Contract No ABC /XY/YY/ZZ

Client Logo Project Name , Location Customer Logo


Overall Manpower Deployment Summary

Status as of - 31-Aug-08
MONTHWISE DEVELOPMENT
SL No. Discipline/ Category Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09
DIRECT MANPOWER
1 Process Plan 0.5 1.5 4.0 5.5 5.5 5.0 2.0 2.0 1.0
Actual 0.5 2.0 4.0 6.5
2 Marine Engineering Plan 0.3 1.0 1.5 1.0 1.0 1.0 1.5 2.5 2.5 1.0 1.0 0.5
Actual 0.3 1.0 1.0 2.0
3 Smms (Corrosion Egr) Plan 0.5 0.5 0.5 0.5 1.0 1.0 0.5
Actual 0.8 0.8
4 Health, Safety & Environment Plan 0.5 0.5 1.0 1.5 1.5 0.5 0.5
Actual 0.5 0.8 0.3 0.5
5 Pipeline Plan 0.5 2.5 3.0 3.0 6.0 9.0 9.0 9.0 4.0 3.0 2.0 0.5
Actual 1.0 2.0 4.0 6.0
6 Piping Plan 0.5 1.0 2.0 2.0 4.0 4.0 4.0 4.0 2.5 2.0 0.5
Actual 0.5 0.5 1.3 2.0
7 Mechanical Equipment Plan 1.0 1.5 1.5 1.0 0.5 0.5
Actual
8 General Civil Plan 0.5 1.0 2.5 2.5 4.0 4.0 4.0 5.0 5.0 3.0 1.0 0.5
Actual 0.3 0.5 1.8 3.0
9 Structural Plan 0.5 1.0 2.0 2.0 1.0 1.0 2.5 2.5 2.5 2.5 1.0
Actual 0.3 0.8 1.8 1.5
10 Architectural Plan 0.5 1.0 1.0 1.0 3.0 3.0 1.0 1.0
Actual 0.3 0.5 1.0
11 Landscape Plan 1.0 1.0 1.0 1.0 1.0 2.0 2.0 1.0 1.0 0.5
Actual 1.0 1.0 0.5
12 Electrical Plan 0.5 0.5 2.0 5.0 5.0 5.0 5.0 5.0 1.0 0.5
Actual 0.3 0.5
13 Instrumentation Plan 0.5 0.5 0.5 0.5 1.0 2.0 5.0 5.0 5.0 2.5 1.0 0.5
Actual 0.3 0.3 1.0 1.0
14 Scada & Telecom Plan 0.5 0.5 0.5 2.0 2.0 2.5 2.5 2.0 0.5 0.5
Actual 0.3 0.3 1.5 1.8
15 Draftsmen Plan 2.0 2.0 3.0 3.0 5.0 7.0 7.0 5.0 3.0 3.0 2.0 2.0
Actual 1.0 3.0 3.0
16 Procurement Plan 1.0 1.0 2.0 2.0 4.0 4.0 7.0 7.0 7.0 5.0 5.0 4.0 2.0 1.0 1.0
Actual 1.0 1.0 2.0
17 Construction Supervisor / Engin Plan 2.0 2.0 4.0 4.0 6.0 8.0 8.0 10.0 10.0 10.0 8.0 8.0 6.0 4.0 2.0
Actual 2.0
18 Skilled Workers Plan 5.0 5.0 10.0 10.0 20.0 20.0 20.0 35.0 35.0 35.0 30.0 30.0 20.0 10.0 5.0
Actual 4.0
19 Un-Skilled Workers Plan 10.0 10.0 20.0 20.0 40.0 40.0 40.0 60.0 60.0 60.0 50.0 50.0 40.0 30.0 10.0
Actual
20 Other Technical Staff Plan 2.0 2.0 2.0 3.0 3.0 3.0 3.0 1.0 1.0 1.0 1.0 1.0
Actual 2.0 3.0
3.8 15.5 23.5 45.0 55.5 83.0 91.5 128.5 115.0 101.0 123.0 115.5 112.0 90.0 89.0 67.0 44.0 17.0
Sub-Total (Direct Manpower)
Actual 4.0 11.0 25.0 41.0
In-Direct Manpower
1 Contract Management Plan 0.5 1.0 0.5 0.5 0.5 0.5 0.5 1.0 1.0 1.0 1.0 0.5 0.5 0.5 0.5
Actual 0.5 1.0 1.0 1.8
2 Cost Engineering Plan 0.3 0.5 1.0 0.5 0.5 0.5 0.5 1.0 1.0 0.5 0.5 0.5 0.5 0.5
Actual 0.3 0.5 1.0 0.8
3 Planning, Scheduling & Monitorin Plan 1.0 1.5 2.0 2.0 1.5 1.5 1.5 1.5 2.0 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.0 0.5 0.5
Actual 1.0 1.5 1.0 2.0 1.8
4 Quality Control & Assessment Plan 0.8 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Actual 0.5 0.8 1.0 0.5
5 Document Controller Plan 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Actual 1.0 1.0
6 Site Safety & Qa/Qc Officers Plan 1.0 1.0 1.5 1.5 2.5 2.5 2.5 4.5 4.5 4.5 3.5 3.5 2.5 2.5 1.5 1.0
Actual 1.0 1.0
7 Project Management & Engineering Cordination Plan 1.5 3.0 3.5 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0 3.0 3.0 3.0 2.5 2.5 1.5 1.5
Actual 1.5 3.0 3.0 4.5 5.0
8 Accounts & Administration Plan 1.0 1.0 1.0 1.0 1.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 2.0 2.0 1.0 1.0
Actual 1.0 1.0
Plan 2.5 5.3 7.8 11.5 9.5 11.0 10.0 11.0 15.5 14.0 16.5 15.5 15.0 13.0 14.0 10.0 10.0 5.5 5.0
Total (In-Direct Manpower)
Actual 2.5 5.8 6.3 12.5 12.8
Plan 2. 5 9.0 23.3 35. 0 54. 5 66.5 93. 0 102.5 144.0 129. 0 117 . 5 138.5 130. 5 125. 0 104.0 99.0 77. 0 49.5 22.0
GRAND TOTAL Actual 2.5 9. 8 17.3 37. 5 53. 8
Months- A-08 M-08 J-08 J-08 A 08 S-08 0 08 N-08 0 08 J-09 F-09 M·09 A 09 M·09 J-09 J-09 A 09 S· 09 O-09