Download as pdf or txt
Download as pdf or txt
You are on page 1of 39

Have you ever seen something like this?

© 2013
Autodesk
…or maybe like this?

© 2013
Autodesk
Audience Poll

§  Audience Background

§  What have you heard about Lean?

§  Has anyone been involved on a Lean


project?

© 2013
Autodesk
Introduction to Lean Construction and
the Last Planner System
Jon Van Benthem, Technical Account Manager, Autodesk
Rebecca Bettler, National Director of Lean Construction, JE Dunn
Tom Feliz, Customer Engagement Manager, Autodesk

© 2013
Autodesk
Lean is not…

Set of Tools

Pull
Planning
LEAN Process

© 2013
Autodesk
So What is Lean…

© 2013
Autodesk
Through continuous improvement
and respect for people, delivering
ever-increasing value to customers
while eliminating waste

© 2013
Autodesk
Innovation Requires Change

Business
Business Process People
People
Process

Technology

Technology

Perception Reality

Most companies find the biggest innovation challenge is executing change to


their people and processes.

© 2013
Autodesk
Project Snapshot – Hospital
“culture of
accountability and
collaboration”

“dynamic and live


interactive planning”

140 Beds
177,500 sq. ft.
$150 M
IPD
Waste
Consumes Resources without Providing Value

1. Overproduction 2. Waiting 3. Inventory

4. Movement 5. Effort 6. Rework of 7. Processing


Errors
© 2013
Autodesk
Non-productive Time On Job Sites
Waiting
25%
¡  Information
¡  Prerequisite Work
¡  Materials
¡  Equipment & Tools

Productive
Non- Time
Productive 42%
Unnecessary
Movement Time
13% 58%

Unnecessary
Material Handling
12%

Rework
8%
-“Show” rather than -Access to Work Area -Material Deliveries -Loading and Hoisting
priority work -Not being able to finish -Floor Congestion -Working around material
-Sequence – Walls too what is started -Changing priorities
early -Other trades in the way -No Clean-up
-Schedule Bottlenecks

-Compressed Timeframe -Out of Sequence Work -Not having answers to


-Manpower Spikes -Changing Priorities questions
-Real Issues not addressed in -Changes -Uncoordinated shop drawings
Coordination Meetings -Redoing and Undoing
-Lack of Schedule work
Commitment
BIM and Lean
§  Reduce Variability
§  Model becomes the Reliable Plan
§  Small Batch Sizes
§  Reduce Inventory
§  Single Piece Flow
§  Pull Planning
§  Visual Management
§  Continuous Improvement
§  Collaborative by Nature
§  Decision by Consensus
§  Extended Network

© 2013
Autodesk
Some of the Tools that Support the
Behavior
§  Last Planner® System §  BIM
– creates stability and §  Prefabrication
exposes opportunities §  Reflections – Lessons
§  5 S – sort, set, shine, Learned – Plus/Delta
standardize, sustain §  Process Mapping
§  Improvement §  Value Stream Mapping
programs §  Target Value Design
§  A3 Process §  Choosing by
§  5 Why Root Cause Advantages
Analysis §  Multi-party contracts
§  Laser Surveying (IFOA)
Continuous Learning and
Improvement
§  Plan - a change or a test,
aimed at improvement
§  Do - Carry out the change or
test (preferably on a small
scale)
§  Study - the results. What
was learned? What went
wrong?
§  Act - Adopt the change,
abandon it, or run through the
cycle again
Respect for People
RESEARCH FINDING FROM EARLY 90’s  

54 %
of the tasks that foreman said would
finished in a week were actually
completed in that week

© 2010 Lean Construction Institute


Last  Planner®  –  Predictable  workflow  &  rapid  learning    

Lookahead  
    Plan  &  
 Constraint  Analysis  
Pull Planning  
Master  
Schedule  

Planning System
Measurement
Percent  Plan  Complete   Weekly  Work  Planning  
Master Planning

© 2013
Autodesk
Make Ready Planning

© 2013
Autodesk
Constraint Log

•  Activity Effected •  Customer •  Constraint


•  Constraint •  Performer Champion

•  Date Identified •  Date Promised


•  Date Required •  Date Accepted

© 2013
Autodesk
Weekly Work Plan

©2012 Lean Project Consulting, Inc

26
© 2013
Autodesk
Daily Stand-Up

§  I  got  this  done  since  


our  last  stand-­‐up  
§  I’ll  get  this  done  by  
the  next  
§  Let’s  re-­‐plan  where  
necessary  
§  How  can  we  prevent  
this  from  happening  
again?  
Learning

§  Did we get to where we needed to be since


yesterday?

§  If not, why not?

§  What is our recovery plan?

§  How can we prevent this from happening


again?

© 2013
Autodesk
PPC Chart

© 2013
Autodesk
Anchor Hospital

§  9,853 square foot §  Actual duration: 19 weeks


addition §  50% contingency returned
§  Planned duration: 26 to owner
weeks §  186% of anticipated profit
Prefabrication  

•  Electrical
Underground
Prior to Precast
Placement

•  Determined
early on through
Pull Planning
and Schedule
Development
Prefabricated
Shared Racks

Mock-Ups
Mobile Kiosks and Digital Plan Room

© 2013
Autodesk
Mobile Tablets

© 2013
Autodesk
Reaching a New Frontier:
Leadership, Planning and Management
Traditional Thought Lean Thought
§  Leadership dictates direction §  Leadership facilitates
collaborative direction
§  Planning is partitioned by
trades and disciplines and is §  Planning is collaborative,
linear. It is predictive and project-based and seeks to
integrate efforts to eliminate
generally fixed, setting negative iterations. It learns
parameters for management as project evolves
§  Management controls are §  Management develops a
inflexible, autocratic – culture of accountability to
processes are fixed and implement the plan, evolves
measures are isolated and intelligence, measures are
generally historical integrated and proactive

© 2012 Lean Project Consulting


We are what we repeatedly do.
Excellence, then, is not an act, but a
habit.
- Aristotle

© 2013
Autodesk
Thank you and Questions?
© 2013
Autodesk
Session Feedback

§  Via the Survey Stations, email or mobile device


§  AU 2015 passes given out each day!
§  Best to do it right after the session
§  Instructors see results in real-time

© 2013
Autodesk

You might also like