J-826
10
AREA 2500
AMINE UNIT
INTRODUCTION
This manual covers the basic procedures for the commissioning, preparation, start-up,
ormal operation, normal shutdown, and emergency shutdown of the Amine Unit, Area
2500. Since the Amine Unit forms only a part of the overall system, it is not possible for
the basic procedures presented to cover all operational contingencies. The information
presented should be carefully reviewed by operating personnel with respect to proper
operator reactions to deviations and difficulties that will arise. For interconnection
between Phase one and Phase two, reference the “Interconnections” sections at the
beginning of this manualAREA 2500
Page 2 - J-826
2.0 PROCESS DESCRIPTION
‘The process description can be better followed by referring to the P&l D's, 826-D-5102-1
through 826-D-5102-13
The Amine Unit is designed to treat approximately 3.0 MM SCMID of gas from 5.0 mole
% CO; to less than 100 ppm CO2.
24
22
Feed Knock Out System
The inlet gas flow to the amine unit is controlled by FV-21405 in the 2100 area
FV-21405 has a minimum stop that will prevent the valve from closing and
sending too much gas to the amine unit. The raw gas enters the amine unit and
flows to the Inlet Separator, V-2501, to knock out any entrained liquids in the
stream. Hydrocarbon carryover causes foaming and decreases efficiency of the
amine system. The vessel is equipped with a coalescing vane pack at the outlet
{0 aid in minimizing the liquid carryover. Entrained liquids are accumulated and
sent to the Condensate Flash Drum, V-2601, by a level controller LIC-25101,
which operates LV-25101. An independent low level switch, LSLL-25103 is
provided as a safeguard. Activation of the low-level switch will close a secondary
valve, NV-25501, to prevent gas blow -by to the condensate stabilization unit
The vessel is also equipped with local level gauge, LG-2501, and a local
pressure gauge, PI-2501, for monitoring purposes. An inlet CO» analyzer (AE-
25602) is provided to monitor inlet CO, concentrations.
Gas Contactor
Gas from V-2501 then flows to the Gas Contactor where a specialty amine (Dow
Gas/Spec now owned by INEOS) removes. the carbon dioxide that is present in
the gas. The contactor contains 21 valve type trays. The gas flows up the tower
and is contacted with the amine, which flows down the tower. The CO» isAREA 2500
Page 3 ~ J-826
2.0 PRE = continued -
chemically reacted with and adsorbed by the amine. The reaction is later
reversed by high temperatures and low pressures in the stripper, to regenerate
the amine. The treated gas from the contactor is then sent to the Outlet
Separator, V-2503.
To aid in trouble shooting the unit, the contactor is equipped with a differential
pressure measurement PDI-25302 across the trays. An increase in pressure
drop usually indicates foaming
‘The rich amine solution flows from the bottom of T-2501 to the Rich Amine Fiash
ow level switch is provided as a safeguard. Activation of LLSL-25106 will close a
secondary valve, NV-25503. Local level gauges, LG-2503 A/B, and a local
pressure gauge, PI-2503 are also provided for monitoring. A relief valve, PSV-
2501 protects V-2501, V-2503, and 7-2501 from overpressure.
2.3 Outlet Separator
Entrained amine is knocked out in the Outlet Separator, V-2503. The vessel
contains a coalescing Vane pack at the outlet to minimize any liquid carryover in
the treated gas. Entrained liquids are collected in the bottom of the vessel, and
sent to the Rich Amine Flash Drum, V-2505, by a level controller, LIC-25102. An
independent low level switch is provided as a safeguard. Activation of LSLL-
25104 will close a secondary valve, NV-25502. A local level gauge, LG-2502,
and a local pressure gauge, P1-2502, are provided for monitoring the vessel. An
outlet CO; analyzer (AE-25601) is provided to monitor treated gas CO,
concentrations.
|
Drum, V-2505, on level contol using LIC-25105 and LV-25108. An independent |
i
eee : PETROPACAREA 2500
Page 4 ~ J-826
2.0 PROCESS DESCRIPTION — continued -
2.4 Rich Amine Flash Drum
The rich amine flows from the contactor to the Rich Amine Flash Drum, V-2505.
Entrained gases and hydrocarbons are flashed from amine solution. The
relatively small amount of flashed gas is sent to the Hot Oil Heaters, H-2701 A/B,
{for disposal. Pressure is maintained on the vessel by PIC-25303 and PV-25303.
\V-2508 also has adequate residence time to separate liquid oil from the aqueous
{amine/water) solution. The oil will overflow the oil side baffle, and is manually
drained from the system.
‘The amine flows through the underflow/overfiow weir assembly to maintain an
aqueous seal and prevent the carry over of oil. Level in the amine side of the
vessel is maintained by LIC-25107 and LV-25107. Local level gauges are
provided for the amine section LG-2504, and the oil section LG-2508, for local
monitoring of the vesse! levels.
2.5 Amine Regeneration
The rich amine from V-2505 is heated by cross exchange with the lean amine in
the Lean/Rich Amine Exchangers, £-2501 A/B (two 50% operating exchangers),
and is then sent to Amine Stripper, T-2502, for regeneration of the amine. Local
temperature gauges are provided for monitoring the performance ofthe plate and
frame exchangers. TI-25203 provides a DCS temperature measurement also.
17-2502 is a trayed tower with twenty-one valve trays and one chimney tray. The
feed enters just above the top tray of the tower through an inlet distributor. A
small amount of the feed will be vapor, and travels out of the top of the tower.
‘The liquid is evenly distributed on to the deck of the top tray.
|
|
i2.0 PROCESS DESCRIPTION — continued -
The Amine Stripper Reboilers, £-2502 AJB, are once-through horizontal
thermosyphon type rebollers. In a thermosyphon type reboiler, the density
difference between the two phase retum line and the liquid inlet line provides the
pressure driving force to allow circulation through the exchanger. The particular
configuration of this reboiler also allows for simple gravity flow through the
‘exchangers. Hot oil is used as the heat source for the reboilers. In the reboilers,
portion of the solution is vaporized. The vapor, mostly steam, travels up
through the tower. The combination of heat and low pressure reverses the acid
gas absorption reaction, and the steam strips the acid gas components from the
amine solution. The amount of heat and the amount of stripping are controlled by
controlling the amount of hot oil to the reboiler via FIC-25403/FIC-25404 and FV-
25403/FV-25404,
The overhead vapor from T-2502 flows to the Amine Stripper Overhead
Condenser, AC-2502. The overhead vapor consists mostly of water vapor, CO>,
and small amounts of hydrocarbons and other components. Most of the water
vapor is condensed in AC-2502, which is an air-cooled heat exchanger. Manually
operated louvers are provided on AC-2502 for controlling the outlet temperature
from the air cooler.
The two-phase mixture from AC-2502 is separated in V-2502, the Amine Stripper
Reflux drum, V-2502 contains a wire mesh mist pad to minimize liquid
carryover. The acid gas is vented to the atmosphere through PV-25305, which
maintains the operating pressure of T-2502 at the pressure controller PIC-25305
set point. The liquid is accumulated in the bottom of the vessel, liquid level is
controlled by LIC-25110 and LV-25110. An independent low level switch is
provided as a safeguard, Activation of the low-level switch, LSLL-25111, wil
shut off P-2502 A/B, the Amine Stripper Reflux Pumps to prevent damage to
these pumps from loss of suction. A local level gauge, LG-2507, and a local
pressure gauge, Pl-2509, are provided for monitoring the vessel
®
PETROFAC
r >
AREA 2500
Page 5 J-826AREA 2500
Page 6 ~ J-826
2.0 PROCESS DESCRIPTION — continued -
28
‘The liquid from V-2502 enters the suction of the Amine Stripper Reflux Pumps,
P-2502 A/B, and is pumped back to T-2502 as reflux. One pump is operational,
and the other is a 100% standby spare,
\V-2502 also contains a oil weir. If an oil layer is present as evidenced by the local
interface level gauge, LG-2508, the oil can be decanted.
The regenerated hot amine leaves the bottom of T-2502 and flows through E-
2501 AVB to the suction of the Lean Amine Circulation Pumps, P-2501 A/B/C.
The level in the bottom of T-2502 is indicated by LT-25108 on the DCS. The
bottom section of T-2502 is the surge compartment for the unit. An independent
low level switch is provided as a safeguard. Activation of the low-level switch,
LSLL-25109, will shut off the Lean Amine Circulation Pumps (P-2501 A/B/C) as
well as the Lean Amine Booster Pumps (P-2506 A/B/C) to prevent damage to.
these pumps from loss of suction. The activation of this low level switch also
causes a secondary valve (NV-25523) at the gas contactor to close. This will
prevent the high pressure gases in the contactor from entering the amine circuit
when the amine circulation pumps are not running. Local level gauges, LG-2506
‘AB are provided to monitor the liquid level as well
ADCS pressure differential gauge, PDI-25304, is also provided to monitor the
pressure drop across the tower. A significant increase in pressure drop is a sign
of foaming in the system. A pressure relief valve, PSV-2508, provides pressure
relief for the regeneration system. |
Lean Amine Circulation, Filtration, and Cooling i
The hot lean amine from the stripper, exchanges heat with the rich amine in the |
Leanv/Rich Amine Exchangers E-2501 A/B. The Lean Amine Circulation Pumps |
(P-2501 A/BIC) are designed such that two pumps are operational and one is aAREA 2500
Page 7 ~ J-826
2.0 PROCESS DESCRIPTION - continued
50% standby spare. P-2501 A/B/C pumps the lean amine to the Lean Amine
Cooler (AC-2501). Flow from AC-2501 then splits, the majority flows to the Lean
‘Amine Booster Pumps (P-2506 A/B/C) and a controlled amount flows to the Lean
‘Amine Mechanical Filters (F-2501 AJB) and on to the Amine Carbon Filters (F-
2502 AJB). These flows blend back at the suction of P-2506 A/B/C. The Lean
‘Amine Booster Pumps (P-2508 A/B/C) are designed such that two pumps are
operational and one is a 50% standby. P-2506 A/B/C pumps the lean amine to T-
2501 Gas Contactor.
‘The Lean/Rich Amine Exchangers (E-2501 A/B) are plate frame exchangers that
are sized for 50% of the total required duly each. Local temperature gauges
provide monitoring of each LeaniRich Exchanger.
‘The Lean Amine Cooler (AC-2501) is an air cooled exchanger that consists of
three (3) bays. One of the bays have automatic louvers which are controlled with
TIC-25206, while the other two bays do not have louvers. Local thermowells
provide the ability to monitor the performance of each bay. A local temperature
‘gauge (TI-2508) provides monitoring of the air cooler.
‘The Lean Amine Mechanical Filters (F-2501 A/B) process a slipstream (10%) of
the total amine flow. The filters are equipped with local pressure differential
indication, PDI-25306 and PDI-25307, to determine when the filter elements have
become clogged and changeout is necessary. The filters can be blocked in while
on-stream for changeout of the elements. PSV-2510 and PSV-2511 provide
pressure relief protection of the filters.
|AREA 2500
Page 8 ~ J-826
2.0 PROCESS DESCRIPTION - continued -
‘The Amine Carbon Fillers (F-2502 A/B) process the stream of amine that has
been filtered in the mechanical flters. F-2502 A/B are filled with activated carbon,
which removes hydrocarbons and other impurities in the amine stream. PDI-
25308 and PDI-25309 provide differential pressure measurement across the
carbon beds to determine when changeout of the carbon is necessary. The filters
can be blocked in while on-stream for changeout of the carbon beds. PSV-2512
and PSV-2513 provide pressure relief protection for the two vessels.
The Lean Amine Booster Pumps (P-2506 A/B/C) pump lean amine to the top of
the Gas Contactor (T-2501). Lean Amine flow to the Contactor is controlled by
FIC-25402, while FIC-25409 provides minimum flow protection for the pumps by |
retuming flow to suction of the Lean Amine Circulation Pumps (P-2501 A/BIC).
27 — Drained Amine System
All of the amine drains in the unit gravity flow to V-2504, the Drained Amine
Vessel. This material is pumped back to the Rich Amine Flash Drum, V-2508, by
the Drained Amine Pump, P-2504. If an oil layer is known to be in V-2504, it can
be decanted to the oil side of the vessel and pumped out by P-2503, the Slop Oil
Pump. This pumps the oil either to V-2508 or to the closed drain header. DCS
level indicators, LI-25114B (amine side) and LI-25115B (cil side), are provided
for monitoring the liquid levels in the vessel. A small flow of sweet fuel gas is
provided as a sweep gas to prevent a build up of high concentrations of H2S |
and/or any oxygen that may have entered the system from venting/purging of
‘equipment during maintenance. The flow of this gas is regulated by PCV-2506AREA 2500
Page 9 — J-826
2.0 PROCESS DESCRIPTION — continued -
2.8 Amine Storage Area
‘The amine storage area consist of two main parts: Tankage and Pumpage.
2.8.4 Tanks
The combined capacity of TK-2501 and TK-2502 is sufficient to hold the
{ull inventory of the system. However, it wil normally be the case that TK-
2501 will be used as a tank of makeup amine and TK-2502 will be used
as temporary storage capacity of drained amine. The Drained Amine
Tank (TK-2502) has sufficient capacity to hold the system inventory with
the exception of V-2505. Under most circumstances, which require the
Unit to be drained, it is likely that V-2505 will be blinded off with its
inventory of amine and the rest of the system will be drained via V-2504
and into TK-2502. Should maintenance be required on V-2505, then this,
vessel should be drained independently of the rest of the system to insure
that sufficient storage volume is available in TK-2502.
The Amine Storage Tank, TK-2501, is supplied to provide the means of
filing, diluting, and makeup of amine to the unit. Over time, amine
‘makeup will be required. The tank has local level indication via LI-25113,
The tank is blanketed with fuel gas to minimize oxygen migration in the
tanks, which accelerates the degradation of the amine. The fuel gas is
regulated by PCV-2505. The tank is protected from overpressure by PSV-
2515. These relief devices also provide vacuum protection. Normal
breathing losses in the tank are vented to the atmosphere. A local
pressure gauge, PI-2517, is provided for monitoring
Makeup water for dilution of amine and normal water makeup
requirements is controlled by FQIC-25407and FV-25407. This.
meterivalve arrangement allows a certain amount of water to be added to
the system, The water can be routed to either V-2505 or V-2502,AREA 2500
Page 10 - J-826
2.0 PROCESS DESCRIPTION — continued -
2.8.2 Amine Makeup Pump
The Amine Makeup Pump, P-2505, is provided to charge amine to the
system, circulate the inventory in the tanks, transfer inventory to the other
tank, or can be used for off-loading amine from the unit. Piping and valves.
are supplied so that the pump can take suction from either of the two
tanks, TK-2501 or TK-2502. The discharge can then be routed to (a) the
unit, (b) the same tank as suction, (c) the opposite tank as suction, (d) the
Phase 1 tanks, (e) a hose connection.
Restcto orffces, FO-2503 and FO-2504 are supplied to provide |
minimum flow protection for the pump if needed, The minimum flow |
recirculation lines are routed back to both of the tanks. FQIC-25408
controls a totazer valve, FV-25408, which allows a certain amount of
artne to be added to V-2505.
29 — Antifoam Injection System
‘The antifoam injection system consists of the Antifoam injection Pump (P-2507)
and a drum rack enabling the antifoam chemical to be pumped directly from the
55-gallon drum in which it is supplied.
A calibration gauge is also furnished with the system. The pump is a small
proportioning pump, and is furnished with a relief valve,
‘The antifoam can be injected into the suction of either P-2506 A/BIC or P-2502
AB,AREA 2500
Page 11 — J-826
344
B42
3.0 PREPARATION FOR INITIAL START-UP
3.4 System Checkout
Following the completion of mechanical installation and electrica/instrument
interconnections to controls, the systems should be checked out and all
deficiencies corected,
Inspect vessels intemally as well as possible from manways and hand
holes. Remove any weld slag, dirt, debris, or any other foreign material,
Check out all piping against the Petrofac P&ID's and verity
3.1.2.1 All items are installed. All items and piping are of proper sizes and
pressure ratings,
3.1.2.2 Control valves and check valves are installed in the proper flow
direction.
3.1.2.3 Relief valve nameplate settings are correct.
3.1.2.4 Free operation and travel of manual valves.
3.1.2.5 Removal of temporary braces and tie downs, if any.
Verify all fiter media is on hand. Remove filter media from all fiters.
These will be reinstalled after cleaning
Using compressed air, blow scale and dirt from piping as well as possible.
Pressure the system to 0.5 to 0.7 kg/cm?(g) (7-10 psig). Check all flanges
and connections for leaks with soap solution or other suitable means of
detection. Correct any leaks.AREA 2500
Page 12 - J-826
3.0 PREPARATION FOR INITIAL START-UP ~ continued -
3.1.5 Install lubricants in pumps and motors as required. Verity electric power
supply to motors. Disconnect drivers and verify free movement of pump
shafts. “Bump " motors to verily correct rotation. Reinstall shaft couplings
and verify correct alignment.
3.4.6 Check out instrumentation and controls
3.1.6.1 Verify proper installation and ranges for local pressure gauges
land temperature gauges.
3.1.6.2 Verify proper installation of orifice plates and thermocouples.
3.1.6.3 Verify installation and continuity of all interconnections between
the unit and control room,
3.1.6.4 Establish instrument air supply to all users.
3.1.6.5Commission control loops and verify proper controller action,
calibrations, and control valve actionitravel :
3.1.6.6Verify alarms and interlock actions, ESD system, ESD |
instruments, and action of ESD valves and instrumentation.
3.1.7 Remove all unnecessary construction debris, scaffolding, and the lke
from the unit area |
3.2 System Cleaning
Any rust, ditt, oils or grease left inside the system after installation can contribute
to serious foaming and fouling problems during startup and operation of the unit, |
In sufficient degree, these problems can cause inability to achieve the required
removal of carbon dioxide from the product gas stream, high amine losses, and |
chronic system upsets. Therefore, the unit should be thoroughly cleaned prior to |
amine charge and start-up. A suggested procedure for the washing of the unit is
as follows: iAREA 2500
Page 13 — J-826
3.0 PREPARATIOI IAL START-UP — continued -
3.24
3.22
3.23
3.24
‘A substantial amount of treated water, as well as a means of disposal of
cleaning solutions will be required. It may be necessary to start storing
water in TK-2501 andlor TK-2502 prior to cleaning, to insure sufficient
water is available. It is also suggested that disposal of the cleaning and
Finsing solutions be arranged. All solutions and chemicals should be
made with demineralized water and low chloride chemicals to prevent
potential chloride stress corrosion of stainless steel components
This boiloutiflushing should be done prior to the installation of the filter
elements and filter media. P-2501 A/B/C and P-2506 A/B/C will be utilized |
to circulate the solution. P-2504 can be used to pump drained liquids to
TK-2502.
Using treated water, establish levels in V-2505, T-2501, and T-2502. This
‘can be done by using hose connections and utility connections for these
vessels. Establish circulation of water, add water as necessary, but keep
2 relatively low level in T-2502 so that cleaning solution can be added
Keep records of the total amount of water added to the system using the
counters on FCIC-25407. T-2501 may need to be pressurized to about 1 |
to 2 kgiom? (15-30 PSIG) with inert gas so that the solution can flow to V-
2505. Do not overfill system inventory so that cleaning solution can later
be added.
‘The preferred solution for the cleaning is a 3 wt% solution of the
GASISPEC amine solvent. This has the advantage of not having to be
water washed after cleaning,
Optionally a solution of 3 w1% caustic soda (NaOH) combined with 2 wi%
soda ash (Na;CO,) can be used.
PETROPAcAREA 2500
Page 14 - J-826
3.0 PREPARATION FOR INITIAL START-UP - continued -
3.25
3.26
3.27
‘Add enough amine to the unit, while circulating, to bring the solution to
approximately 3 wi%, or add the caustic soda and soda ash to the
circulating water to achieve the 3wt% and 2wt% concentrations
respectively. Reference Appendix 3 for estimated quantities of Boil out
materials.
Introduce hot oil to the reboiler, E-2502 A/B and heat the solution to 65°C-
85°C (149°F - 185°F), Circulate the warm solution for a minimum of 12
hours. A small amount of water vapor may go overhead at T-2502. Use
the overhead condenser and reflux pumps (P-2502 A/B) when needed to
minimize water losses. It should not be necessary to start any of the fans
for the air cooler. If fans are used, be sure to close the louvers on AC-
2501, because it is desired to keep the circulating solution warm over the
entire unit.
Be sure to open all available circuits for flow, such as the filters, spare
pumps, exchangers, etc, so that they are all cleaned. Run spare pumps
and clean suction strainers of the offline pumps. This is particularly
important during the initial running of the pumps. when most of the debris
will be caught in the strainers.
After 12 hours, stop the heating of the solution and allow to cool to
approximately 48°C (118°F), The fans for AC-2501 can be used if
necessary to cool the solution. Drain the solution to V-2504, pump to TK-
2502, and drain to appropriate facilites.AREA 2500
Page 15 - J-826
3.0 PREPARATION FOR INITIAL START-UP ~ continued -
33
3.2.8 IF CAUSTIC AND SODA ASH ARE USED AS THE CLEANING
SOLUTION: After draining the solution, refil the unit with treated water.
Circulate the water through the system for a minimum of two hours to
clean as much of the solution as possible from the system. Again, make
sure that all circuits, such as spare pumps, exchangers, filters, etc., are
flushed. AMter flushing, drain the system. Continue flushing unit until the
sodium content of the water is less than 100 ppm.
3.29 Open the manways of T-2501, T-2502, and V-2505. Inspect for
cleanliness. If they do not appear clean, redo procedure until unit is clean.
3.2.10 After completion of the water flush and draining, install the filer elements
in F-2501 A/B, and fill F-2502 A/B with the carbon bed media. The amine
system is now ready to purge for removal of oxygen
Purging The System
[At this point, itis necessary to purge the air from the system. Before hydrocarbon
{928 oF amine is introduced to the unit, itis important that oxygen be purged with
an inert gas. This prevents oxidation of the amine and also protects against the
formation of an explosive mixture.
Due to length of time required to purge the unit, purging should be undertaken as
quickly as possible to minimize oxidation.
3.3.1. A supply of inert gas for purging the unit must be available.
3.3.2. Make sure all hydrocarbon lines to the unit are blocked in.
(é
PeraoracAREA 2500
Page 16 - J-826
3.3.3
3.3.4
335
341
|
i
3.4 Preparation of Ar
3.0 PREPARATION FOR INITIAL START-UP — continued -
Introduce inert gas slowly to the equipment at convenient points
Pressure the unit up to about 1.25 kg/cm*(g) (18 psig). Vent the inert gas
from all available equipment and piping extremities, so that all of the
‘equipment and piping are purged as well as possible. When venting the
inert gas/air, vent down to about 0.1 kg/cm*(g) (1.5 psig).
Close all vents, repeat inert gas pressurization/depressurization. Continue
purging until oxygen content is below 1%, as measured with portable
analyzers. It will take approximately 4 to 6 purges to reduce the oxygen to
less than 1%.
If desired, the unit can be separated into several sections, and each
section purged individually.
WARNING - Do not vent the purge gases to the flare, as this could
produce an explosive or flammable mixture in the flare line.
When purging is complete, maintain the system at a certain pressure for a
pre-determined amount of time for a leak test. If pressure decreases, look
for and correct any leaks. Note that ambient temperature fluctuations can
‘also cause slight pressure fluctuations in the system
After leak test is complete, the equipment can be maintained at about 0.7
kg/em?(g) (10 psig).
1e Solution
Prior to charging amine, remove any blinds as necessary to allow normal
system flows. Purge air from any equipment that may be opened to the
atmosphere.
PETROPAC
®AREA 2500
Page 24 - J-826
amine circulation. Also make proportional increases in the hot oil rate to
the reboiler. Observe CO, content of treated gas and differential pressure
across T-2501. At design rates, analyses should be performed on the
inlet gas, outlet gas, rich amine, lean amine, and acid gas. This is
necessary to determine operating conditions, loadings, and optimization
of the unit
The amine unit should now be commissioned and operational.5.0
AREA 2500
Page 25 ~ J-826
NORMAL OPERATION
It is important to monitor the unit regularly to make sure that all the temperatures,
pressures, flows, and levels are at their normal conditions. Regular analyses of the
amine solution and of the inlet and outlet gases are vitally important to the operation of
the unit. Prompt corrective action to any abnormal condition will result in increased
safety, less downtime, and more on-spec product.
Under normal operation conditions, the amine unit will be controlled from the control
room with a few exceptions. However, the unit should be visited on a periodic basis by a
qualified operator who will take readings of locally indicated instruments and observe
that all of the equipment is functioning correctly.
The raw gas feed, treated gas, and off gas should be tested on a routine basis, Also,
samples of the rich amine and lean amine should be tested to determine the COz loading
of the amine to monitor the effectiveness of the stripping and regeneration cycle,
Lean amine solution strength should be checked at least once every twenty-four hours.
A listing of expected operating conditions at design capacity is included in Section 5.1
‘Some of the major items to be monitored by the operators are:
5.1 Amine Circulation Rate - Adjusted to provide approximately 100 ppmv CO; in the
sweet gas. At reduced rates or lower than design acid gas content of the feed
gas, the circulation rate can be lowered to save operating costs.
5.2 Reboiler - The amount of reboiling in E-2502 A/B is the key variable for the
degree of acid gas stripping achieved in the Amine Stripper, and is generally
controlled by setting the flow rate through FV-25403 and FV-25404. If amine
circulation rate is reduced, the hot oil rate can also be reduced, but generally not
as much.
Py