Technical Summary

Technical Summary (Part 1)

Technology name ES NET

Technological
Development 2010, JAPAN
Country
**Patent application
H22-2273842
number
Company / Persona Raito Kogyo co.,Ltd.
Kobelco Engineered Construction Materials Co.,Ltd /
Company
Raito Kogyo co.,Ltd.
Responsible
Technology Division, development section
Department
Technolo Person in Charge MASAKI Satoshi
gical 46 Marushima-cho, Amagasaki-shi, Hyogo, 660-0086
Developm Street Address JAPAN
ent Tel +81 6-6418-2731
Fax +81 6-6418-2732
E-mail s-masaki@shinkokenzai.co.jp
Contact information Web page http://www.shinkokenzai.co.jp
Company Raito Kogyo co.,Ltd.
Responsible
Overseas Business Division
Department
Person in Charge TANAKA Masahide

Sales Street Address 4-2-35, Kudan-kita, Chiyoda-ku, Tokyo, 102-8236 Japan

Tel +81 3-3265-2454


Fax +81 3-3265-3402
E-mail m-tanaka@raito.co.jp
Web page http://www.raito.co.jp
Type of physical disaster Earthquake / Heavy snow / Heavy rain
Classification
Details of physical disaster types Slope failure / rock fall

Concept and mechanism


1. What is the relevant feature of this technology?
・By installing soil nail on the slope at equal intervals, attaching pressure plates (ES plates) to them, connecting the
cables in a grid pattern and tightening the nuts of the soil nail, tension is generated in the cables and the interaction
between these causes It is a technology that prevents the collapse of the surface layer by integrating the ground and the
surface
2. Whatlayer
is theofconventional
the slope. technology supported by this technology?
・In the past, soil nail were installation on slopes at equal intervals, and concrete was sprayed onto them, and Concrete
grating crib method + soil nail method was used. All existing trees were cut down before construction because existing
trees would hinder the installation of Concrete grating crib work.

3.What are the public works projects to which this technology applies?
・Slope protection method

Effect of technology
・By changing the surface structure from a concrete grating crib to a cable wire, it is possible to construct an existing
trees without cutting it.
・No need to spray cement material, so no dust is generated.
・Since member assembly is easy and construction can be performed using general tools, no skilled workers requiring
special skills are required.
・The construction period can be shortened by about 30% to 40% compared to the conventional method. (Depending on
construction conditions)

JPY 22,000 - JPY 30,000


per Square meters
(USD 204 - USD 278)
Estimated unit cost
・Exchange rates are converted as of May 2020. ( USD 1.00 = JPY 108.00 )
・The unit price for construction will vary depending on the specifications of the soil nail
calculated by slope stability calculation.
Technical Summary (Part 2)
Technology name ES NET
Schematic drawings, Photographs

It is a construction method against surface collapse that combines soil nail and wire cable.
Slope reinforcement
mechanism

Conventional concrete material method ES NET method

Number of construction
※2011 to Sep 2017
results
XXXX (Country of origin) 35 works executed (public = 21 works, private = 14 works)
Central American area 0 work
0 work
Other
Technical Summary (Part 3)
Technology name ES NET
Summary of Design

START

Geotechnical condition
Confirmation of design and Groundwater conditions
construction conditions Constructing conditions
Assumption of slip surface

Calculation of slope stability Planned safety factor

Design
NO
Alternatives Examination of Required prevention force
method applicability Economical efficiency

YES

Slope stability calculation Arrangement interval


for soil nails Length
Specification

NO
designed

YES

Detailed plan Corrosion-resistant and Rust-proofed


consideration Soil nail head

END

The A net construction method is applicable to the following slopes for the purpose of
improving the stability of slopes.
1) Slope failure and collapse with relatively small required prevention force.
2) The slope is gentler than 63.3 degrees. ( 1 : 0.5 )

Detailed design information (web page URL, etc.)


Technical Summary (Part 4)
Technology name ES NET
Summary of cost estimation
The following is the structure (case example) of the direct construction cost of the ES NET method.

■ Per 400 m2 (in case of driling lightweight boring machine, for soil neil specification Dia22mm Length = 3,600mm)
Unit
Type of work Unit Quantity Amount Remark
price

Material LS 1.0 ¥5,721,819

Centering nos 121.0 ¥1,667 ¥201,707

Drilling nos 121.0 ¥21,755 ¥2,632,355

Soil Nail nos 121.0 ¥1,248 ¥151,008

Grouting m3 2.1 ¥119,562 ¥251,080

Wire rope installation m 1,659.8 ¥508 ¥843,178

Cross clip isntallation pcs 1,560.0 ¥206 ¥321,360

Combine Wire rope and Soil nail


nos 121.0 ¥1,159 ¥140,239
Torque tightening

Head treatment nos 121.0 ¥1,320 ¥159,720

¥
Total
10,422,466

per square ¥26,056 USD 241.30

Note
・Exchange rates are converted as of May 2020. ( USD 1.00 = JPY 108.00 )
・The specifications of the Soil nail are as follows.
Drilling dia 65mm, Thread deformed steel bar : Ggalvanized coating, Dia 22mm, Length 3,600mm
・It does not include scaffolding for drilling and loading and unloading of drilling machines.

Calculation details (web page URL, etc.)