Professional Documents
Culture Documents
Design of Drainage System
Design of Drainage System
4.1. General
The channel design may be divided into two categories by depending upon
whether the channel boundary is erodible or non-erodible. Lined channel is rigid
boundary channel or non-erodible channel and unlined channel is erodible or earthen
channel.
Since lined channel or non-erodible channel offers less resistance to flow than
unlined channel or erodible channel, the required channel size to convey a specified
flow rate at a selected slope is smaller for a lined channel than unlined channel.
Therefore, in some cases, a lined channel may be more economical than unlined
channel. Lined channel is used to reduce seepage, to increase discharge capacity and
to prevent erosion. The designer simply computes the dimension of the channel by the
uniform flow formula and then decides the final dimensions on the basis of hydraulic
efficient, of empirical rule of best section, practicability and economy. The factor to
be considered in the channel design are; the kind of material forming the channel
body which determines roughness coefficient, the minimum permissible velocity, to
avoid deposition if the water carries silt of debris, the channel bottom slope and side
slope, the freeboard and the most efficient section, either hydraulically or empirically
determined.
Lined channel can permit transmission of water at high velocity through areas
of deep or difficult excavation, reduce construction cost, decrease channel seepage,
reduce operation and maintenance costs and to ensure stability of the channel section.
In this study, brick lined is used for lateral channels and main channels. Types of
channel, based on shape are classified in circular, triangular, rectangular and
trapezoidal channel. In this study, rectangular channels are used for both lateral and
main channel. Estimating of the cost of the all
41
The following procedures are taken to determine the section dimensions for
lined channel.
1. Select a value of roughness coefficient n and bottom slope for the flow
surface.
2
3 nQ
AR =
2. Compute section factor from φ √S
3. Determine the channel dimensions and the flow depth.
4. Check that the minimum velocity is not less than the velocity that
required to carry the sediment to prevent silting.
5. Add a suitable amount of freeboard.
6. Make a sketch providing all the dimensions.
The existing topography is shown in Figure 4.1 in order to design the drainage system.
The main channels are described in green color and the lateral channels are described
42
in purple color separate. The total wastewater from this proposed area will be
discharged into the main drain and finally this wastewater will be discharged into
drainage channel below Koe Pay Bridge. The channel layout for study area is shown
in Figure 4.1.
43
The calculations of the discharge from the street for all lateral channels are
computed with above method.
Calculation results for estimated discharge flowing to all channels are as shown in
Table 4.1
C1 - 0.08355
C2 - 0.11325
C3 0.06452 0.01275
C4 0.02219 0.11875
C5 0.03261 0.14732
C6 - 0.08512
C7 0.01111 0.02310
C8 0.09067 0.17732
44
C9 0.02253 0.02162
C12 - 0.01462
C13 0.05346 -
C18 0.01568 -
Table 4.3. Calculation for Tentative Slope and Length of Lateral Channels
Surface Surface
Channel Elevation Elevation
Length of Upper of Lower Tentative Design
Channel Remark
Edge of Edge of Slope(S) Slope
(m)
Channel Channel
(m) (m)
Table 4.3(Continued)
C15R 213 85 79.77 0.02455 -
In this calculation, if the tentative slopes are around the acceptable values, the
actual bed slope is taken. If the bed slopes of lateral channels are too small, bed slopes
are increased than the actual values.
Table 4.4. Calculation for Tentative Slope and Length of Main Channels
Surface Surface
Elevation Elevation
Channel
of Upper of Lower Tentative Design
Channel Length Remark
Edge of Edge of Slope(S) Slope
(m)
Channel Channel
(m) (m)
In this study, the channels are designed by using Manning’s Formula. The
design channels are assumed as brick lined channels and the Manning’s roughness
coefficient is taken as 0.015. The minimum and maximum permissible velocities in
channel are taken as 0.61 m/sec and 2.4 m/sec respectively. The lateral channels are
designed of rectangular shape. The minimum freeboard is taken as 0.3m.
Calculations for C1R ,
For Flow Depth (y),
S = 0.005434
Q = 0.08357 m3/s
n = 0.015
∅ = 1
Q = AV
∅ 2
= A× ×R 3 × √ S
n
2 nQ
Section factor, AR 3 =
∅ √S
2 0.015× 0.08357
A R 3 =¿
1× √ 0.005434
= 0.01701
Flow depth, y = ?
A = by
= 0.5y
P = b+2y
= 0.5 + 2y
A
R =
P
48
0.5 y
=
0.5+2 y
y
=
1+ 4 y
2
AR 3 = 0.01701
2
y
0.5y × (
1+4 y ) 3
= 0.01701
y = 0.16m
For Area, A = by
= 0.5 × 0.16
= 0.08m 2
= 0.5 + 2× 0.16
= 0.82 m
A
For hydraulic radius, R =
P
0.08
=
0.82
= 0.097 m ≈ 0.1 m
∅ 2
For flow velocity, V = ×R 3 × √ S
n
1 2
× 0.005434
= 0.015 0.097 × √
3
= 0.16+0.3
= 0.46m