Building Works at Hougang Town: Lower Deck Pile Cap Status

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Wednesday, August 26, 2020 DAILY SITE PHOTO

Activities Location Description of works Remarks


PILE CAP STATUS

Lower DECk PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 11 nos.
total Number OF Pile Caps@ Lower Deck 27 nos. 40.74%
Upper DECk PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 21 nos.
total Number OF Pile Caps 30 nos. 70.00%
Structural work

MSCP PILES 100.00%


CONTIGUOUS Bored Pile ( CBP ) 100.00%
GROUT PILES 100.00%
TOWER CRANE PILE CAP CAST 100.00%
CAPPING BEAMS CAST TO DATE 66.45%
1ST STOREY WALL- COLUMN STUMP CAST TO DATE 42.10%
DETENTION DRAIN CAST TO DATE 60.51%
RC SUMP CAST TO DATE 2.857%

55 92 0.398550724637681

25 57 43.86%

SITE VIEW

PILE CAP STATUS @


LOWER DECK AT 40.74% @
Architectural

UPPER DECK AT 70% COMPLETED


work
M & E Work

cast 2 Pile Caps today PILE CAPs AT P47 UPPER Pile Cap Construction At Upper Deck is at 70% Completed AT
DECK AND AT P25 AT LOWER DECK PILE CAPS. LOWER DECK PILE CAP P 40.74% COMPLETED, ON GOING
STATUS: at Upper Deck = 70.00% Pile Caps EXCAVATION AT Electrical Substation Area
Completed at Lower Deck
= 40.74% Pile Caps Completed

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
1 DETENTION DRAIN
P Manager
Site Supervisor
1

1
Supervisor
Safety Supervisor 1
Generator
Excavator CL
2

1
DETENTION DRAIN FOR TOP SLAB
Safety officer REBAR WORKCOLUMN CAST DETENTION
1 WALL 4 DRAIN AT60.51 %
08:30 17:30
COMPLETE
Site engineer FORMWORK COLUMN BAR BENDER MACHINE
1 WALL 4 1

RTO BIG BREAKER


1 FORMWORK D DRAIN 3 1

REBAR WORK D DRAIN


REMARKS Administrator 1 4 RC SUMP
Coordinator 1 CAPPING BEAM 3 AIR RECEIVER 1

COLUMN STUMP TC INSTALLED


ECO 1 3 1

Weather G Worker 6 23
TC OPERATOR 1
LBD HACK TEAM 3
EXCAV. OPTR
1 IC WORKS IC#4
1
DRIZZLE
EXCAV SUPVSR 1
Manpower
2:00 14:30 TOTAL : 14 TOTAL : 29 TOTAL : 0 TOTAL : 1 44 DETENTION DRAIN @60.51% COMPLETED DETENTION DRAIN BASE REBAR INSTALLATION APPROXIMATELY
25 LINEAR METERS TO CAST TOMORROW BEFORE 3PM
Housekeeping work inprogress,
cast 2 Pile Caps today PILE CAPs AT P47 UPPER DECK AND AT P25 AT LOWER DECK PILE CAPS. COLUMN STUMPS AND RC WALL
STATUS: at Upper Deck = 70.00% Pile Caps Completed at Lower Deck = 40.74% Pile Caps
Completed COLUMN STUMP -WALL AT
LOWER AND UPPER DECK
CAST TO DATE AT 43.86%
cast 2 Pile Caps today PILE CAPs AT P47 UPPER DECK AND AT P25 AT LOWER DECK PILE CAPS.
STATUS: at Upper Deck = 70.00% Pile Caps Completed at Lower Deck = 40.74% Pile Caps COMPLETE
Completed

23 WORKERS +8 LCT +2 LBD +2CL DOING SITEWORKS:BEAKDOWN OF MANPOWER @DETENTION Two RC SUMPS CAST TODAY 23 WORKERS +8 LCT +2 LBD +2CL DOING SUPERVISOR 1,
DRAIN CONSTRUCTION: 6BASE REBAR WRKRS/@COLUMN WALL/CONSTRUCTION + 5workers SITEWORKS:BEAKDOWN OF MANPOWER SAFETY 1,
COLUMN STUMP FORMWORK INSTALLATION, CAPPING BEAMS- @DETENTION DRAIN CONSTRUCTION: COLUMN STUMP
3 WORKERS . RC SUMP 3 WORKERS + 2 WORKERS
6BASE REBAR WRKRS/@COLUMN REBARWORK 5
SAFETY & HOUSEKEEPING, SHIFTING HOISTING MARTERIALS FROM LC&T Laydown Area, 3 LBD
HACKING OF MSCP PILES+ 1WORKERS IC WORKS @HDB BLOCK 231 WALL/CONSTRUCTION + 5workers COLUMN COLUMN
STUMP FORMWORK INSTALLATION, STUMP WALL FMWRK
CAPPING BEAMS- 5, DDRAIN RBWRK 6
3 DDRAIN FRMWRK/
WORKERS . CAPPING BEAM 5
RC SUMP 3 WORKERS + 2 TC OPERATOR 1
WORKERS SAFETY & HOUSEKEEPING, LBD HACK TEAM 2
SHIFTING HOISTING MARTERIALS FROM EXCAV OPRTR 1
LC&T Laydown Area, 3 LBD HACKING OF EXCAV SUPVSR 1
MSCP PILES+ 1WORKERS IC WORKS @HDB
BLOCK 231

DETENTION DRAIN BASE REBAR INSTALLATION APPROXIMATELY 25 LINEAR METERS TO CAST


TOMORROW BEFORE 3PM
Today Noise Meter does not exceed.