CG Green Field FTTx Project Schedule

Neoteric Nepal Pvt. Ltd.

Project Start Date 9/1/2020 (Tuesday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead 31 Aug 2020 7 Sep 2020 14 Sep 2020 21 Sep 2020 28 Sep 2020 5 Oct 2020 12 Oct 2020 19 Oct 2020
31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
%
WBS TASK Team START END DAYS Note M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE
1 Survey + Acquisition -

1.1 POP Location / LC Tue 9/01/20 Wed 9/30/20 30 0%

1.2 Agg Ring Survey + Liasoning Tue 9/01/20 Thu 9/10/20 10 0%

1.3 Acc Ring Survey + Liasoning Tue 9/01/20 Thu 9/10/20 10 0%

1.4 OLT Ring Survey + Liasoning Tue 9/01/20 Thu 9/10/20 10 0%

1.5 Nea Power Acquisition Tue 9/01/20 Wed 9/30/20 30 0%


DG Location Survey/PAD Foundation For
1.6 Fri 9/11/20 Sun 9/20/20 10 0%
Agg/Acc
1.7 Earthing System Location Tue 9/15/20 Sun 10/04/20 20 0%

1.8 [Task] - 0%

2 Infra Work -

2.1 Earthing System Installation Thu 10/01/20 Fri 10/30/20 30 0%

2.2 Generator Installation Thu 10/01/20 Fri 10/30/20 30 0%

2.3 Power Plant Installation Thu 10/01/20 Tue 10/20/20 20 0%

2.4 Network Rack Installation with ODF/Rectifier Thu 10/01/20 Tue 10/20/20 20 0%

2.5 Air Conditioner Installation Thu 10/01/20 Tue 10/20/20 20 0%

2.6 Nea Power Installation Thu 10/01/20 Fri 10/30/20 30 0%

3 Installation Of Equipment -

3.1 OLT Installation/ Power ON Sun 11/01/20 Fri 11/20/20 20 0%

3.2 Route Connectivity to ODF-OLT Sun 11/01/20 Fri 11/20/20 20 0%

4 Fiber Laying -

4.1 Agg Ring A&B Sun 11/01/20 Sat 12/05/20 35 0%

4.2 Acc Ring 1 C&D Sun 11/01/20 Sat 11/14/20 14 0%

4.3 Acc Ring 2 C&D Mon 11/09/20 Sun 11/22/20 14 0%

4.4 Acc Ring 3 A&B Mon 11/16/20 Sun 11/29/20 14 0%

4.5 Acc Ring 4 C&D Mon 11/23/20 Sun 12/06/20 14 0%