HIGH RISE PROJECT: PIRAMAL ARANYA

PROJECT TRAINING | BATCH’15 High Rise Construction Sequence::


Figure shows the sequence of activities
Name of Project: Piramal Aranya Project Phases: for high rise core wall construction, the
Type of Project: High-rise Residential Phase1- North Tower including tower area in podium and basement levels, different level of works is followed on
Client: Piramal Realty Basement Structure & Podium Structure of Zone C and Zone B. site, as shown core wall runs above all
PMC: Mace Group. Phase 1 A- Basement Structure & Podium Structure of Zone E, EWS, Spindle then followed by surrounding columns
Contractor: L&T Construction. and Rehab/MHADA a Structures. which are also constructed with auto
Type of Contract: Item Rate Contract. Phase 2- South Tower including tower area in podium and basement levels. climbing system as their dimensions are
Building Configuration constant. After core wall and columns
Towers: 2 (North & South) 3 Basements + 7 Podiums + 66 Habitable Floors + 11 Service/Fire check & Amenities floors tower slabs are casted along with the
schedule of non-tower area. This type of
Spindle Structural Steel Building (G+4 Floors)
slab is known as stich slab.
EWS & Rehabilitation 22.Floors
Reinforcement & Formwork Sketches
Logistic Plan:

Activity Sketchup Model

Activity Logistic Reinforcement from Raft Wall Reinforcement


Construction Methodology:
ACS: It is used in Core wall and surrounding columns of Tower area, as it is high concrete structures volumetric wise which
makes it extremely fast, cost-effective and safe. The climbing units comprising wall formwork and platforms are moved
between floors of integrated hydraulic systems. The efficient sequence of operations facilitates a very high level of
productivity and exceptionally reduces floors cycle times.
Core Wall: Core walls are created with combination of walls. They are arranging like a core and generally located at the
geometric center of the building to void torsion. Also, core is used to install lifts and to accommodate services. In addition,
we can say that core walls are combination of shear walls. Walls are used to carry the lateral force exerted on the
structure due to wind, earthquake or any other lateral load. High strength concrete i.e. M80 is used for the core wall
construction. As observed in current location wind directions are found to be in north-west at maximum time of the year,
so is the placement of extended walls of core structure as per design requirement.

DOKA Lubeca Formwork Pockets for SKB


Element: Core Wall PERI Formwork

Location: Zone D / Tower Area Observations:


Core Wall Cycle Floor Cycle
Floor Height: 3.20 m Project Delay Reasons Affecting Scale 35 25
Concrete Grade: M80
30 20
Core walls are created with combination of walls. They 25
15
are arranging like a core and generally located at the 20
geometric center of the building to void torsion. 10
15
Also, core is used to install lifts and to accommodate
10 5
services. In addition, we can say that core walls are
combination of shear walls. Walls are used to carry the 5 0
1 2 3 4 5 6 7 8 9 10 11
lateral force exerted on the structure due to wind, 0
1 4 7 10 13 16 19 22 25 28 31 Cycle Days
earthquake or any other lateral load. High strength Drawing Labour Labour Procurement Staff Fabrication Crane

2019
concrete i.e. M80 is used for the core wall construction Clearance Deployment Productivity Issue Availability Availability Cycle Days