Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Mar 30, '20 Apr 6, '20

S M T W T F S S M T

1 INTERIOR WORK OF KITCHEN 56 days Tue 4/07/20 Tue 6/23/20

2 CLIENT 4 days Tue 4/07/20 Fri 4/10/20

3 Requirement study 1 day Tue 4/07/20 Tue 4/07/20

4 measurement of room 1 day Tue 4/07/20 Tue 4/07/20

5 Interior planning 1 day Wed 4/08/20 Wed 4/08/20 3;4

6 Estimation and Design 1 day Thu 4/09/20 Thu 4/09/20 5

7 Briefing with client 1 day Fri 4/10/20 Fri 4/10/20 6

8 Order conformation 1 day Fri 4/10/20 Fri 4/10/20 6

9 Work preparation 1 day Mon 4/13/20 Mon 4/13/20 8

10 PHASE 1 20 days Tue 4/14/20 Mon 5/11/20 2

11 BASE WORK 3 days Tue 4/14/20 Thu 4/16/20

12 Necessary floor protection installed 1 day Tue 4/14/20 Tue 4/14/20

13 Markings countertops, sinks, faucets, disp 1 day Wed 4/15/20 Wed 4/15/20 12

14 osals
Installation of party wall etc 1 day Thu 4/16/20 Thu 4/16/20 13

15 NECESSARY FRAMING WORK 5 days Fri 4/17/20 Thu 4/23/20 11

16 Install the necessary temporary walls and 1 day Fri 4/17/20 Fri 4/17/20

17 bracing
Install to support
new beams asceiling/roof
needed to-1support c 1 day Mon 4/20/20 Mon 4/20/20 16

18 eiling /new
Install roof ceiling joints and blocking as n 1 day Tue 4/21/20 Tue 4/21/20 17

19 eeded temporary walls and bracing


Remove 1 day Wed 4/22/20 Wed 4/22/20 18

20 Install joist angers and bracing as needed 1 day Thu 4/23/20 Thu 4/23/20 19

21 CONCRETE WORK 12 days Fri 4/24/20 Mon 5/11/20 15

22 Trench slab for necessary plumbing 1 day Fri 4/24/20 Fri 4/24/20

23 Trench slab for necessary electrical 1 day Mon 4/27/20 Mon 4/27/20 22

24 Plumbing work 3 days Tue 4/28/20 Thu 4/30/20 23

25 Electrical work 3 days Fri 5/01/20 Tue 5/05/20 24

26 Plumbing electrical inspection 1 day Wed 5/06/20 Wed 5/06/20 25

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: kitchen-interior Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/22/2020 12:02 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Mar 30, '20 Apr 6, '20

S M T W T F S S M T

27 Refill trenches with concrete and rebars o 1 day Thu 5/07/20 Thu 5/07/20 26

28 nce utilities
Vent have beenduct
hood (chimney) installed 1 day Fri 5/08/20 Fri 5/08/20 27

29 Install flooring 1 day Mon 5/11/20 Mon 5/11/20 28

30 PHASE 2 20 days Tue 5/12/20 Mon 6/08/20 10

31 New cabinet deliverables 1 day Tue 5/12/20 Tue 5/12/20

32 CABINET SETS 6 days Wed 5/13/20 Wed 5/20/20

33 Base cabinets 3 days Wed 5/13/20 Fri 5/15/20

34 Wall cabinets 3 days Mon 5/18/20 Wed 5/20/20

35 Install cabinet hardware 3 days Thu 5/21/20 Mon 5/25/20 32

36 Counter tops templated 2 days Tue 5/26/20 Wed 5/27/20 35

37 Appliance plugs installed 2 days Thu 5/28/20 Fri 5/29/20 36

38 Paint ceiling 2 days Mon 6/01/20 Tue 6/02/20 36;37;32;35

39 Paint walls 2 days Wed 6/03/20 Thu 6/04/20 38

40 New counter tops installed 1 day Fri 6/05/20 Fri 6/05/20 39

41 New blacksplashes installed 1 day Mon 6/08/20 Mon 6/08/20 40

42 PHASE 3 10 days Tue 6/09/20 Mon 6/22/20 30

43 Seal blacksplash installed 1 day Tue 6/09/20 Tue 6/09/20

44 Plumbing trimout completed 1 day Wed 6/10/20 Wed 6/10/20

45 Electrical trimout completed 1 day Thu 6/11/20 Thu 6/11/20

46 Vent hood (chimney) installed 1 day Fri 6/12/20 Fri 6/12/20

47 Appliances installed 1 day Mon 6/15/20 Mon 6/15/20 43;44;45;46

48 FLOORING 2 days Tue 6/16/20 Wed 6/17/20

49 Stain and finish flooring 2 days Tue 6/16/20 Wed 6/17/20

50 toe space (skirting) installed 1 day Thu 6/18/20 Thu 6/18/20 48

51 Inspection -P &E final 1 day Fri 6/19/20 Fri 6/19/20

52 Full inspection- Checking 1 day Mon 6/22/20 Mon 6/22/20

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: kitchen-interior Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/22/2020 12:02 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names Mar 30, '20 Apr 6, '20

S M T W T F S S M T

53 Overall checklist completed 1 day Mon 6/22/20 Mon 6/22/20

54 PROJECT COMPLETED 1 day Tue 6/23/20 Tue 6/23/20 2;10;30;42

55 1 day Tue 6/23/20 Tue 6/23/20

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: kitchen-interior Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/22/2020 12:02 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 3
Apr 13, '20 Apr 20, '20 Apr 27, '20 May 4, '20 May 11, '20 May 18, '20 May 25, '20 Jun 1,

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: kitchen-interior Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/22/2020 12:02 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 4
Apr 13, '20 Apr 20, '20 Apr 27, '20 May 4, '20 May 11, '20 May 18, '20 May 25, '20 Jun 1,

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: kitchen-interior Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/22/2020 12:02 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 5
Apr 13, '20 Apr 20, '20 Apr 27, '20 May 4, '20 May 11, '20 May 18, '20 May 25, '20 Jun 1,

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Summary Rollup Progress


Project: kitchen-interior Split External Tasks Inactive Summary Manual Summary Deadline
Date: 4/22/2020 12:02 AM Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 6

You might also like