Professional Documents
Culture Documents
2D Assembly Procedure 20200830
2D Assembly Procedure 20200830
2D Assembly Procedure 20200830
H-042
1. OBJECTIVE
1.1. This Procedure is a document system for modeling process.
2. SCOPE
2.1. This Procedure must be applied on all types of production information project.
4. REFERENCE
4.1. Yard standard reference which have been completed with set-up codes /
Customization tribon.
4.2. Thickness disposition
4.3. Raw material standard
4.4. Connection and Gap table
4.5. Approval drawing
4.6. Standard Naming
5. EQUIPMENT
5.1. One set computer which has been installed with tribon.
6. MATERIAL
6.1. Green Colour Marker / Stabilo
7. PROCEDURE
English Version Page 1 of 2
1. Assembly form is using the standard form which has been pointed.
2. Standard default file is using standard default file which has been pointed.
3. Standard view used is looking Fwd, looking Port and Looking Bottom.
4. All the sections in construction drawing must appeared in 2D assembly, plus views which
not in 2D assembly (if needed) and all the details.
5. a. Giving Properties in Sectional plan :
1. Over all dimension.
2. Section’s Name
Section’s name for thing beneath the picture.
3. Dimension of fitting position
4. Thickness Disposition (for panel only)
b. Giving Properties in Part :
1. Post Number.
2. Size / Thickness.
3. Symbols.
4. Dimension Notch.
6. After all done print it out and submit to the project leader by attached the 2D assembly
request form for checking by QC.
7. Project leader will submit the 2D assembly to QC.
8. If there is any mistake QC will put remark by using Red marking and give comment, so
the person who in charge 2D assembly must revise the model (if there is related to model)
and revise the 2D assembly drawing.
9. If the revision has been done, so the 2D assembly drawing must be marked by using
Green marker on the previous Red marker and be submitted as item 7 & 8 by attached
the QC request form and the previous 2D Assembly Drawing.
10. If all the comments have been revised, so QC will give comment “Ready to Deliver” on
QC request form.