ID Task  Task Name Duration Start Finish Predecessors 18 Sep '16 25 Sep '16 02 Oct '16

Mode S S M T W T F S S M T W T F S S M T W T
1 PENINGKATAN 65 days Wed Tue
JALAN CANDI JAGO 05/10/16 03/01/17
2 Pekerjaan 7 days Wed Thu
Pendahuluan 05/10/16 13/10/16
3 Mobilisasi 7 days Wed 05/10/16Thu 13/10/16
4 Pekerjaan Jalan 56 days Wed 12/10/1Wed 28/12/1
5 Lapis Perekat 11 days Wed 12/10/16Wed 26/10/16
6 Lataston Lapis Aus 15 days Thu 27/10/16 Wed 5
(HRS-WC) 16/11/16
7 Lataston Lapis 15 days Thu 17/11/16 Wed 6
Pondasi 07/12/16
8 Marka Jalan 15 days Thu 08/12/16 Wed 7
Termoplastik 28/12/16
9 Pekerjaan lain-lain 5 days Wed 28/12/1Tue 03/01/17
10 Pembersihan Proyek 5 days Wed 28/12/16Tue 03/01/17 7FS+3 days

Task Inactive Task Start‐only


Split Inactive Milestone Finish‐only
Milestone Inactive Summary Deadline
Project: barcahrt bangun
Date: Mon 19/09/16 Summary Manual Task Progress
Project Summary Duration‐only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 1
09 Oct '16 16 Oct '16 23 Oct '16 30 Oct '16 06 Nov '16 13 Nov '16 20 No
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Inactive Task Start‐only


Split Inactive Milestone Finish‐only
Milestone Inactive Summary Deadline
Project: barcahrt bangun
Date: Mon 19/09/16 Summary Manual Task Progress
Project Summary Duration‐only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 2
Nov '16 27 Nov '16 04 Dec '16 11 Dec '16 18 Dec '16 25 Dec '16 01 Jan '17
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Task Start‐only


Split Inactive Milestone Finish‐only
Milestone Inactive Summary Deadline
Project: barcahrt bangun
Date: Mon 19/09/16 Summary Manual Task Progress
Project Summary Duration‐only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 3