Project Scope - Technical Brief & Project Cost Estimates
Project Scope - Technical Brief & Project Cost Estimates
Project Scope - Technical Brief & Project Cost Estimates
11 – 13 OCT 2016
Grand Blue Wave Hotel, Shah Alam, Selangor
OVERVIEW
Penerangan ringkas dan sepintas lalu terhadap Skop
Projek – Brif Teknikal (Technical Brief) dan Anggaran
Kos Projek (Project Cost Estimate) yang lazim bagi
projek-projek yang dilaksanakan JKR khususnya
projek Fasiliti Kesihatan untuk Kementerian Kesihatan
Malaysia.
Pengenalan
Proses Pengesahan Skop
Penyata Kehendak Kerajaan
(Keperluan Teknikal)
Anggaran Kos Projek
Isu-isu Berkaitan Skop & Kos
“Lesson Learnt”
1. Ar. HASNAH YUN
2. CKK IPJKR
PENGENALAN
SKOP + KOS
BPPP
MBOR
PROSES PERKHIDMATAN
TEKNIKAL
Penyediaan SOA
Pengesahan PDA
Need Statement
Senibina
Lain-Lain
(Geoteknik,
Sivil & Struktur
Alam Sekitar
dan etc) Brif
Teknikal
Elektrikal Mekanikal
• SERVICES
• MECHANICAL
• ELECTRICAL
• ICT
• EXTERNAL WORKS
• CIVIL WORKS
• LANDSCAPE Ar. HASNAH YUN
CKK IP JKR
PENYATA KEHENDAK
KERAJAAN
SKOP GEOTECHNICAL
GROUND TREATEMENT
RETAINING STRUCTURES
FOUNDATION
SKOP SIVIL
DRAINAGE SYSTEM
ROAD WORKS
SEWERAGE SYSTEM
SKOP STRUKTUR
SKOP ELEKTRICAL
1. REKABENTUK
KONSEP
• ZONING LAYOUT
• INTERDEPARTMENTAL LAYOUT
• INTRADEPARTMENTAL LAYOUT
2. REKABENTUK
AWALAN
• LOADED DRAWING
3. REKABENTUK
TERPERINCI
Ar. HASNAH YUN
• LUKISAN TENDER CKK IP JKR
Schedule of Accomodation (SOA)
Signages
Landscape
Material & Component List for HODT Architect’s Approval Ar. HASNAH YUN
CKK IP JKR
FINISHES
FINISHES Floor Finishes Sample : Vinyl Tiling Proposals
Proposal
Masterkey Zoning
Ar. HASNAH YUN
Material Approval CKK IP JKR
IRONMONGERY
Masterkey System & Schedule of Ironmongery
Internal signage
g) Directional Signage
h) Corporate Signage at all counters
i) Departmental Location Signage & sub location
sign
j) Statutory signage(e.g. escape routes, BOMBA,
fire exit, fire alarm - to be coordinate with M & E)
k) Mimic plans of all departments for every level
where required
l) Door sign – room titles, numbers, designations &
name slot (for officer’s room/ seminar/meeting
rooms – where applicable)
m) M & E
n) Notices
o) Room codes (on left top of door frame or other
suitable locations where there are no doors)
p) Mission & vision display panel
q) Floor location directory
r) Lift lobby directory.
s) Floor numbers at lift lobbies and staircases
where required.
t) Event board where required
u) Bed head numbers with 3 slots
v) Digital display (to be coordinate with M & E)
w) Pictogram/ symbol sign
x) Portable signage where required
y) Others
Kos Preliminaries
Kos Piling
Loose Furniture
Maintenance
GST 6%
Ar. HASNAH YUN
CKK IP JKR
ANGGARAN KOS PROJEK
KOS PEMBINAAN
Kesan :
Kesan :
Kesan :
ATDA yang diluluskan adalah tidak termasuk bayaran GST 6%. Ini
menyebabkan proses mengeluarkan Surat Setuju Terima (SST)
menjadi lewat.
Kesan :
2)Meningkatkan kos.
Implikasi:
Projek lambat diserah kepada
pelanggan
Ar. HASNAH YUN
CKK IP JKR