PREFACE EARTHWORK
Feb 2010 2
PREFACE EARTHWORK
Benefit
• ACQUIRRING cutting edge practical design knowledge & skills that last
forever in the world of ever-changing infrastructural engineering.
• WINNING at the office and in daily job with the power of practical skill.
Feb 2010 3
EARTHWORK
TABLE OF CONTENTS
Feb 2010 4
EARTHWORK
1 INTRODUCTION
5
Feb 2010 5
1 INTRODUCTION EARTHWORK
Definition of Earthwork
Feb 2010 6
1 INTRODUCTION EARTHWORK
Typical earthworks include Platforms, roads, dams, dikes, cannal, bunding, and berms ("noise mounds").
Feb 2010 7
1 INTRODUCTION EARTHWORK
Sinkhole
High tide
8
Slope Failure
Feb 2010 8
EARTHWORK
Feb 2010 9
2 MASTERPLAN & DESIGN GUIDING PRINCIPLE EARTHWORK
Objectives
• Costs Plan
Feb 2010 10
2 MASTERPLAN & DESIGN GUIDING PRINCIPLE EARTHWORK
Controlled Earthwork
Centralised facility
Slopes turfed
Feb 2010 12
1 MASTERPLAN & DESIGN GUIDING PRINCIPLE EARTHWORK
Uncontrolled Earthwork
Feb 2010 13
2 MASTERPLAN & DESIGN GUIDING PRINCIPLE EARTHWORK
A. Client’s Requirement
• Terms Of Reference
B. Authority’s Requirement
• Design Guidelines
• Statutory Requirement
2
14
Feb 2010 14
N 2 MASTERPLAN & DESIGN GUIDING PRINCIPLE EARTHWORK
Development Masterplan
• Engineer to establish
Term Of Reference
15 Industrial
Typical Development Masterplan
Residential Feb 2010 15
Layout
2 MASTERPLAN & DESIGN GUIDING PRINCIPLE EARTHWORK
Source: MSMA
Feb 2010 17
EARTHWORK
3 Preliminary Design
Feb 2010 18
3 PRELIMINARY DESIGN EARTHWORK
Identification
of correct site &
Project Boundary
“CRUCIAL”
• Obtain CP
from Survey
Dept.
• Check lot
numbers
• Check
boundaries
Feb 2010 20
3 PRELIMINARY DESIGN EARTHWORK
Site Reconnaissance
Feb 2010 21
3 PRELIMINARY DESIGN EARTHWORK
Tidal influence
Feb 2010 22
3 PRELIMINARY DESIGN EARTHWORK
Objectives
SOIL INVESTIGATION
Feb 2010 23
EARTHWORK
4 Detail Design
Feb 2010 24
4 DETAIL DESIGN EARTHWORK
• Achieve an almost balanced cut and fill volume within the development
Feb 2010 25
4 DETAIL DESIGN EARTHWORK
Design Procedure
• Design Criteria
Feb 2010 26
4 DETAIL DESIGN EARTHWORK
Design Procedure
• Design Criteria
• Study Project Layout (Development Plan)
Feb 2010 27
4 DETAIL DESIGN EARTHWORK
Design Criteria
• Clearing, grubbing, stripping top soil, cut & fill,
compact, trimming, turfing, soil test for FGL
1.2
Feb 2010 28
4 DETAIL DESIGN EARTHWORK
Design Criteria
• All slopes closed turf
Tg Gelang
Feb 2010 29
4 DETAIL DESIGN EARTHWORK
Design Criteria
Feb 2010 30
4 DETAIL DESIGN EARTHWORK
Feb 2010 31
4 DETAIL DESIGN EARTHWORK
Feb 2010 32
4 DETAIL DESIGN EARTHWORK
Design Procedure
• Design Criteria
Feb 2010 33
4 DETAIL DESIGN EARTHWORK
Feb 2010 34
4 DETAIL DESIGN EARTHWORK
Slopes direction
Swampy
+2m to 3m
Potential high
Ground for Water
Hilly 80m Supply Tank
Existing Existing
+5m to 9m +5.5m
Existing
+3m
Slopes direction
Feb 2010 35
4 DETAIL DESIGN EARTHWORK
Design Procedure
• Design Criteria
Feb 2010 36
4 DETAIL DESIGN EARTHWORK
Existing Existing
+5m to 9m +5.5m
Existing
+3m
Slopes direction
Feb 2010 37
4 DETAIL DESIGN EARTHWORK
Design Procedure
• Design Criteria
Feb 2010 38
4 DETAIL DESIGN EARTHWORK
Max.
Proposed Platform Level Formation
Min.
Freeboard = +1m
Highest Flood Level = +2.2m ODL
Water body
Feb 2010 39
4 DETAIL DESIGN EARTHWORK
Conceptual Platform
Platform Level to
be above Highest Flood Level
Feb 2010 40
4 DETAIL DESIGN EARTHWORK
Cut area
Fill area
Follow drainage
pattern
Notes:
1. All levels are in meter O.D.L
Feb 2010 41
4 DETAIL DESIGN EARTHWORK
Notes:
1. All levels are in meter O.D.L
Feb 2010 42
4 DETAIL DESIGN EARTHWORK
Feb 2010 43
4 DETAIL DESIGN EARTHWORK
Design Procedure
• Design Criteria
Feb 2010 44
4 DETAIL DESIGN EARTHWORK
Design Procedure
Principle
• Too much fill material - Difficult to obtain borrow source & Cost
Feb 2010 45
Methods
4 DETAIL DESIGN EARTHWORK
Design Procedure
• Land development
• Cross-section Method
Feb 2010 46
4 DETAIL DESIGN EARTHWORK
Feb 2010 47
4 DETAIL DESIGN EARTHWORK
1 2 3 4 5 6 7 8 9 10 11
A
X F
7 10 8 10 9 10 10
EARTHWORK
A E 10 10 10 88 55 33 33 22 22 33 3 Grid System
P 7.5 7.5 7.5 7.5 7.5 7.5 7.5 66 55 55 55 55 5
10 C 250 175 0 0 0 0 0 0 0
F 0 0 0 -212.5 -275 -275 -300 -250 -200
P 7.5 7.5 7.5 7.5 7.5 5 5 6 6 6 6 5 5 5 5 5 5 5
E 10 10 10 9 9 5 5 3 3 3 3 2 2 2 2 3 3 3
B E 10 10 10 9 9 5 5 3 3 3 3 2 2 2 2 3 3 3
P 7.5 7.5 7.5 7.5 7.5 5 5 6 6 6 6 5 5 5 5 5 5 5
10 C 325 300 212.5 0 0 0 0 0 0
F 0 0 0 -25 -250 -250 -247.5 -245 -195
P 6 6 6 6 6 6 6 6 6 6 6 6 6 5.9 5.9 5.9 5.9 5.9 Legend
E 10 10 10 10 10 9 9 5 5 3 3 5 5 3 3 4 4 4
C E 10 10 19 10 10 9 9 5 5 3 3 5 5 3 3 4 4 4
P 6 6 6 6 6 6 6 6 6 6 6 7 7 5.9 5.9 5.9 5.9 5.9 E Existing
10 C 325 500 225 50 0 0 0 0 0 P Proposed
F 0 0 0 0 -150 -150 -115 -105 -80
P 6 6 6 6 6 6 6 6 6 6 6 5 5 4.7 4.7 4.7 4.7 4.7
C Cut
E 9 8 8 7 7 7 7 5 5 5 5 5 5 5 5 5 5 5 F Fill
D E 9 8 8 7 7 7 7 5 5 5 5 5 5 5 5 5 5 5
P 6 6 6 6 6 6 6 6 6 6 6 6 6 4.7 4.7 4.7 4.7 4.7
10 C 250 162.5 137.5 75 25 0 0 30 30
F 0 0 0 0 0 0 -10 0 0
P 6 6 6 6 6 6 6 6 6 5 5 5 5 4.7 4.7 4.7 4.7 4.7
E 9 8 8 7.5 7.5 8 8 7 7 7 7 5 5 5 5 5 5 5
E E 9 8 8 7.5 7.5 8 8 7 7 7 7 5 5 5 5 5 5 5
P 6 6 6 6 6 6 6 6 6 5 5 5 5 4.7 4.7 4.7 4.7 4.7
10 C 225 162.5 137.5 137.5 162.5 100 15 30 30
F 0 0 0 0 0 0 0 0 0
P 6 66 66 66 5.5 5.5 55 55 4.7 4.7 4.7 4.7 4.7
F E8 88 77 77 77 77 55 55 55 5
Feb 2010 49
4 DETAIL DESIGN EARTHWORK
Design Procedure
• Design Criteria
Feb 2010 50
4 DETAIL DESIGN EARTHWORK
Design Procedure
Earth Retaining Structure
Feb 2010 51
4 DETAIL DESIGN EARTHWORK
Split Levels
Feb 2010 52
4 DETAIL DESIGN EARTHWORK
Feb 2010 53
4 DETAIL DESIGN EARTHWORK
Feb 2010 54
4 DETAIL DESIGN EARTHWORK
Feb 2010 55
4 DETAIL DESIGN EARTHWORK
Feb 2010 56
4 DETAIL DESIGN EARTHWORK
Feb 2010 57
EARTHWORK
5 Authority
Compliance & Approvals
Feb 2010 58
5 AUTHORITY Compliance & Approvals EARTHWORK
Governing Law
Feb 2010 59
5 AUTHORITY Compliance & Approvals EARTHWORK
Submission Checklist
√ Copy of Letter of Appointment As Consulting Engineer
√ Copy of Geological Mapping (for hill dev) & Erosion Control Plan
Report
Feb 2010 60
5 AUTHORITY Compliance & Approvals EARTHWORK
SUBMITTING
PERSON
No
JPS
Yes
JKR
Approval
PTG
LC
Feb 2010 61
EARTHWORK
6 Construction
Feb 2010 62
6 CONSTRUCTION EARTHWORK
Earthwork Construction
• Construction of Hoarding
Feb 2010 63
6 CONSTRUCTION EARTHWORK
Earthwork Construction
• Review costruction
programme
Feb 2010 64
6 CONSTRUCTION
Feb 2010 65
6 CONSTRUCTION EARTHWORK
• General Instruction
• Construction Drawings
• Specifications Contract Document
• Bills of Quantities
• Compliance to Authority’s requirement
• Compaction 75%
Building footprints but to allow Suspended Floor slab design
Area not subject to buildings construction i.e fields, landscape, etc
Feb 2010 66
6 CONSTRUCTION EARTHWORK
Soil Compaction
Selection of types of compaction machinery Vs types of soil
Grid roller
In-land Development
Feb 2010 69
6 CONSTRUCTION EARTHWORK
Feb 2010 70
6 CONSTRUCTION EARTHWORK
Mandatory Hoarding
Feb 2010 71
6 CONSTRUCTION EARTHWORK
Feb 2010 72
6 CONSTRUCTION EARTHWORK
Feb 2010 73
6 CONSTRUCTION EARTHWORK
Feb 2010 74
6 CONSTRUCTION EARTHWORK
Feb 2010 75
6 CONSTRUCTION EARTHWORK
Feb 2010 77
EARTHWORK
7 Post - Construction
Feb 2010 78
7 POST - CONSTRUCTION EARTHWORK
Feb 2010 79
7 POST - CONSTRUCTION EARTHWORK
SUBMITTING
PERSON (SP)
No
JPS
Yes
JKR
Recommendation
PTG
Feb 2010 80
7 POST - CONSTRUCTION EARTHWORK
Post - CCC
• Final Account
Feb 2010 81
Thank You
Terima Kasih