PTW Requester Name: PTW Requester Company: PTW Requester Contact No.
PALA RAM SEPCO III 0552037180
WHAT: (description of the activity to be completed – Attach document whenever necessary for further description)
Proposed Start Date and Time: End Date and Time Proposed Duration: (days)
From: To:
28 days
30-08-2020 07:00am 27-09-2020 07:00am
WHERE: (precise location(s) of the activity, including layout and drawing
HOW: (specific equipment, tools used) Add attachment for details e.g. Method Statement etc.)
Using Hand tools & power tools, such as drill machine, grinding machine etc.
HIGH-RISK ACTIVITIES
Additional Requirements / modifications if required (if PTW is accepted ) OR Reason for Rejection:
Fire blanket available Flash back arresters MSRA attached � � � Helmet, Glasses & Gloves � � �
✓ ✓ available
Correct type of Gas Mask Heat Resistant
Competent scaffold � � � Safety harnesses are 3rd � � �
available ✓ Clothing or leather ✓ team party certified
apron and sleeves
Other Other Scaffold structure � � � Safety Harness color � � �
✓ ✓ elements of sound steel coded
Confined Space Y N NA Y N NA material
MSRA attached � � � Entry log sheet � � � Any defective or � � � Minimum clearance from � � �
attached damaged scaffold overhead power lines and
Working party trained on � � � Means of � � � materials conductors if present
Confined space entry communication Approved drawing and � � � Work area identified with � � �
available design for scaffold barrier and safety signage
Safety signage display on � � � Safety Harness � � � Scaffolder hold valid � � � Ground condition are � � �
entry point certificates checked and safe
Trained watcher available � � � Gas Mask � � � Other � � � Other � � �
Safe Access and egress � � � Dust Mask � � � LOTOV-Electrical Y N NA Y N NA
Electric Tools with 110V � � � Required PPE � � � MSRA attached � � � Correct insulated Rubber � � �
Adequate Ventilation � � � Other � � � gloves are available
Marked up electric � � � Non-conductive shoes and � � �
Adequate Lighting � � � Other � � �
Diagram identifying Arc flash protective
Lifting Y N NA Y N NA required Isolations clothing available
attached
MSRA attached � � � Lifting equipment � � �
Main source or Breaker � � � Double insulated tools � � �
inspected
� � switched off available
Approved lifting plan � � Lifting equipment � �
attached 3rd party certified Adjacent live services � � � Non-conductive and Arc � � �
Critical lift � � � Tandem Lifting � � � identified and flash protective head
Protective Isolation protection available
Crane operator has valid � � � Lifting accessories � � � fixed in place where
license have ID number and required
color code
Fuse is removed if � � � Arc flash Eye protection � � �
Lifting accessories have 3rd � � � Rigging team 3rd � � �
present available
party certification party certification
Safety signage available � � � Exclusion zone identified � � �
Area free from overhead � � � Flagman available � � �
obstructions/live conductors Adequate lighting (lux) � � � Isolation key kept in safe � � �
Exclusion zone identified � � � Weather condition � � � for the task available place
satisfactory Lock and tag applied � � � Personal lock applied � � �
Correct Safety signs � � � Tagline available � � �
available LOTOV-Mechanical Y N NA Y N NA
Other � � � Other � � � MSRA attached � � � Helmet, Glass & Gloves � � �
Radiography available
Y N NA Y N NA Marked up Mechanical � � � All isolation points are correctly � � �
Diagram identifying identified and Padlocks applied
MSRA Attached Company by AP
� � � certification record � � � required Isolations
attached attached
Main source of energy shut � � � Safety signages displayed � � �
Marked up Drawing/map Competency of
attached � � � technician attached � � � off
Eye protection available � � � Isolation key kept in safe place � � �
Radiography Work Notice Means of
Provided prior to 24 hours � � � communication � � � Main energy sources are � � � All lines are isolated as per the � � �
available verified either locked or marked-up drawing
Radiography preparation Personal film badges blinded
form attached � � � available � � � Other: � � � Personal lock applied by RA � � �
B. Verification of Risks and Impacts control measures (to be completed by EPC Contractor EHS Authority)
I hereby confirm that the control measures defined in the Permit to Work and all attached documents comply with all applicable EHS
requirements and will effectively contribute to reduce risks and impacts to an acceptable level if they are strictly implemented.
Full name: Signature: Date and Time:
Mohamed Zakir Hussain 29-08-2020 @ 6:30 pm
C. Permit to Work Issuance (to be completed by the Issuing Authority and Receiving Authority)
ISSUING AUTHORITY statement: I hereby confirm that authorization is granted to the Receiving Authority to proceed with the activity
covered by the Permit within the period defined below and according to the EHS Requirements.
RECEIVING AUTHORITY statement: I hereby confirm that I have understood the content of the Permit, including the scope of work, its
limitations, the timing, the conditions, the control measures and EHS requirements.
VALIDITY PERIOD From (Date/Time): To (Date/Time):
(to be filled by Issuer) 30-08-2020 07:00 am 06-09-2020 07:00am
Issuing Authority Receiving Authority
Name: Signature: Name: Pala Ram Signature:
Yong Zhang
Release by: PTW Officer PTW Officer
Name:
E. Permit extension 1 (to be completed by the Issuing Authority and Receiving Authority)
VALIDITY PERIOD From (Date/Time): To (Date/Time):
(to be filled by Issuer)
Issuing Authority Receiving Authority
Note: A General PTW format to be used for all permit excluding Confined Space Permit (e.g. excavation, work at height, work in confined space,
lifting operation, hot work, work on/near live equipment, work for which LOTOV is required, Radiography, work in ATEX area, scaffold work, work
near/above/under water, use of hazardous substances, pressure test, commissioning and other works).
Project Nr : JAS101-TK4035P
Project title: RO Water Plant for Jebel Ali
Aluminium Smelter
Equipment Title:
Tag Nos.:
1. SCOPE......................................................................................... 3
2. REFERENCES................................................................................3
3. ABBREVIATION........................................................................... 3
6. RESPONSIBILITIES ...................................................................... 4
7. EHS Requirements...................................................................... 4
8. QUALITY..................................................................................... 5
13. ATTACHMENTS.......................................................................... 37
This Method statement outlines the procedures & requirements of MV and LV switchgear
installation.
2. REFERENCES
• Dubai Municipality code of Construction Safety Practices
• EGA Green Book
• Project EHS Manual
• Site Instructions
• ENG/SPE.04.10 – Specifications for Distribution & Motor Control Center
• Field Quality Plan (FQP)
3. ABBREVIATION
• Multi Meter
• Power tools
• Electrical Tool Box
• Hand tools
• Lifting accessories
• Trailers, HI- up truck, Pick-ups
• Crane, Fork lift
• Safety Helmet
• Safety Shoes
• Safety Glasses
• Safety Gloves
• Site dress
• Dust Mask
• Safety Harness
• Other task specific PPEs
7. EHS Requirements
• All personnel involved in the activities shall be inducted on site safety requirements.
• All personnel shall use site mandatory PPEs such as safety helmet, glasses, shoes, and etc.
Arc Flash PPE to be used as required. A minimum of Cat2 or higher, as per the requirements
of the work location and conditions, to be used as per EGA Standards
• Task specific PPEs as per MSDS to be worn such as ear protection, respiratory protection
etc.
• The workers must be trained on their tasks.
• Safe work environment, safe material and equipment to be provided.
• Adequate housekeeping and material management to be ensured.
• Adequate housekeeping to ensure during course of work and after work.
• Equipment should be maintained in an orderly manner and labeled in accordance with
statutory requirements and should be inspected as required.
• The workers shall be educated on work related hazards, risks, consequences and their
control measure via daily toolbox talk.
• All equipment/tools must be inspected and color coded.
• All efforts shall be made to keep the Environment clean.
8. QUALITY
• Testing and Inspection activities shall be done in accordance with the approved FQP.
• Necessary work permits shall be obtained by PTW RA from respective authorities prior to
commencement of work.
• Ensure that materials and accessories had been approved by EGA prior to use at site.
• Verify the site access and ensure that the interrelated work of the civil construction has
been finished and released, handed over and ready for safe work operation
• Check relevant items like PPE’s, access of working area, equipment etc. to ensure safety,
workability and environmental requirements.
• Review Specification and IFC drawings.
• TBT shall be conducted and carried out by the site in charged prior to starting the activities
to ensure working in a safe way.
• Ensure that the method statement for respective activity is approved.
• Attached the list of panels to be installed along with individual dimensions and weight
details for each.
9.2 Unloading the equipment and lifting equipment into loading bay:
9.3 Shifting the Equipment from loading bay to building installation place.
• Ensure that the location where the Switchgear Panel to be installed conforms to the
approved drawings and has been released for safe work execution. In case of any field
changes on locations to suit field requirements, it shall be reflected on drawings and
informed engineering department for As -Built. Any changes shall be informed and
approved by the client prior to proceed
• Installation place should be ready for switchgear installation: HVAC and lighting system
should be completed; room should be cleaned properly.
• Switchgear base support installed as per the general arrangement drawing.
• Drilling hole for installed anchoring bolt installation for switchgear base.
• All base supports must be installed on proper finished floor and level.
• Ensure that material type, rating, size, area classifications etc. confirms to project
specifications. Check for proper labels / identifications.
• Ensure that surfaces (i.e. walls, structures, flooring etc.) where it will be mounted are well
finished / painted. During installation necessary cover / protection to be provided on
openings not to be used on Substation/control room floors, walls, doors for safety purposes
and avoid entrance of dust.
• While moving to its final installation point, pallet trolley to be used and suitable wooden
boards to be inserted for painting protection.
• Base plate, panel frame, floor fixings etc. will be checked for level and location and fixing
points checked against their position on the respective panels. Cable sleeves and ducts will
be inspected to ensure correct line and location.
• The equipment will be inspected and checked against the relevant General Arrangement
drawing.
• Place / position / align Switchgears Panel as shown on the approved drawings. Drill and
insert anchors. Ensure proper type, size of anchors / bolts / washers is used.
• The side walls for the end cubicles have to be fastened. During fastening the side walls,
make sure that protective conductor connection is secured as per standards.
Hot Work-
A Hot work Permit shall be required to start in any hot work activity in construction site area. A careful
identification of these hazards shall be carried out as part of the risk assessment.
Hot work is defined as any work that generates sparks, flames and / or heat. Hot work includes, but is not
limited to, Drilling and any related heat-producing activities that could ignite combustible materials or
flammable atmospheres.
All personnel involved in hot work shall be trained (3rd party or in-house) on hot work hazards and
mitigation measures. Training shall be based on the use, maintenance and inspection of hot work
equipment.
The Contractor shall ensure the following precautions are taken before starting hot work;
• Remove any combustible materials (such as flammable liquids, wood, paper, textiles,
packaging or plastics) from within 10 meters of the work where possible;
• Ventilate spaces where vapours could accumulate, such as excavations, Confined Space
areas;
• Protect any combustible materials with fire blankets that cannot be moved, from close
contact with flame, heat, sparks or hot slag.
• Check that there are no combustible materials hidden behind/close which could be ignited,
particularly if prolonged welding or cutting is planned;
• Use guards or covers to prevent hot particles passing through openings;
• Maintain a continuous fire watch during the period of the work and keep fire extinguishers
nearby.
• Fire Watch shall be trained and made competent to tackle any incipient fire, initiate &
participate in emergency response.
Lifting Operation –
A lifting operation is an operation concerned with the lifting and lowering of a load. A load is the item or
items being lifted which could include a person or people. A lifting operation may be performed manually
or using lifting equipment. A lifting operation is a high-risk activity that shall be controlled through a safe
system of work. A careful identification of these hazards shall be carried out as part of the risk assessment.
A Permit to Work is a part of the safe system of work that shall be implemented strictly before starting the
activity.
• Suitable lifting equipment and tackles shall be selected as per task specification.
• 3rd party certified and colour coded lifting equipment and accessories shall be used.
• An approved lifting plan shall be attached with the permit.
• Competent operators and riggers with having 3rd party certification shall be allowed to
perform the activity.
• A dedicated lifting supervisor must be appointed and available during critical lifting
operations.
• Load weight and lifting zone shall be identified with barricades and safety signs and
flagman shall be deployed.
• Weather conditions shall be monitored; lift methods shall be re-assessed when wind speed
exceeds 35 km/h and adequate supervision and EHS coverage in place.
• All lifting activities shall stop when wind speed exceeds 38 km/h
• Lifting equipment shall park on even and stable ground.
• Lifting machinery shall be thoroughly examined and tested at least once in every period of
12 months.
• Lifting machinery used for the lifting of personal shall be thoroughly examined and tested
at least once in every period of 6 months.
• Jib cranes exceeding 5-tons lifting capacity shall be fitted with a load indicating device
allowing the operator to ensure that the machine is being used within its stated capacity.
• Taglines shall be used to control load swing.
• Standing, passing or working under a suspended load shall not be allowed.
Working at heights is work in which there is a potential of falling due to earth gravity pull from
anywhere to any place/ structure that is above ground, on the ground or below ground sufficient
to cause injury.
Most of the injuries during work at height involve falls from ladders, scaffolds, working platforms
and roof edges and through fragile roofs.
Work at height is a high-risk activity that shall be controlled through safe system of work. An
adequate risk assessment shall be carried out to identify the risks and control measures. A
systematic approach shall be adopted to protect the employees form fall;
First step to assess the workplace and the work itself. Fall hazard shall be eliminated wherever
possible by changing the sequence of the job, by working from ground level or by the use of
special tools and equipment.
Second step also requires assessing the workplace and work processes. If fall hazard cannot be
completely eliminated during the first step, management shall take a proactive approach to the
prevention of fall by improving installation of stairs, guardrails, scaffolds, and travel restriction
systems can ensure a safe work environment.
Third step is to use fall arresting equipment. Use fall arresting equipment, however, only after
determining that potential fall cannot be eliminated by changing work procedures or workplace or
collective protection cannot be used. Equipment such harnesses, fall arresters, can reduce the risk
of injury if a fall occurs.
• Task specific training shall be provided to the persons involved in work at height activity
that shall include the usage and maintenance of PPEs.
• Safety harnesses and other fall protection equipment, all arresters) shall be inspected by a
3rd party.
• A visual inspection shall be conducted by the user before each use of fall protection
equipment.
• Every quarter, a documented inspection by a competent person shall be performed on fall
arrest equipment by competent persons.
• Personnel performing jobs from an aerial lift, scissor lift or basket shall use a fall arrest
system attached to the basket.
• Climbing onto the middle rail, top rail or working from the outside of the basket shall not
be allowed.
• All work on flatbed trailers higher than 1.8m must be performed with full fall protection
such as - safety nets, fall arrest systems, or full guardrail protection where possible.
• Only safe and inspected portable ladder shall be used and single portable ladders shall not
be longer than 4m. When ascending or descending, the climber must face the ladder and
must keep three points of contact.
• Tools should be carried on a waist belt, in a shoulder bag or raised and lowered on a rope
to ensure a person climbing up/down a ladder maintains an adequate grip on the ladder.
• Platforms based on trestles should be fully boarded, adequately supported (at least one
support per 1.5 meter of board for standard scaffold boards) and provided with standard
edge protection. This all scaffolding shall be erected by EGA approved companies only by
using sound material. Lightweight Aluminium scaffolding shall not allow using on site. (ref-
EGA-Green Book-Sec-19.2.8)
• Mobile scaffold’s wheels shall be firmly fixed to the base of the uprights so that they cannot
fall out when the scaffold is being moved. The scaffold is never moved with anyone or
material on the working platform. While working on a mobile scaffold all the wheels at the
base shall be locked.
Electric Work
• Working hours will be 07:00-19:00 in general, but may continue 24 hours to fulfil site
requirements, if continuity of work required beyond the normal hours then it will be
communicated in advance.
• Special care to be taken when night shift work shall be carried out.
• Special permission to be obtained from client if required.
• All lighting arrangements to be carried out during day light, adequacy and continuity of
lighting to be ensured.
• As per UAE law mid-day break timing will be followed during summer season.
• All Personnel involved in the activities covered in the scope of this method statement shall
follow the requirements of Health & Safety Management Plan.
• All safety measures and Employer safety procedures shall be implemented.
• All drivers shall have valid license from UAE.
• All work permits (as applicable) shall be obtained prior to commencing any work.
• Barricades and Warning signs to be provided for excavation (if any) at site / work area.
• MSDS Sheet will be provided for all chemicals going to use
• HSE Officer will thoroughly monitor all site activities and advise safe work procedures on
site.
• Site team will be responsible for keeping away vehicles / equipment safely away from the
services and other concerned area.
• First Aid kit will be available always in the area.
13. ATTACHMENT
13.1 DRAWING:
13.2 LIST OF PACKING LIST:
13.3 MANUFACTURE INSTALLATION MANUAL:
Environment
Likelihood
No needs Effects complete
Severity
Total (L x S)
People
Asset
Asset additional
control
measures
sheet
01 Access to the EGA people & Unauthorized X Personal Injury Request to be submitted to EGA to obtain gate pass. 2 2 4 Yes
site, Site Contractor & access to site X X Property Site specific Induction training to be provided to the
and movement Equipment Follow the established rules as per the task requirements
preparation Inadequate PPEs damage Competent operator/ drivers to be appointed to operate the
vehicle.
activity.
02 Materials EGA people & Mechanical Personnel Selection of equipment as per task specification 2 2 4 Yes
handling with Contractor failure of injury PTW to be obtained before commencing the work if required.
fork lift truck equipment Material Equipment shall be inspected before entering at site.
Unsecure and damage Operators shall be certified 3rd party company and valid
gravity of Load weight should not exceed more than SWL capacity of the
material. equipment.
access of lights.
persons.
course of work.
03 Use of hand EGA people & Sharpe edge of X X X Personal Injury Trained and competent persons to be assigned to use hand 2 2 4 Yes
tools Contractor tools like cuts, hand tools.
Pinch point of injuries, eye Suitable and task specific tools to be selected.
prior to start.
course of work.
04 Use of Power Contractor Untrained X X X Equipment Pre-use inspection of tools, cables to be ensured 2 3 6 Yes
tools Operatives damage All electric powered tools to be equipped with Dead man or
equipment, tools body parts Use electric powered tool of rating 110V.
Damage hoses injury Power supply to power hand tools must be centre tapped
White finger Avoid cable joints and use proper socket and plugs,
Hearing loss Double eye protection to be used while using electric grinders.
Rotating parts of Tinnitus Nine inch grinder not allowed at site.
ensured.
tools/equipment.
05 Lifting Work EGA people & Mechanical X X X Injury to PTW requirement to be followed as per PTW procedure. 2 3 6 Yes
( Including Contractor failure of Crane person All lifting equipment to be selected as per task specification-
Offloading and operator damage EGA approved rental companies’ crane to be hired.
installation Parking of crane Damage to Crane must be having 3rd party certification of EGA approved
crane etc. ) unstable ground Crane to be inspected and sticker to fixed before entering at
surface. site.
devices failure Crane must be sited on level and well compacted ground and
Failure of All lifting accessories to be identified with unique ID, SWL and
Sandstorm and physical barricades and minimize the persons inside lifting
Rain) zone.
Waki-taki to be used.
colour.
conditions.
Lifting operation must be stopped if wind speed exceeds 35
KM/H even less if it the cane operator deems it necessary.
Work to be stopped in foggy climate until visibility clear.
Parking of Hiab Damage to Hiab to be inspected and sticker to fixed before entering at
ground surface. Operator must have UAE valid license, 3rd party competency
Lifting certificate.
equipment safety Hiab must be sited on level and well compacted ground and
accessories area.
lifting items All lifting accessories to be identified with unique ID, SWL and
Rain) loads.
zone.
Waki-taki to be used.
colour.
conditions.
activity
07 Stacking and EGA people & Poor stacking of x x x Personal The site layout will include adequate facilities for the material 2 2 4 Yes
Storage of Contractor material Injuries storage and stacking of material.
08 Work at Height EGA people & Damaged ladder x x Personal Injury Suitable ladders (Length) to be selected for the task, 2 3 6 Yes
(use of ladder) Contractor Incorrect type of Portable single ladder length should not more than 4 meters.
same time.
09 Work at height- Unsecured work x x Personal Site specific induction and specific work training to be 2 3 6 Yes
using scaffold EGA people & platform Injuries provided all personnel involved in work at height.
Contractor Fall of material Property PTW to be obtained before commencing the work.
Unauthorized Damage Platform based on trestle must be fully boarded with edge
Insufficient boards.
Adverse weather Certified Gin Wheel& lifting bags to be used to shift the
full body harness with double lanyards (EN: 361) and clipped
on with 100% tie off at all time while erecting the scaffold/
scaffolding Platform.
specification.
tag.
scaffolding.
10 Hot works EGA people & Contact with hot x x x Injury to PTW to be obtained 2 3 6 Yes
-Drilling Contractor metal/ surface person/cuts & Ensure all Hot work operations are carried out by trained,
Compressed gas hand crushed/ Check equipment before use-specifically electric cables,
Use of power Ensure any All combustible material to be removed from hot work areas if
Faulty equipment operations a Hot work area to be barricaded and identified by safety
produced by Eye Damage Ensure suitable fire extinguisher equipment and fire blankets
No-ionizing Inhalation Respiratory mask. Helmet Fire retardant overalls or apron, face
Trailing cable Skin burn Loose clothes, long hair and jewellery to be avoided.
Combustible Heat stress Earthing cable to be connected close to the welding point as
Excessive heat All power hand tools must be inspected by sepco iii
generated by hot
work.
11 Working in EGA people & High x x x Heat rashes, Cool and shaded area to be provided for rest. 2 2 4 Yes
Summer season Contractor atmospheric Heat cramps, Cold and fresh water along with Hydrolyte drink to be
High humidity Exhaustion Availability of water close to the work area will be ensured.
regulation.
course of work.
12 Night shift EGA people & Poor Lighting X X X Injuries to Proper illumination (lighting) to be provided to cover the work 2 2 4 Yes
activities Contractor Vehicle personnel due area with required Halogen lights/LED light/ mobile tower
Unprotected visibility No employee will be allowed to wear dark glasses during night
openings fall from same Wearing uniform with reflecting strips or reflecting vest.
Improper Vision level- lead to All openings and exactions will be closed or suitably guarded
management Health Vehicle to be fitted with audible alarm and reflecting bacon
issue-Fainting, lights.
to ensured.
Ensure the night shift workers are getting good sleep in day
time.
13 Manual Handling EGA people & Unidentified x x Avoid manual handling, if possible. 2 2 4 Yes
of material Contractor weight of load. Back Injury Eliminate where possible the requirement for manual handling,
grasp points and sprain. Assess the weight and nature of load prior to lift.
Poor body injury Proper manual handling techniques to be adopted and manual
The area should be level and free from any trip hazards.
14 Handling of EGA people & Incorrect storage x x x Grease and other hazardous liquids will be stored separately 2 2 4 Yes
hazardous Contractor facilities Fire in a bounded area.
substances Incompatibility of Explosion, Grease etc. to be provided with drip trays (110% in volume) to
Uncontrolled contamination Spill kit to be placed close to the storage area and Spill kits to
hazardous skin allergy Storage will be away from any source of ignition.
Storage area will be shaded to protect from direct sun and will
be well ventilated.
logs to be maintained.
requirements.
15 Working in EGA people & Sand Strom x x x Collapse of Stop work during heavy rain and sand storm until condition 2 2 4 Yes
adverse Weather Contractor High speed Wind equipment not safe.
conditions Heavy Rain Personal injury Assess the area after rain/high wind before commencing the
due to fog equipment or Stop work in foggy weather condition until visibility clear.
flying objects/ Stop all lifting operation when speed exceed 35 KMH .
material from All work at height activities to be assessed after heavy rain or
height wind.
Slip, trip and Material stored at height will be secured to avoid flying.
fall from same Site and UAE traffic rules to be followed in case of adverse
Vehicle/road team.
activity
16 Electrical Panel EGA people & Slip, trip and PTW to be obtained. 2 2 4 Yes
Installation Contractor fall from same Competent & certified electricians to handle all electrical
electrician Hand injury 110 V supply to be used where possible, If supply exceeds
Damaged hand such cuts, more the 110V, System to be equipped with 30mA RCD.
Sharp edge tools Electric shock Task specific tools to be selected and double insulated tools
switchgear room Equipment Damaged tool to be removed from work location immediately.
Other site and task specific PPEs to be worm all the time.
equipment.
pallet.
with LOTOV.
Ensure Permit is in
place and follow
LOTO procedures.
Only allow
authorized
personals to enter
the work area.
Unauthorized All equipment shall
Working near to access. be visually
EGA
Live Falling objects Personal injuries inspected prior to
17 Employees. X X 2 2 4 Yes
areas/operation Pinch points Electrocution installation to
Contractor.
areas. Electricity ensure that it is free
from any defects,
etc.
Ensure that all
equipment being
installed complies
with all relevant and
safety standards
and of the correct
Close supervision
from site
supervisors and
EHS personals
during the work
activity.
NOTES: WARNING
1. ALL PLANT FINISHED FLOOR ELEVATIONS (INSIDE BUILDING) WILL BE WITH RESPECT This drawing is an uncontrolled document. The controlled document is available electronically online.
th TO ELEVATION AS 0.0M, WHICH WILL BE CORRESPONDING TO (+)6.0M DMD. FINISHED
or
38
Please check the print date located at bottom right corner.
GRADE ELEVATION SHALL BE (-)0.300M WHICH WILL BE CORRESPONDING TO (+)5.7M
N
.
DMD.
43
A G Whilst it is intended that this drawing reflect the current As-built information as at the date of the
e 2. BUILDING DIMENSIONS AND EQUIPMENT SIZES SHOWN ARE PRELIMINARY AND SHALL
ru
95
BE FINALIZED AFTER RECEIPT OF ACTUAL VENDOR DETAILS. drawing, it may contain inaccuracies or omissions including those which arise from subsequent
T 46100
3. PANEL DOOR SHOWN IN THIS LAYOUT IS INDICATIVE ONLY. PANEL DOOR DETAILS works. This drawing should not be used as the sole source of information for any work which may
°
SHALL BE INDICATED IN ARCHITECTURAL DRAWING.
have implications for safety or operability (for example, buried services, electrical isolations).
N
B C D E F
Plant North Actual condition are to be verified by physical measures such as Cat scans, hand excavations
7500 8000 8000 7000 8000 7600 LEGENDS: and isolation tests.
8 8
FRD
A FOR MAN-MOVEMENT 3. All Coordinates are as per DUBAL / EMAL Grids.
ABBREVIATIONS:
2 DO NOT SCALE DRAWING. IF IN DOUBT, ASK
1000
MINIMUM DOOR
REQUIREMENT
FGL FINISHED GRADE LEVEL TOC TOP OF CONCRETE
1200W x 2160H KEY PLAN / GENERAL NOTES / LEGEND
FFL FINISHED FLOOR LEVEL DB DISTRIBUTION BOARD
815 1000 (TYP) TYPICAL FRD FIRE RATED DOOR
38
SST STATION SERVICE
TRANSFORMER SUB-07 (CLOUD MARK UP)
N
.43
e
ru
7800
95
EQUIPMENT LIST: T
°
7 7
N
PANELS IN ELECTRICAL ROOM:
Plant North
5 DELETED -
FFL
EL(-)3.050
6 400V HVAC MCC 00BJA02
4
10b 220V AC UPS-2 00BRV02
FRD
15 INERGEN/FIRE PROTECTION CYLINDERS (92 NOs) LATER 02. JAS101-TK4035P-M01-5005 GENERAL ARRANGEMENT FOR RO BUILDING AREA
[46 NOs WORKING & 46 NOs STAND BY]
03. JAS101-TK4035P-E18-6447 RO ELECTRICAL BUILDING RACEWAY LAYOUT
STAIRCASE-2
16 SST#01 00BFT01
04. JAS101-TK4035P-M19-6562 HVAC DUCT LAYOUT DRAWING RO ELECTRICAL AND CONTROL BUILDING
A G 17 SST#02 00BFT02
05. JAS101-TK4035P-C01-6224 ELECTRICAL & CONTROL BUILDING - RC DETAILS OF STAIRCASE
22 110V DC BATTERY FUSE BOX-1 [SYSTEM-1] 00BTF01 03. ARC DUCT WILL RELEASE THE ARC TO OUTSIDE. THE BUILDING EXTERIOR NEED AN ISOLATION ZONE,
AROUND THE END OF ARC DUCT WITH 3 METERS RADIUS. THE ZONE IS FORBIDDEN TO PASS.
27 AC UPS BATTERY-2 00BTA02 07 04/23/20 ISSUED FOR REVIEW KNS DSF PK SRW
28 AC UPS BATTERY FUSE BOX-1 00BTF04 06 01/22/20 ISSUED FOR REVIEW KNS DSF PK SRW
STAIRCASE-1
TYP)
2500
2595
2500
HANDRAIL RAMP UP
(
1
2
4
5
C)
M V VSD-
M V VSD-
2 PT
1 PT
2270 3830
SPARE
SPARE
1
2
4
3
B/
MV MV MV MV MV
SST-
1
SST-
SST-
SST-
2
BUS
C-
SECTI
E(
7800
C-
C-
UP
/
/
I
(SEE NOTE : 03) MINIMUM DOOR P09 -UNKNOWN PVC PIPE 200DIA
TYP)
1180
ARC PRESSURE
(
REQUIREMENT 15
RELIEF CHANNEL 1000W x 2160H
(
TYP)
TYP)
3 3
2335
2335
200
TYP)
1606
MINIMUM DOOR 3030 550
(
9a
15800
3 FOR DETAILS, REFER DWG 2. Revise and resubmit. Work may proceed subject to
1000W x 2160H
NO. JAS101-TK4035P-E18-6441 specifications and design
3981
1246
RAMP UP
4795 responsibility for errors in 5. As-Built certified
2075
11KV INCOMING CABLES
FROM CCPP PLANT FOR UP design and detailing as
DETAILS, REFER DWG NO. 6. Cancelled
8000
AC
MINIMUM DOOR 7. Incorporate Mark-ups & submit final As-Built or Certified
FFL REQUIREMENT
(
ACB
/C
3485 18
EDG I
JAS101-TK4035P-E18-6441
TYP)
6 P01 29
1204
1254
1204
1204
1299
1299
TYP)
TYP)
1654
1654
1654
1654
1654
1804
CABLE TRAY 30
1410
1410
14 P09
PERMANENT 13 14
1100
1100
1100
1100
(
CUT-OUT (TYP)
(
HANDRAIL 1000
(
718 24
WITH A GATE
1
7
2 4 2
20
31
2 HOURS FIRE P02 25 FRD
2 1513 ELECTRICAL FLOOR
1500
1500
1500
1500
3850
26
FFL (±) 0.0M FOR MAN-MOVEMENT 27 1000W x 2160H
THRU CAGE LADDER FROM
3 10
GROUND FLOOR TO BASEMENT
4 Project
P05 22
DN
3050
12
15
5 33 34 1100 1100
1100 1100 1400 1100 P07
19
RO Water Plant for Jebel Ali Aluminium Smelter
17
P08 1100
16 STAIRCASE-2
8122
1100
1100
1100
1100
19 18 17 16
36 35 Drawing Title
3600 1100 MINIMUM DOOR NEW ROAD
REQUIREMENT
1200W x 2160H
7750
1282
1282
A
ELECTRICAL BUILDING LAYOUT
1 1