Professional Documents
Culture Documents
Hydraulic Design of Hydropower Component: by Praveen Chaudhary
Hydraulic Design of Hydropower Component: by Praveen Chaudhary
Hydraulic Design of Hydropower Component: by Praveen Chaudhary
By Praveen Chaudhary
Hydro-Power Engineer
• Super Tamor HPP-155MW
• Likhu-1 HPP-77MW
• Loti Karnali HPP-50MW
• Bheri Babai Diversion Multipurpose Project-48MW
• Lower Chameliya HPP-30MW
• SuperMai HPP-7.8 MW
• Ghatte HPP-5MW
• Others
Hydraulic Design of Hydropower Component
Types of Hydropower
• ROR
• PROR
• Storage
• Pumped
Hydraulic Design of Hydropower Component
Overall Concept: Hydropower Development
Data Required:
Topographical Survey: Overall topography
Hydrological Investigations: low flow, mean monthly flow, Flood Flow, PMF/design Flood.
Sedimentological Investigations: Sediment data
Geological and Geotechnical Investigations: Geological and Geophysical parameters
Headworks Planning and Layout:
Barrage/Dam Structure
Dissipating structures
Fish ladder
Undersluice
Intake
Approach canal
Settling Basin/Gravel trap
Headpond
Hydraulic Design of Hydropower Component
Overall Concept: Hydropower Development
Headworks:
1. Weir/dam, intake, stilling basin, aprons and floodwalls should be designed to pass safely the maximum flood
of 1 in 100 years return period. Stability analysis should be done for 1 in 200 years return period flood.
2. Weir crest level or spillway crest level should be determined and fixed considering clearance required between
undersluice invert level and intake bottom sill level, height of intake opening and submergence requirement for
intake opening in order t avoid/minimize entry of trash into the intake, intake capacity should be about 130% of
the design discharge in case of conventional gravel trap and settling basin flushing systems while plant operates
at full load during flushing.
3.Carry out preliminary seepage analysis under the weir/dam foundation and other water retaining structures.
4. Sufficient freeboards should be provided for design flood between the design flood level and the operating
platforms and other necessary areas/structures.
5. Gravel trap should be designed to trap greater than 2-5 mm particles and gravel flushing system should be
designed to flush up to 200 mm particles.
Hydraulic Design of Hydropower Component
Headworks: 10MW<50MW……Contd…..
Headworks:
6.Under sluice structure of headworks should be designed to pass safely bed-load and flush sediment deposited
in front of the intake and to pass a portion of flood discharge. Either vertical sluice gates or radial gates should be
provided at under sluice with hydraulic or cable-drum type hoisting system.
7. A number of gates at undersluice should be made as per optimization and selected scope of the alternative
study.
8. A stilling basin should be designed for energy dissipation before releasing spillway flows back into the river.
Basin cross section, basin length and depth, apron elevation, side wall, minimum free board, drainage etc. should
be designed and described.
9. The clear spacing of the coarse trash rack in intake should be fixed considering the transport capacity of gravel
flushing conduit.
10. Settling basin should be designed for continuous supply of required design flow plus flushing discharge. The
trapping efficiency should be 90% or higher for particle size greater than 0.2 mm, depending on the available
head and mineral composition of sediments. Adequate justification should be provided, if smaller than 0.2 mm
particle size is selected to be settled in the settling basin. It is suggested to divide the settling basin into 2 or
more chambers.
11. Sediment handling, controlling and flow regulation mechanism should be defined in the project description.
12. An automatic/ungated spillway should be provided downstream of the settling basin at conveyance tank
wherever possible.
13. Sediment/gravel flushing outlets should be located at shooting flow areas of the stilling basin/river.
14. Design of fish ladder should be provided for the movement of the fish over the structures at the left or right
abutment of the gated weir or dam.
Hydraulic Design of Hydropower Component
Headworks: 50MW<100MW
Layout:
1. Select the shortest and most economical access road(s) alignment with minimum numbers of crossing
structures.
2. Detailed topographic maps and preliminary geological maps should be prepared for designing the project
configuration/layout.
3. Use updated hydrological data/analysis results for the design of project components. The design discharge
should be based on prevailing practices in the context of Nepal (e.g. 40-45 percentile flow/flow mentioned in
survey license).
Diversion During Construction:
1. A general plan to divert the river in dry season in order to carry out the construction works at weir and intake
sites should be prepared, which may require 2-4 dry seasons.
2. An upstream cofferdam should be designed in order to protect the working area at weir site. A cofferdam
should also be provided to prevent river entering in working area from downstream.
3. Design and drawing of temporary river diversion during construction should be prepared. The diversion
channel should be designed to pass 1:20 years return period dry season flood. If the headworks construction is
to be continued during monsoon season, at least 1 in 10 years return period flood should be used.
Hydraulic Design of Hydropower Component
Headworks: 50MW<100MW….Contd…
Headworks:
1. Weir/dam, intake, stilling basin, aprons and floodwalls should be designed to pass safely the maximum flood of
1 in 100 years return period. Stability analysis should be done for 1 in 200 years return period flood.
2. Weir crest level or spillway crest level should be determined and fixed considering clearance required between
undersluice invert level and intake bottom sill level, height of intake opening and submergence requirement for
intake opening in order t avoid/minimize entry of trash into the intake, intake capacity should be about 130% of
the design discharge in case of conventional gravel trap and settling basin flushing systems while plant operates
at full load during flushing.
3.Carry out preliminary seepage analysis under the weir/dam foundation and other water retaining structures.
4. Sufficient freeboards should be provided for design flood between the design flood level and the operating
platforms and other necessary areas/structures.
5. Gravel trap should be designed to trap greater than 2-5 mm particles and gravel flushing system should be
designed to flush up to 200 mm particles.
6. Settling basin should be designed for continuous supply of required design flow plus flushing discharge. The
trapping efficiency should be 90% or higher for particle size greater than 0.2 mm depending on available head
and mineral composition of sediments. Adequate justification should be provided, if smaller than 0.2 mm
particle size is selected to be settled in the settling basin. It is suggested to divide the settling basin into 2 or
more chambers.
7. Sediment handling, controlling and flow regulation mechanism should be defined in the project description.
8. An automatic/ungated spillway should be provided downstream of the settling basin at conveyance tank
wherever possible.
9. Sediment/gravel flushing outlets should be located at shooting flow areas of the stilling basin/river.
10. Design of fish ladder should be provided for the movement of the fish over the structures at the left or right
abutment of the gated weir or dam.
Hydraulic Design of Hydropower Component
Headworks: >100MW
Layout:
1. Design of temporary and permanent infrastructures such as camp facilities, construction power, access roads
(ropeways, bridges, tunnel), drinking water supply, etc. should be carried out.
2. Detailed topographic maps and preliminary geological maps should be prepared for designing the project
configuration/layout.
3. Use updated hydrological data/analysis results for the design of project components. The design discharge
should be based on prevailing practices in the context of Nepal (e.g. 40-45 percentile flow/flow mentioned in
survey license).
Diversion During Construction:
1. A general plan to divert the river in dry season in order to carry out the construction works at weir and intake
sites should be prepared, which may require 2-4 dry seasons.
2. An upstream cofferdam should be designed in order to protect the working area at weir site. A cofferdam
should also be provided to prevent river entering in working area from downstream.
3. Design and drawing of temporary river diversion during construction should be prepared. The diversion
channel should be designed to pass 1:20 years return period dry season flood. If the headworks construction is
to be continued during monsoon season, at least 1 in 10 years return period flood should be used.
Hydraulic Design of Hydropower Component
Headworks: >100MW….Contd…
Headworks:
1. Weir/dam, intake, stilling basin, aprons and floodwalls should be designed to pass safely the maximum flood of
1 in 200 years return period. Stability analysis should be done for 1 in 500 years return period flood.
2. Weir crest level or spillway crest level should be determined and fixed considering clearance required between
undersluice invert level and intake bottom sill level, height of intake opening and submergence requirement for
intake opening in order t avoid/minimize entry of trash into the intake, intake capacity should be about 130% of
the design discharge in case of conventional gravel trap and settling basin flushing systems while plant operates
at full load during flushing.
3.Carry out preliminary seepage analysis under the weir/dam foundation and other water retaining structures.
4. Sufficient freeboards should be provided for design flood between the design flood level and the operating
platforms and other necessary areas/structures.
5. Gravel trap should be designed to trap greater than 2-5 mm particles and gravel flushing system should be
designed to flush up to 200 mm particles.
6. Settling basin should be designed for continuous supply of required design flow plus flushing discharge. The
trapping efficiency should be 90% or higher for particle size greater than 0.2 mm depending on available head
and mineral composition of sediments. It is suggested to divide the settling basin into 2 or more chambers. For
high head projects, the settling basin should be designed for greater than 0.15 mm particles with 90% trapping
efficiency.
7. Sediment handling, controlling and flow regulation mechanism should be defined in the project description.
8. An automatic/ungated spillway should be provided downstream of the settling basin at conveyance tank
wherever possible.
9. Sediment/gravel flushing outlets should be located at shooting flow areas of the stilling basin/river.
10. Design of fish ladder should be provided for the movement of the fish over the structures at the left or right
abutment of the gated weir or dam.
Hydraulic Design of Hydropower Component
Other Codes:
IS Codes: Spillway, dam, intake…etc.
USBR Guidelines: Stilling basin, Dam Spillway… etc.
Books:
P. Novac (Hydraulic Structure)
Santosh Kumar Garg ( Irrigation Engineering and Hydraulic Structure)
Hydropower Masonyi Vol II (High Head Power Plant)
V.T. Chow
Hanif Choudhary..(open channel flow)
Hydraulic Design of Hydropower Component
Thank you!