mortic type (English) door lock etc.

E-2 Supply & fix door type D1 size 3’ - 0’’X 7’-0" 02nos 42.00 Sqft 760.00 31,920.00
frame & panelled door sash with
4’’ X 3’’ timber frame. Rate shall include for
03 Nos 4’’ X 3’’ brass butt hinges and 01
No mortic type (English) door lock etc.

E-3 Supply & fix door type D3 size 2’ - 9’’X 7’-0" 19.25 Sqft 650.00 12,512.50
frame & panelled door sash with
4’’ X 3’’ timber frame. Rate shall include for
03 Nos 4’’ X 3’’ brass butt hinges and 01
No mortic type (English) door lock etc.

E-4 Supply & fix door type D5 size 2’ - 3’’X 6’- 9" 15.18 Sqft 650.00 9,867.00
PVC door

E-5 Window type W1-03 Nos. top decoreted plank with 108.00 Sqft 1,025.00 110,700.00
glazed window 4"x3" timber frame cl 1.
& 1" tk. Timber sash 1/8' tk. Clear glass 03
Nos. butt hinges casement srays pastners
etc.in ground floor

E-6 Window type W2-01 Nos. as above…………. 16.00 Sqft 950.00 15,200.00

E-7 Window type F-01 Nos. as above…………. 8.00 Sqft 658.00 5,264.00
Total carried to summary 189,224.50

F - Plaster work & other floor finishing


Rate shall include for :
a) Racking out joint of new brick work or
hacking new concrete work for key.
b) Forming internal & external angle & arises.
c) Making good ground pipes etc.

F -1 3/4’’ thick cement and sand 1 : 2 DPC 1.93 Sqrs 3,100.00 5,983.00
finished with 02 coats of hot tar & blinded
with sand.

F -2 5/8’’ thick plaster in cement lime mortar 10.00 Sqrs 3,400.00 34,000.00
1 : 1 : 5 in all external faces of walls and
columns finished semi rough with wood float
including reveals.

F -3 5/8’’ thick plaster in cement lime mortar 18.53 Sqrs 3,200.00 59,296.00
1 : 1 : 5 in all internal faces of walls finished
smooth with lime putty including reveals.

F -4 Non skid floor tiles bedded in 1/2’’ tk. 0.34 Sqrs 24,000.00 8,160.00
Cement mortar 1 : 2 and pointing in tile grout
cement for Bath room

F -5 Supply lay 6’ - 0’’ height glazed wall tiles 1.40 Sqrs 22,300.00 31,220.00
including bedding in cement mortar 1 : 2 for
Bath room
F -6 Non skid floor tiles bedded in 1/2’’ tk. 4.65 Sqrs 24,800.00 115,320.00
Cement mortar 1 : 2 and pointing in tile grout
cement for bed room 3& 6 kitchen dining without living
including skirting
Total carried to summary 253,979.00

G - Plumber & drain layer


All work should conform specification issued
for drainage & water services.

Rate include for :


a) All sanitary fittings should be of white
colour Ceylon ceramic manufacture.
b) Screws, mils hooks saddles brackets
sockets, connectors short casing all bends
elbow & all other specials making good in
all necessary excavation & back filling &
required gradient.

G -1 Allow he provisional sum for Plumbing & Drain 01 item 48,250.00 48,250.00
laying as directed by the Engineer.
Total carried to summary 48,250.00

H - Electrical Installation
Internal lighting wiring shall comply with
the drawings and shall be in full PVC conduits
using SLE 40 PVC insulated copper cables
all conduits shall be burried into brick walls
slab beams or columns to entire satisfaction
of the Architect/ engineer

All switches and socket cutlet shall be temby


clipsal ,MK or simillar approved sunk type
unless other wise specified.

All fans & regulators shall be National


hitachi,KDK,Sanyo or similar approved to
and approved colour.

Rate to include for all necessary plastic


switch boxes brass screws 02 core wires,
woodn plugs, round or square blocks ceiling
roses, holder ( ordinary batten and angle
batten) and any other items necessary.

Whole installation shall be carried cut


according to CEB/IEE regulations.

H -1 Allow the provisional sum for Electrical 01 item 76,000.00 76,000.00


Installation of Ground floor
Total carried to summary 76,000.00
SUMMERY
A - EXCAVATION & EARTH WORK Rs. 36,150.00
B - CONCRETE WORK Rs. 525,768.00
C - RUBBLE WORK Rs. 142,155.00
D - BLOCK WORK Rs. 277,100.00
E - CARPENTRY & JOINERY Rs. 189,224.50
F - PLASTER WORK & OTHER FLOOR FINISHING Rs. 253,979.00
G - PLUMBER & DRAIN LAYER Rs. 48,250.00
H - ELECTRICAL INSTALLATION Rs. 76,000.00
TOTAL AMOUNT 1,548,626.50

Prepared by:-…………………….
& soffit & sides of stair case)