DAILY SITE RECORD Wednesday, August 26, 2020 DAILY SITE PHOTO
55 92 0.398550724637681
25 57 43.86%
SITE VIEW
cast 2 Pile Caps today PILE CAPs AT P47 UPPER Pile Cap Construction At Upper Deck is at 70% Completed AT
DECK AND AT P25 AT LOWER DECK PILE CAPS. LOWER DECK PILE CAP P 40.74% COMPLETED, ON GOING
STATUS: at Upper Deck = 70.00% Pile Caps EXCAVATION AT Electrical Substation Area
Completed at Lower Deck
= 40.74% Pile Caps Completed
1
Supervisor
Safety Supervisor 1
Generator
Excavator CL
2
1
DETENTION DRAIN FOR TOP SLAB
Safety officer REBAR WORKCOLUMN CAST DETENTION
1 WALL 4 DRAIN AT60.51 %
08:30 17:30
COMPLETE
Site engineer FORMWORK COLUMN BAR BENDER MACHINE
1 WALL 4 1
Weather G Worker 6 23
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 IC WORKS IC#4
1
DRIZZLE
EXCAV SUPVSR 1
Manpower
2:00 14:30 TOTAL : 14 TOTAL : 29 TOTAL : 0 TOTAL : 1 44 DETENTION DRAIN @60.51% COMPLETED DETENTION DRAIN BASE REBAR INSTALLATION APPROXIMATELY
25 LINEAR METERS TO CAST TOMORROW BEFORE 3PM
Housekeeping work inprogress,
cast 2 Pile Caps today PILE CAPs AT P47 UPPER DECK AND AT P25 AT LOWER DECK PILE CAPS. COLUMN STUMPS AND RC WALL
STATUS: at Upper Deck = 70.00% Pile Caps Completed at Lower Deck = 40.74% Pile Caps
Completed COLUMN STUMP -WALL AT
LOWER AND UPPER DECK
CAST TO DATE AT 43.86%
cast 2 Pile Caps today PILE CAPs AT P47 UPPER DECK AND AT P25 AT LOWER DECK PILE CAPS.
STATUS: at Upper Deck = 70.00% Pile Caps Completed at Lower Deck = 40.74% Pile Caps COMPLETE
Completed
23 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS:BEAKDOWN OF MANPOWER @DETENTION Two RC SUMPS CAST TODAY 23 WORKERS +8 LCT +2 LBD +2CL DOING SUPERVISOR 1,
DRAIN CONSTRUCTION: 6BASE REBAR WRKRS/@COLUMN WALL/CONSTRUCTION + 5workers SITEWORKS:BEAKDOWN OF MANPOWER SAFETY 1,
COLUMN STUMP FORMWORK INSTALLATION, CAPPING BEAMS- @DETENTION DRAIN CONSTRUCTION: COLUMN STUMP
3 WORKERS . RC SUMP 3 WORKERS + 2 WORKERS
6BASE REBAR WRKRS/@COLUMN REBARWORK 5
SAFETY & HOUSEKEEPING, SHIFTING HOISTING MARTERIALS FROM LC&T Laydown Area, 3 LBD
HACKING OF MSCP PILES+ 1WORKERS IC WORKS @HDB BLOCK 231 WALL/CONSTRUCTION + 5workers COLUMN COLUMN
STUMP FORMWORK INSTALLATION, STUMP WALL FMWRK
CAPPING BEAMS- 5, DDRAIN RBWRK 6
3 DDRAIN FRMWRK/
WORKERS . CAPPING BEAM 5
RC SUMP 3 WORKERS + 2 TC OPERATOR 1
WORKERS SAFETY & HOUSEKEEPING, LBD HACK TEAM 2
SHIFTING HOISTING MARTERIALS FROM EXCAV OPRTR 1
LC&T Laydown Area, 3 LBD HACKING OF EXCAV SUPVSR 1
MSCP PILES+ 1WORKERS IC WORKS @HDB
BLOCK 231