Test Project Test Project: General Milestone General Milestone

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

TRIAL PROJECT Classic Schedule Layout 23-Sep-13 14:55

Activity ID Activity Name Original Start Finish Total Float


Qtr 3, 2013 Qtr 4, 2013 Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
test project 386 03-Aug-13 19-Feb-15 0
A
general milestone 0 03-Aug-13 03-Aug-13 0 03-Aug-13, general milestone

general 0 03-Aug-13 03-Aug-13 0 03-Aug-13, general


all floor 0 03-Aug-13 03-Aug-13 0 03-Aug-13, all floor
1400 PROJECT START 0 03-Aug-13 PROJECT START, 03-Aug-13

engineering work 319 03-Aug-13 13-Nov-14 67 13-Nov-14, engineering work

general 30 03-Aug-13 16-Sep-13 0 16-Sep-13, general


all floor 30 03-Aug-13 16-Sep-13 0 16-Sep-13, all floor
1730 MOBILZATION 30 03-Aug-13 16-Sep-13 0 MOBILZATION
civil shopdrawing 75 03-Aug-13 20-Nov-13 143 20-Nov-13, civil shopdrawing
underground 10 03-Aug-13 17-Aug-13 44 17-Aug-13, underground
1410 R.C SHOPDRAWING SUBMITAL 5 03-Aug-13 10-Aug-13 36 R.C SHOPDRAWING SUBMITAL
1420 R.C SHOPDRAWING APPROVAL 5 10-Aug-13 17-Aug-13 44 R.C SHOPDRAWING APPROVAL
basement floor 15 10-Aug-13 31-Aug-13 73 31-Aug-13, basement floor
1450 B.COL. SHOPDRAWING SUBMITAL 5 10-Aug-13 17-Aug-13 36 B.COL. SHOPDRAWING SUBMITAL
1460 B.COL SHOPDRAWING APPROVAL 5 17-Aug-13 24-Aug-13 71 B.COL SHOPD RAWING APPROVAL
1740 B.SLAB SHOPDRAWIN G SU BMITAL 5 17-Aug-13 24-Aug-13 36 B.SLAB SHOPDRAWING SUBMITAL
1750 B.SLAB SHOPDRAWIN G APPROVAL 5 24-Aug-13 31-Aug-13 73 B.SLAB SHOPDRAWIN G APPROVAL
ground floor 15 24-Aug-13 16-Sep-13 80 16-Sep-13, ground floor
1470 GR.COL. SHOPDRAWING SUBMITAL 5 24-Aug-13 31-Aug-13 36 GR.COL. SHOPDRAWING SUBMITAL
1480 GR.COL SHO PDRAWING APPROVAL 5 01-Sep-13 09-Sep-13 78 GR.COL SHO PD RAWING APPROVAL
1760 GR.SLAB SHOPDRAWING SUBMITAL 5 01-Sep-13 09-Sep-13 36 GR.SLAB SHOPDRAWING SUBMITAL
1770 GR.SLAB SHOPDRAWING APPROVAL 5 09-Sep-13 16-Sep-13 80 GR.SLAB SHOPDRAWING APPROVAL
1st floor 15 09-Sep-13 30-Sep-13 97 30-Sep-13, 1st floor
1490 1ST COL. SHOPDRAWING SUBMITAL 5 09-Sep-13 16-Sep-13 36 1ST COL. SHOPDRAWING SUBMITAL
1500 1ST COL SHOPDRAWING APPROVAL 5 16-Sep-13 23-Sep-13 95 1ST COL SHOPDRAWING APPROVAL
1780 1ST SLAB. SHOPDRAWING SUBMITAL 5 16-Sep-13 23-Sep-13 36 1ST SLAB. SHOPDRAWING SUBMITAL
1790 1ST SLAB SHOPDRAWING APPROVAL 5 23-Sep-13 30-Sep-13 97 1ST SLAB SHOPDRAWING APPROVAL
2nd floor 20 23-Sep-13 22-Oct-13 108 22-Oct-13, 2nd floor
1510 2ND COL. SHOPDRAWING SUBMITAL 5 23-Sep-13 30-Sep-13 36 2ND COL. SHOPDRAWING SUBMITAL
1520 2ND COL SHO PD RAWING APPROVAL 5 01-Oct-13 08-Oct-13 36 2ND COL SHO PD RAWING APPROVAL
1800 2ND SLAB. SHOPDRAWING SUBMITAL 5 08-Oct-13 15-Oct-13 36 2ND SLAB. SHOPDRAWING SUBMITAL
1810 2ND SLAB SHOPDRAWING APPROVAL 5 15-Oct-13 22-Oct-13 108 2ND SLAB SHOPDRAWING APPROVAL
3rd floor 15 15-Oct-13 06-Nov-13 124 06-Nov-13, 3rd floor
1530 3RD COL. SHOPDRAWING SUBMITAL 5 15-Oct-13 22-Oct-13 36 3RD COL. SHOPDRAWING SUBMITAL
1540 3RD CO. SHOPDRAWING APPROVAL 5 22-Oct-13 29-Oct-13 122 3RD CO. SHOPDRAWING APPROVAL
1820 3RD SLAB. SHOPDRAWING SUBMITAL 5 22-Oct-13 29-Oct-13 36 3RD SLAB. SHOPDRAWING SUBMITAL
1830 3RD SLAB SHOPDRAWING APPROVAL 5 30-Oct-13 06-Nov-13 124 3RD SLAB SHOPDRAWING APPROVAL
roof floor 15 30-Oct-13 20-Nov-13 143 20-Nov-13, roof floor
1550 ROOF COL. SHOPDRAWING SUBMITAL 5 30-Oct-13 06-Nov-13 36 ROOF COL. SHOPDRAWING SUBMITAL
1560 ROOF COL. SHOPDRAWING APPROVAL 5 06-Nov-13 13-Nov-13 148 ROOF COL. SHOPDRAWING APPROVAL
1840 ROOF SLAB SHOPDRAWING SUBMITAL 5 06-Nov-13 13-Nov-13 36 ROOF SLAB SHOPDRAWING SUBMITAL
1850 ROOF SLAB SHOPDRAWING APPROVAL 5 13-Nov-13 20-Nov-13 36 ROOF SLAB SHOPDRAWING APPROVAL
arch shopdrwaing 40 20-Nov-13 20-Jan-14 113 20-Jan-14, arch shopdrwaing
basement floor 10 20-Nov-13 07-Dec-13 36 07-Dec-13, basement floor
1860 B.MASONARY SHOPDRAWING SUBMITAL 5 20-Nov-13 27-Nov-13 36 B.MASONARY SHOPDRAWING SUBMITAL
1870 B.MASONARY SHOPDRAWING APPR OVAL 5 30-Nov-13 07-Dec-13 36 B.MASONARY SHOPDRAWING APPR OVAL
ground floor 10 30-Nov-13 14-Dec-13 39 14-Dec-13, ground floor
1880 GR.MASONARY SHOPDRAWING SUBMITAL 5 30-Nov-13 07-Dec-13 39 GR.MASONARY SHOPDRAWING SUBMITAL
1890 GR.MASONARY SHOPDRAWING APPROVAL 5 07-Dec-13 14-Dec-13 39 GR.MASONARY SHOPDRAWING APPROVAL
1st floor 10 07-Dec-13 21-Dec-13 68 21-Dec-13, 1st floor

Actual Level of Effort Remaining Work Milestone Page 1 of 6 TASK filter: All Activities
Resource Profile Filter:E01.excavator
Actual Work Critical Remaining Work summary
TRIAL PROJECT Classic Schedule Layout 23-Sep-13 14:55

Activity ID Activity Name Original Start Finish Total Float


Qtr 3, 2013 Qtr 4, 2013 Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1900 1ST.MASONARY SHOPDRAWING SUBMITAL 5 07-Dec-13 14-Dec-13 68 1ST.MASONARY SHOPDRAWING SUBMITAL
1910 1ST.MASONARY SHOPDRAWING APPROVAL 5 14-Dec-13 21-Dec-13 68 1ST.MASONARY SHOPDRAWING APPROVAL
2nd floor 10 21-Dec-13 06-Jan-14 68 06-Jan-14, 2nd floor
1920 2ND.MASONARY SHOPDRAWING SUBMITAL 5 21-Dec-13 29-Dec-13 68 2ND.MASONARY SHOPDRAWING SUBMITAL
1930 2ND.MASONARY SHOPDRAWING APPROVAL 5 30-Dec-13 06-Jan-14 68 2ND.MASONARY SHOPDRAWING APPROVAL
3rd floor 10 30-Dec-13 13-Jan-14 89 13-Jan-14, 3rd floor
1940 3RD.MASONARY SHOPDRAWING SUBMITAL 5 30-Dec-13 06-Jan-14 89 3RD.MASONARY SHOPDRAWING SUBMITAL
1950 3RD.MASONARY SHOPDRAWING APPROVAL 5 06-Jan-14 13-Jan-14 89 3RD.MASONARY SHOPDRAWING APPROVAL
roof floor 10 06-Jan-14 20-Jan-14 113 20-Jan-14, roof floor
1960 ROOF MASONARY SHOPDRAWING SUBMITAL 5 06-Jan-14 13-Jan-14 113 ROOF MASONARY SHOPDRAWING SUBMITAL
1970 ROOF MASONARY SHOPDRAWING APPROVAL 5 13-Jan-14 20-Jan-14 113 ROOF MASONARY SHOPDRAWING APPROVAL
civil material 28 16-Oct-13 26-Nov-13 307 26-Nov-13, civil material
all floor 28 16-Oct-13 26-Nov-13 307 26-Nov-13, all floor
1570 ISOLATION MATERIAL SUBMITAL 5 16-Oct-13 23-Oct-13 330 ISOLATION MATERIAL SUBMITAL
1580 ISOLATION MATERIAL APPROVAL 5 24-Oct-13 31-Oct-13 310 ISOLATION MATERIAL APPROVAL
1590 ISOLATION MATERIAL PROCURMENT 5 31-Oct-13 07-Nov-13 310 ISOLATION MATERIAL PROCURMENT
1600 ISOLATION MATERIAL PROCURMENT 10 07-Nov-13 21-Nov-13 310 ISOLATION MATERIAL PROCURMENT
1980 backfill MATERIAL SUBMITAL 5 21-Oct-13 28-Oct-13 312 backfill MATERIAL SUBMITAL
1990 backfill MATERIAL APPROVAL 5 28-Oct-13 04-Nov-13 312 backfill MATERIAL APPROVAL
2000 backfill MATERIAL PROCURMENT 5 05-Nov-13 12-Nov-13 312 backfill MATERIAL PROCURMENT
2010 backfill MATERIAL PROCURMENT 10 12-Nov-13 26-Nov-13 307 backfill MATERIAL PROCURMENT
finishing material 286 21-Sep-13 13-Nov-14 67 13-Nov-14, finishing material
all floor 286 21-Sep-13 13-Nov-14 67 13-Nov-14, all floor
1610 BRICK MATERIAL SUBMITAL 5 31-Oct-13 07-Nov-13 310 BRICK MATERIAL SUBMITAL
1620 BRICK MATERIAL APPROVAL 5 21-Sep-13 28-Sep-13 343 BRICK MATERIAL APPROVAL
1630 BRICK MATERIAL PROCURMENT 5 28-Sep-13 05-Oct-13 343 BRICK MATERIAL PROCURMENT
1640 BRICK MATERIAL DELIEVERY 30 05-Oct-13 18-Nov-13 313 BRICK MATERIAL DELIEVERY
1650 CERMIC MATERIAL SUBMITAL 5 07-Nov-13 14-Nov-13 310 CERMIC MATERIAL SUBMITAL
1660 CERMIC MATERIAL APPROVAL 5 31-Oct-13 07-Nov-13 320 CERMIC MATERIAL APPROVAL
1670 CERMIC MATERIAL PROCURMENT 5 07-Nov-13 14-Nov-13 315 CERMIC MATERIAL PROCURMENT
1680 CERMIC MATERIAL DELIEVERY 60 14-Nov-13 12-Feb-14 255 CERMIC MATERIAL DELIEVERY
1690 RED TILES MATERIAL SUBMITAL 5 01-Oct-14 08-Oct-14 92 RED TILES MATERIAL SUBMITAL
1700 RED TILES MATERIAL APPROVAL 5 08-Oct-14 15-Oct-14 87 RED TILES MATERIAL APPROVAL
1710 RED TILES MATERIAL PRO CURMENT 5 15-Oct-14 22-Oct-14 82 RED TILES MATERIAL PRO CURMENT
1720 RED TILES MATERIAL DELIEVERY 15 23-Oct-14 13-Nov-14 67 RED TILES MATERIAL DELIEVERY

substructure 56 16-Sep-13 08-Dec-13 0 08-Dec-13, substructure

earthwork 54 16-Sep-13 04-Dec-13 0 04-Dec-13, earthwork


underground 54 16-Sep-13 04-Dec-13 0 04-Dec-13, underground
10 EXCAVATION 10 16-Sep-13 30-Sep-13 0 EXCAVATION
20 REPLACMENT LAYER 7 01-Oct-13 10-Oct-13 0 REPLACMENT LAYER
30 BACKFILL 5 26-Nov-13 04-Dec-13 0 BACKFILL
concrete work 39 10-Oct-13 08-Dec-13 0 08-Dec-13, concrete work
underground 39 10-Oct-13 08-Dec-13 0 08-Dec-13, underground
40 P.C 7 10-Oct-13 21-Oct-13 0 P.C
50 R.C 12 21-Oct-13 07-Nov-13 0 R.C
60 NECK COLUMN 7 07-Nov-13 18-Nov-13 0 NECK COLUMN
70 SLAB ON GRADE 2 05-Dec-13 08-Dec-13 0 SLAB ON GRADE
masonary 3 18-Nov-13 21-Nov-13 0 21-Nov-13, masonary
underground 3 18-Nov-13 21-Nov-13 0 21-Nov-13, underground
100 BRICK WORK 3 18-Nov-13 21-Nov-13 0 BRICK WORK
thermal 3 23-Nov-13 26-Nov-13 0 26-Nov-13, thermal

Actual Level of Effort Remaining Work Milestone Page 2 of 6 TASK filter: All Activities
Resource Profile Filter:E01.excavator
Actual Work Critical Remaining Work summary
TRIAL PROJECT Classic Schedule Layout 23-Sep-13 14:55

Activity ID Activity Name Original Start Finish Total Float


Qtr 3, 2013 Qtr 4, 2013 Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
underground 3 23-Nov-13 26-Nov-13 0 26-Nov-13, underground
80 DAMP PROOFING 2 23-Nov-13 25-Nov-13 0 DAMP PROOFING
90 INSULATION 1 25-Nov-13 26-Nov-13 0 INSULATION

supersturcture 96 08-Dec-13 28-Apr-14 46 28-Apr-14, supersturcture

concrete work 96 08-Dec-13 28-Apr-14 46 28-Apr-14, concrete work


basement floor 17 08-Dec-13 02-Jan-14 0 02-Jan-14, basement floor
110 BASEMENT COLUMN 7 08-Dec-13 18-Dec-13 0 BASEMENT COLUMN
120 BASEMENT SLAB 10 18-Dec-13 02-Jan-14 0 BASEMENT SLAB
ground floor 18 02-Jan-14 29-Jan-14 0 29-Jan-14, ground floor
130 GROUND COLUMN 7 02-Jan-14 13-Jan-14 0 GROUND COLUMN
140 GROUND SLAB 11 13-Jan-14 29-Jan-14 0 GROUND SLAB
1st floor 17 29-Jan-14 23-Feb-14 9 23-Feb-14, 1st floor
150 1ST FLOOR COLUMN 7 29-Jan-14 08-Feb-14 9 1ST FLOOR COLUMN
160 1ST FLOOR SLAB 10 09-Feb-14 23-Feb-14 9 1ST FLOOR SLAB
2nd floor 17 23-Feb-14 19-Mar-14 18 19-Mar-14, 2nd floor
170 2ND FLOOR COLUMN 7 23-Feb-14 05-Mar-14 18 2ND FLOOR COLUMN
180 2ND FLOOR SLAB 10 05-Mar-14 19-Mar-14 18 2ND FLOOR SLAB
3rd floor 17 19-Mar-14 13-Apr-14 27 13-Apr-14, 3rd floor
190 3RD FLOOR COLUMN 7 19-Mar-14 30-Mar-14 27 3RD FLOOR COLUMN
200 3RD FLOOR SLAB 10 30-Mar-14 13-Apr-14 27 3RD FLOOR SLAB
roof floor 10 14-Apr-14 28-Apr-14 46 28-Apr-14, roof floor
210 ROOF FLOOR COLUMN 5 14-Apr-14 21-Apr-14 46 ROOF FLOOR COLUMN
220 ROOF FLOOR SLAB 5 21-Apr-14 28-Apr-14 46 ROOF FLOOR SLAB

rough finishes 203 29-Jan-14 A 20-Nov-14 62 20-Nov-14, rough finishes

concrete work 1 12-Aug-14 13-Aug-14 105 13-Aug-14, concrete work


roof floor 1 12-Aug-14 13-Aug-14 105 13-Aug-14, roof floor
580 P. C . SC REED 1 12-Aug-14 13-Aug-14 105 P. C. SC REED
masonary 63 29-Jan-14 A 30-Apr-14 46 30-Apr-14, masonary
basement floor 3 29-Jan-14 02-Feb-14 0 02-Feb-14, basement floor
230 B. FLOOR MASONARY WORK 3 29-Jan-14 02-Feb-14 0 B. FLOOR MASONARY WORK
ground floor 9 03-Feb-14 16-Feb-14 5 16-Feb-14, ground floor
280 GR. FLOOR MASONARY WORK 9 03-Feb-14 16-Feb-14 5 GR. FLOOR MASONARY WORK
1st floor 11 23-Feb-14 A 11-Mar-14 9 11-Mar-14, 1st floor
340 1ST FLOOR MASONARY WO RK 11 23-Feb-14 A 11-Mar-14 9 1ST FLOOR MASONARY WO RK
2nd floor 10 19-Mar-14 03-Apr-14 18 03-Apr-14, 2nd floor
400 2ND FLOOR MASONARY WORK 10 19-Mar-14 03-Apr-14 18 2ND FLOOR MASONARY WORK
3rd floor 10 14-Apr-14 28-Apr-14 27 28-Apr-14, 3rd floor
460 3RD FLOOR MASONARY WORK 10 14-Apr-14 28-Apr-14 27 3RD FLOOR MASONARY WORK
roof floor 2 28-Apr-14 30-Apr-14 46 30-Apr-14, roof floor
520 ROOF FLOOR MASONARY WORK 2 28-Apr-14 30-Apr-14 46 ROOF FLOOR MASONARY WORK
finshes 200 03-Feb-14 20-Nov-14 62 20-Nov-14, finshes
basement floor 62 03-Feb-14 04-May-14 154 04-May-14, basement floor
240 WINDOWS&DOORS 14 03-Feb-14 23-Feb-14 33 WINDOWS&DOORS
250 PLASTER 14 12-Feb-14 05-Mar-14 0 PLASTER
260 CERMIC 5 12-Feb-14 19-Feb-14 204 CERMIC
270 INTIAL PAINTING 12 16-Apr-14 04-May-14 45 INTIAL PAINTING
ground floor 83 20-Feb-14 21-Jun-14 131 21-Jun-14, ground floor
290 WINDOWS&DOORS 14 23-Feb-14 15-Mar-14 33 WINDOWS&DOORS
300 PLASTER 20 05-Mar-14 03-Apr-14 0 PLASTER
310 MATEL LATH 4 10-Apr-14 16-Apr-14 45 MATEL LATH
320 CERMIC 10 20-Feb-14 06-Mar-14 204 CERMIC
330 INTIAL PAINTING 20 22-May-14 21-Jun-14 33 INTIAL PAINTING

Actual Level of Effort Remaining Work Milestone Page 3 of 6 TASK filter: All Activities
Resource Profile Filter:E01.excavator
Actual Work Critical Remaining Work summary
TRIAL PROJECT Classic Schedule Layout 23-Sep-13 14:55

Activity ID Activity Name Original Start Finish Total Float


Qtr 3, 2013 Qtr 4, 2013 Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1st floor 88 16-Mar-14 21-Jul-14 120 21-Jul-14, 1st floor
350 WINDOWS&DOORS 14 16-Mar-14 05-Apr-14 33 WINDOWS&DOORS
360 PLASTER 25 03-Apr-14 10-May-14 0 PLASTER
370 MATEL LATH 4 17-May-14 22-May-14 33 MATEL LATH
380 CERMIC 10 22-Mar-14 05-Apr-14 194 CERMIC
390 INTIAL PAINTING 15 30-Jun-14 21-Jul-14 29 INTIAL PAINTING
2nd floor 98 05-Apr-14 25-Aug-14 106 25-Aug-14, 2nd floor
410 WINDOWS&DOORS 14 05-Apr-14 24-Apr-14 33 WINDOWS&DOORS
420 PLASTER 26 10-May-14 16-Jun-14 0 PLASTER
430 MATEL LATH 4 24-Jun-14 30-Jun-14 29 MATEL LATH
440 CERMIC 10 14-Apr-14 28-Apr-14 188 CERMIC
450 INTIAL PAINTING 16 03-Aug-14 25-Aug-14 21 INTIAL PAINTING
3rd floor 91 28-Apr-14 08-Sep-14 108 08-Sep-14, 3rd floor
470 WINDOWS&DOORS 14 28-Apr-14 18-May-14 31 WINDOWS&DOORS
480 PLASTER 23 17-Jun-14 20-Jul-14 0 PLASTER
490 MATEL LATH 4 28-Jul-14 02-Aug-14 21 MATEL LATH
500 CERMIC 11 08-May-14 24-May-14 181 CERMIC
510 INTIAL PAINTING 9 26-Aug-14 08-Sep-14 21 INTIAL PAINTING
roof floor 60 19-May-14 13-Aug-14 29 13-Aug-14, roof floor
530 WINDOWS&DOORS 7 19-May-14 28-May-14 34 WINDOWS&DOORS
540 PLASTER 8 20-Jul-14 31-Jul-14 0 PLASTER
550 MATEL LATH 4 09-Aug-14 13-Aug-14 29 MATEL LATH
enterance & staircase 17 31-Jul-14 25-Aug-14 0 25-Aug-14, enterance & staircase
590 PLASTER 17 31-Jul-14 25-Aug-14 0 PLASTER
facades 60 26-Aug-14 20-Nov-14 62 20-Nov-14, facades
600 CERETAL WORK 14 26-Aug-14 15-Sep-14 103 CERETAL WORK
610 PLASTER 55 26-Aug-14 13-Nov-14 0 PLASTER
620 RED TILES 5 13-Nov-14 20-Nov-14 62 RED TILES
thermal 8 31-Jul-14 12-Aug-14 105 12-Aug-14, thermal
roof floor 8 31-Jul-14 12-Aug-14 105 12-Aug-14, roof floor
560 PROOFING 4 31-Jul-14 06-Aug-14 105 PROOFING
570 THERMAL INSULATION 4 06-Aug-14 12-Aug-14 105 THERMAL INSULATION

final finishes 183 04-May-14 26-Jan-15 17 26-Jan-15, final fini

finshes 183 04-May-14 26-Jan-15 17 26-Jan-15, finshes


basement floor 24 04-May-14 08-Jun-14 100 08-Jun-14, basement floor
630 WINDOWS&DOORS 14 04-May-14 24-May-14 100 WINDOWS&DOORS
640 PAINTING 10 25-May-14 08-Jun-14 100 PAINTING
ground floor 60 04-May-14 30-Jul-14 75 30-Jul-14, ground floor
650 WOODEN FLOORS 7 03-Jun-14 14-Jun-14 45 WOODEN FLOORS
660 MARBLE FLOORS 10 03-Jun-14 18-Jun-14 45 MARBLE FLOORS
670 FINISHING FLOORS 7 03-Jun-14 14-Jun-14 45 FINISHING FLOORS
680 ALUMINUM 21 04-May-14 03-Jun-14 45 ALUMINUM
690 DOOR 21 14-Jun-14 14-Jul-14 45 DOOR
700 PAINTING 11 14-Jul-14 30-Jul-14 75 PAINTING
1st floor 59 21-Jun-14 15-Sep-14 53 15-Sep-14, 1st floor
710 WOODEN FLOORS 14 22-Jul-14 11-Aug-14 33 WOODEN FLOORS
720 MARBLE FLOORS 7 22-Jul-14 31-Jul-14 33 MARBLE FLOORS
730 FINISHING FLOORS 7 22-Jul-14 31-Jul-14 33 FINISHING FLOORS
740 ALUMINUM 21 21-Jun-14 21-Jul-14 33 ALUMINUM
750 DOOR 21 31-Jul-14 31-Aug-14 33 DOOR
760 PAINTING 10 01-Sep-14 15-Sep-14 53 PAINTING
2nd floor 60 22-Jul-14 16-Oct-14 42 16-Oct-14, 2nd floor

Actual Level of Effort Remaining Work Milestone Page 4 of 6 TASK filter: All Activities
Resource Profile Filter:E01.excavator
Actual Work Critical Remaining Work summary
TRIAL PROJECT Classic Schedule Layout 23-Sep-13 14:55

Activity ID Activity Name Original Start Finish Total Float


Qtr 3, 2013 Qtr 4, 2013 Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
770 WOODEN FLOORS 14 21-Aug-14 10-Sep-14 33 WOODEN FLOORS
780 MARBLE FLOORS 5 21-Aug-14 28-Aug-14 33 MARBLE FLOORS
790 FINISHING FLOORS 7 21-Aug-14 31-Aug-14 33 FINISHING FLOORS
800 ALUMINUM 21 22-Jul-14 21-Aug-14 33 ALUMINUM
810 DOOR 21 01-Sep-14 01-Oct-14 33 DOOR
820 PAINTING 11 01-Oct-14 16-Oct-14 42 PAINTING
3rd floor 58 08-Sep-14 01-Dec-14 21 01-Dec-14, 3rd floor
830 WOODEN FLOORS 14 08-Oct-14 28-Oct-14 21 WOODEN FLOORS
840 MARBLE FLOORS 5 08-Oct-14 15-Oct-14 21 MARBLE FLOORS
850 FINISHING FLOORS 7 08-Oct-14 19-Oct-14 21 FINISHING FLOORS
860 ALUMINUM 21 08-Sep-14 08-Oct-14 21 ALUMINUM
870 DOOR 21 19-Oct-14 18-Nov-14 21 DOOR
880 PAINTING 9 18-Nov-14 01-Dec-14 21 PAINTING
roof floor 73 14-Aug-14 29-Nov-14 57 29-Nov-14, roof floor
890 CEMENT TILES 9 14-Aug-14 27-Aug-14 105 CEMENT TILES
900 FACADES PLASTER 9 27-Aug-14 09-Sep-14 105 FACADES PLASTER
910 DOOR 7 18-Nov-14 29-Nov-14 57 DOOR
enterance & staircase 48 26-Jul-14 04-Oct-14 71 04-Oct-14, enterance & staircase
920 CERETAL WORK 21 26-Jul-14 25-Aug-14 0 CERETAL WORK
930 PLASTER COLORD 13 02-Sep-14 21-Sep-14 71 PLASTER COLORD
940 MARBLE FLOORS 8 21-Sep-14 02-Oct-14 71 MARBLE FLOORS
950 MARBLE STAIRS 9 21-Sep-14 04-Oct-14 71 MARBLE STAIRS
facades 45 22-Nov-14 26-Jan-15 0 26-Jan-15, facades
960 FACADES PLASTER DAHARA 40 22-Nov-14 18-Jan-15 0 FACADES PLASTER
970 BARGOLAS 5 19-Jan-15 26-Jan-15 0 BARGOLAS
all floor 0 26-Jan-15 26-Jan-15 17 26-Jan-15, all floor
1360 final fisihes closeout 0 26-Jan-15 26-Jan-15 17 final fisihes closeou

mechincal works 81 03-Feb-14 01-Jun-14 181 01-Jun-14, mechincal works

mechincal 81 03-Feb-14 01-Jun-14 181 01-Jun-14, mechincal


basement floor 15 03-Feb-14 24-Feb-14 233 24-Feb-14, basement floor
980 INTIAL SAINTARY WORK 7 03-Feb-14 12-Feb-14 0 INTIAL SAINTARY WORK
990 FINAL SAINTARY WORK 3 20-Feb-14 24-Feb-14 233 FINAL SAINTARY WORK
ground floor 16 16-Feb-14 11-Mar-14 226 11-Mar-14, ground floor
1000 INTIAL SAINTARY WORK 7 16-Feb-14 25-Feb-14 5 INTIAL SAINTARY WORK
1010 FINAL SAINTARY WORK 3 06-Mar-14 11-Mar-14 226 FINAL SAINTARY WORK
1st floor 20 11-Mar-14 09-Apr-14 209 09-Apr-14, 1st floor
1020 INTIAL SAINTARY WORK 7 11-Mar-14 20-Mar-14 9 INTIAL SAINTARY WORK
1030 FINAL SAINTARY WORK 3 05-Apr-14 09-Apr-14 209 FINAL SAINTARY WORK
2nd floor 20 03-Apr-14 03-May-14 196 03-May-14, 2nd floor
1040 INTIAL SAINTARY WORK 7 03-Apr-14 13-Apr-14 18 INTIAL SAINTARY WORK
1050 FINAL SAINTARY WORK 3 28-Apr-14 03-May-14 196 FINAL SAINTARY WORK
3rd floor 21 28-Apr-14 28-May-14 181 28-May-14, 3rd floor
1060 INTIAL SAINTARY WORK 7 28-Apr-14 08-May-14 27 INTIAL SAINTARY WORK
1070 FINAL SAINTARY WORK 3 25-May-14 28-May-14 181 FINAL SAINTARY WORK
roof floor 16 08-May-14 01-Jun-14 181 01-Jun-14, roof floor
1080 INTIAL SAINTARY WORK 3 08-May-14 12-May-14 47 INTIAL SAINTARY WORK
1090 FINAL SAINTARY WORK 2 28-May-14 01-Jun-14 181 FINAL SAINTARY WORK
all floor 0 01-Jun-14 01-Jun-14 181 01-Jun-14, all floor
1370 mechincal closeout 0 01-Jun-14 01-Jun-14 181 mechincal closeout

electrical work 241 23-Feb-14 09-Feb-15 0 09-Feb-15, ele

electrical 241 23-Feb-14 09-Feb-15 0 09-Feb-15, ele


basement floor 79 23-Feb-14 18-Jun-14 105 18-Jun-14, basement floor

Actual Level of Effort Remaining Work Milestone Page 5 of 6 TASK filter: All Activities
Resource Profile Filter:E01.excavator
Actual Work Critical Remaining Work summary
TRIAL PROJECT Classic Schedule Layout 23-Sep-13 14:55

Activity ID Activity Name Original Start Finish Total Float


Qtr 3, 2013 Qtr 4, 2013 Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1100 1ST ELECTRICAL FIX 10 23-Feb-14 09-Mar-14 49 1ST ELECTRICAL FIX
1110 2ND ELECTRICAL FIX 5 05-Mar-14 12-Mar-14 60 2ND ELECTRICAL FIX
1120 FINAL ELECTRICAL FIX 7 08-Jun-14 18-Jun-14 105 FINAL ELECTRICAL FIX
ground floor 104 16-Mar-14 13-Aug-14 76 13-Aug-14, ground floor
1130 1ST ELECTRICAL FIX 10 16-Mar-14 30-Mar-14 45 1ST ELECTRICAL FIX
1140 2ND ELECTRICAL FIX 5 03-Apr-14 10-Apr-14 45 2ND ELECTRICAL FIX
1160 FINAL ELECTRICAL FIX 10 30-Jul-14 13-Aug-14 76 FINAL ELECTRICAL FIX
1st floor 122 05-Apr-14 29-Sep-14 54 29-Sep-14, 1st floor
1170 1ST ELECTRICAL FIX 10 05-Apr-14 19-Apr-14 41 1ST ELECTRICAL FIX
1180 2ND ELECTRICAL FIX 5 10-May-14 17-May-14 33 2ND ELECTRICAL FIX
1190 FINAL ELECTRICAL FIX 10 15-Sep-14 29-Sep-14 54 FINAL ELECTRICAL FIX
2nd floor 130 26-Apr-14 01-Nov-14 42 01-Nov-14, 2nd floor
1200 1ST ELECTRICAL FIX 10 26-Apr-14 10-May-14 37 1ST ELECTRICAL FIX
1210 2ND ELECTRICAL FIX 5 17-Jun-14 24-Jun-14 29 2ND ELECTRICAL FIX
1220 FINAL ELECTRICAL FIX 10 18-Oct-14 01-Nov-14 42 FINAL ELECTRICAL FIX
3rd floor 145 19-May-14 16-Dec-14 21 16-Dec-14, 3rd floor
1230 1ST ELECTRICAL FIX 10 19-May-14 02-Jun-14 31 1ST ELECTRICAL FIX
1240 2ND ELECTRICAL FIX 5 20-Jul-14 27-Jul-14 21 2ND ELECTRICAL FIX
1250 FINAL ELECTRICAL FIX 10 01-Dec-14 16-Dec-14 21 FINAL ELECTRICAL FIX
roof floor 142 02-Jun-14 25-Dec-14 21 25-Dec-14, roof floor
1260 1ST ELECTRICAL FIX 10 02-Jun-14 16-Jun-14 31 1ST ELECTRICAL FIX
1270 2ND ELECTRICAL FIX 5 31-Jul-14 07-Aug-14 29 2ND ELECTRICAL FIX
1280 FINAL ELECTRICAL FIX 7 16-Dec-14 25-Dec-14 21 FINAL ELECTRICAL FIX
enterance & staircase 163 17-Jun-14 09-Feb-15 0 09-Feb-15, ent
1290 1ST ELECTRICAL FIX 10 17-Jun-14 01-Jul-14 31 1ST ELECTRICAL FIX
1300 2ND ELECTRICAL FIX 5 26-Aug-14 02-Sep-14 50 2ND ELECTRICAL FIX
1310 FINAL ELECTRICAL FIX 10 26-Jan-15 09-Feb-15 0 FINAL ELECTR
facades 102 01-Jul-14 26-Nov-14 51 26-Nov-14, facades
1320 1ST ELECTRICAL FIX 7 01-Jul-14 12-Jul-14 31 1ST ELECTRICAL FIX
1330 2ND ELECTRICAL FIX 5 13-Nov-14 20-Nov-14 0 2ND ELECTRICAL FIX
1340 FINAL ELECTRICAL FIX 4 22-Nov-14 26-Nov-14 51 FINAL ELECTRICAL FIX
all floor 0 09-Feb-15 09-Feb-15 0 09-Feb-15, all f
1380 electrical closeout 0 09-Feb-15 09-Feb-15 0 electrical closeo

confeying system 7 09-Feb-15 19-Feb-15 0

elevator 7 09-Feb-15 19-Feb-15 0


all floor 7 09-Feb-15 19-Feb-15 0
1350 ELEVATOR 7 09-Feb-15 19-Feb-15 0
1390 confeying closeout 0 19-Feb-15 19-Feb-15 0

Actual Level of Effort Remaining Work Milestone Page 6 of 6 TASK filter: All Activities
Resource Profile Filter:E01.excavator
Actual Work Critical Remaining Work summary